Mui Ne tourist road upgrade project still has 5 cases that have not handed over the site

Duy Tuấn |

Lam Dong - Mui Ne Ward enforces land recovery for cases of non-compliance to hand over land for the Mui Ne tourist road upgrade project.

On July 16, the People's Committee of Mui Ne ward (Lam Dong province) organized forced land recovery for a case of not complying with the land recovery decision to implement the project to repair and upgrade Nguyen Dinh Chieu street and Huynh Thuc Khang street.

This is a key traffic infrastructure project on the Mui Ne tourist route, contributing to urban embellishment, improving the exploitation capacity of the coastal road and promoting tourism and socio-economic development of the locality.

Phó Chủ tịch UBND phường Mũi Né Trần Hải Anh đọc quyết định cưỡng chế thu hồi phần đất do bà P.T.H làm đại diện. Ảnh: Duy Tuấn
Vice Chairman of Mui Ne Ward People's Committee Tran Hai Anh reads the decision to enforce the recovery of the land represented by Ms. P.T. H. Photo: Duy Tuan

According to the decision of the Chairman of Mui Ne Ward People's Committee, the area to be coerced is 35.2m2 of perennial crop land, which is the land in front of the yard, represented by Ms. P.T. H.

Previously, the locality issued a decision to recover land, approved compensation and support plans and repeatedly propagated and mobilized land users to comply. However, households still did not hand over land according to regulations.

For this case, the total approved compensation and support costs are more than 13.5 million VND, including land compensation and crop support. The payment is made in accordance with the law.

According to the People's Committee of Mui Ne ward, as of July 16, the locality has mobilized 486/491 cases to receive compensation and hand over land, reaching nearly 99%. Only 5 cases have not agreed and must carry out land recovery coercion procedures according to regulations.

Dự án sửa chữa, nâng cấp đường Nguyễn Đình Chiểu - Huỳnh Thúc Kháng đang triển khai thi công. Ảnh: Duy Tuấn
The project to repair and upgrade Nguyen Dinh Chieu - Huynh Thuc Khang street is under construction. Photo: Duy Tuan

The project to repair and upgrade Nguyen Dinh Chieu street and Huynh Thuc Khang street has a length of nearly 4.9km, a roadbed width of 17m, with a total investment of more than 309 billion VND.

After completion, the road is expected to improve traffic capacity on the Mui Ne coastal axis, creating a spacious appearance for the tourist area and meeting the travel needs of people and tourists.

Mui Ne Ward People's Committee said it will continue to complete site clearance for the remaining cases to soon hand over clean ground to the construction unit, ensuring project implementation progress.

Duy Tuấn
RELATED NEWS

Ninh Binh accelerates site clearance for a bridge project worth over 800 billion VND to replace a pontoon bridge

|

Ninh Binh - The Ninh Cuong bridge construction project worth over 800 billion VND to replace the pontoon bridge is being accelerated in site clearance.

Site clearance for a 19km long drainage project outside Long Thanh airport

|

Dong Nai - The drainage project outside Long Thanh airport (phase 1) will complete site clearance in December 2026.

Dong Nai publicizes compensation plan for airport connecting road project

|

Dong Nai - The 25B road upgrade project, the section from the center of Nhon Trach ward to National Highway 51, has publicly announced the 12th phase of compensation, support, and resettlement plan.

VN-Index increases by 22 points thanks to Vingroup stocks

|

The stock market fell into a state of "green shell, red core", but VN-Index had a spectacular reversal.

Large stone slab rolls down the road, causing traffic congestion in Lai Chau

|

Lai Chau - Heavy rain causes many landslides, traffic on many roads is cut off.

It is expected to cut dozens of administrative procedures, saving nearly 190 billion VND

|

The draft Law and draft documents detailing the reduction of dozens of administrative procedures and business conditions; equivalent to a reduction of 904 days.

Russia claims to have shot down 375 UAVs of Ukraine

|

The Russian Ministry of Defense said that the country's air defense forces intercepted 375 Ukrainian unmanned aerial vehicles (UAVs) overnight.

First time submitting to the National Assembly the draft Law on Prevention and Combat of Mass Destructive Weapons

|

The Government for the first time submitted the draft Law on Prevention and Combat of the Proliferation of Weapons of Mass Destruction, consisting of 4 chapters and 37 articles.