10-lane road connecting Tay Ho with Son Tay is under construction
HỮU CHÁNH |
The 33km-long Tay Thang Long route, when completed, will play an important role in connecting and developing the western area of Hanoi.
According to the Master Plan for Hanoi Capital Construction to 2030 and Vision to 2050 approved by the Prime Minister, Tay Thang Long route is the main traffic axis connecting the West West Lake area and the North of Thang Long bridge with Son Tay Urban Area.
The project starts at the intersection with Vo Chi Cong Street (Ring Road 2); ends at National Highway 32, Son Tay town. Total route length is 33.18km (Tay Ho: 300m; Bac Tu Liem: 8.56km; Dan Phuong: 10km; Phuc Tho: 13.40km; Son Tay: 920m).
Up to now, 6.04km has been invested and completed according to the plan; 9.04km is under research project for construction investment; 18.1km has no investment research project.
Currently, 4 sections have been invested and completed according to the plan (6.04km): 1 section in Tay Ho district, 300m long; 2 sections in Bac Tu Liem district, 4.82km long; 1 section in Son Tay town, 920m long.
2 sections are being invested and implementing investment procedures (9.04km): 1 section in Bac Tu Liem district, 3.24km long (from Van Tien Dung to Pham Van Dong); 1 section in Dan Phuong district, 5.8km long (from Ring Road 3.5 to Dan Hoai canal).
3 sections of the route have no investment projects (18.1km): 1 section in Bac Tu Liem area with a length of 500m (underpass at different levels with Pham Van Dong street); 1 section in Dan Phuong district with a length of 4.2km (section from Dan Hoai canal to La Thach dike); in Phuc Tho district with a length of 13.4km.
According to the Hanoi People's Committee, the sections on Tay Thang Long Street, when completed, will form a vital and smooth axis connecting the West Lake area to Son Tay town, connecting inter-regional traffic.
These routes also connect with the city's planned roads to reduce the load on National Highway 32, facilitating people's travel as well as promoting the capital's socio-economic development.
The Tay Thang Long section from Vo Chi Cong Street to Pham Van Dong Street, about 2km long, has completed construction investment. In the photo is the starting point of the project, at the Vo Chi Cong intersection. Photo: Huu ChanhThe route has a cross-section of about 60m, accommodating 10 lanes. Photo: Huu ChanhThe section from Pham Van Dong to Van Tien Dung streets is under construction with a length of 3.2km, total investment of nearly 1,500 billion VND. Photo: Huu ChanhConstruction started in 2019 and was expected to be completed in 2021, but so far only about 50% of the work has been completed. Photo: Huu ChanhThe reason for the delay is due to many difficulties in site clearance. Bac Tu Liem District is focusing on removing obstacles, completing site clearance work soon, and speeding up the project's progress. Photo: Huu ChanhThe more than 3km long section from Van Tien Dung Street to the intersection of Ring Road 3.5 has been completed. Photo: Huu ChanhThe system of trees, lighting, median strips, and sidewalks on the route has been completed. Photo: Huu ChanhThe cross-section of the road is about 60m. Photo: Huu ChanhNotably, in the period of 2021 - 2025, Tay Thang Long road (from the intersection of Ring Road 3.5 to Dan Hoai canal road, Dan Phuong district) with a total investment of nearly 1,300 billion VND will be invested in construction. In the photo is the starting point of the project. Photo: Huu ChanhAccording to the plan, the route is about 5.8km long, with a cross-section width of 40-60.5m (urban main road type) and is an important and vital road south of the Red River to connect Tay Thang Long road with Ring Road 3.5 and Ring Road 4. Photo: Dan Phuong District People's CommitteeThere are currently 3 sections of the West Thang Long axis, about 18km long, that have not yet been invested in construction. As a key traffic project of the capital, the West Thang Long route, when completed, will play an important role in connecting and developing the western area of Hanoi. Photo: Huu Chanh
Hanoi - Ha Dong District plans to reclaim land from more than 300 households with a total area of about 30 hectares to widen National Highway 6 to 50-60m.
Hanoi - Construction started in 2019 and was expected to be completed after 2 years, but to date, the project to build Tay Thang Long road, more than 3km long and costing nearly 1,500 billion VND, is still unfinished.
Hanoi is focusing on clearing the ground to complete the second section and is about to invest in building the fourth section of the 33km-long Tay Thang Long axis road, connecting Tay Ho with Son Tay.
The Chairman of Son La Provincial People's Committee directly attended the scene, directing functional forces to rescue, rescue and overcome the consequences of the accident on National Highway 6.
Millions of views in less than half a day. At one point, more than 200,000 people watched a video game and still thought they were watching the U23 Vietnam - UAE match live.
With the goal to increase the score to 2-1 for U23 Vietnam in the match against U23 UAE, striker Dinh Bac scored 3 goals at the 2026 AFC U23 Championship Finals.
Hanoi - Ha Dong District plans to reclaim land from more than 300 households with a total area of about 30 hectares to widen National Highway 6 to 50-60m.
Hanoi - Construction started in 2019 and was expected to be completed after 2 years, but to date, the project to build Tay Thang Long road, more than 3km long and costing nearly 1,500 billion VND, is still unfinished.
Hanoi is focusing on clearing the ground to complete the second section and is about to invest in building the fourth section of the 33km-long Tay Thang Long axis road, connecting Tay Ho with Son Tay.