10-lane road connecting Tay Ho with Son Tay is under construction

HỮU CHÁNH |

The 33km-long Tay Thang Long route, when completed, will play an important role in connecting and developing the western area of ​​Hanoi.

According to the Master Plan for Hanoi Capital Construction to 2030 and Vision to 2050 approved by the Prime Minister, Tay Thang Long route is the main traffic axis connecting the West West Lake area and the North of Thang Long bridge with Son Tay Urban Area.

The project starts at the intersection with Vo Chi Cong Street (Ring Road 2); ends at National Highway 32, Son Tay town. Total route length is 33.18km (Tay Ho: 300m; Bac Tu Liem: 8.56km; Dan Phuong: 10km; Phuc Tho: 13.40km; Son Tay: 920m).

Up to now, 6.04km has been invested and completed according to the plan; 9.04km is under research project for construction investment; 18.1km has no investment research project.

Currently, 4 sections have been invested and completed according to the plan (6.04km): 1 section in Tay Ho district, 300m long; 2 sections in Bac Tu Liem district, 4.82km long; 1 section in Son Tay town, 920m long.

2 sections are being invested and implementing investment procedures (9.04km): 1 section in Bac Tu Liem district, 3.24km long (from Van Tien Dung to Pham Van Dong); 1 section in Dan Phuong district, 5.8km long (from Ring Road 3.5 to Dan Hoai canal).

3 sections of the route have no investment projects (18.1km): 1 section in Bac Tu Liem area with a length of 500m (underpass at different levels with Pham Van Dong street); 1 section in Dan Phuong district with a length of 4.2km (section from Dan Hoai canal to La Thach dike); in Phuc Tho district with a length of 13.4km.

According to the Hanoi People's Committee, the sections on Tay Thang Long Street, when completed, will form a vital and smooth axis connecting the West Lake area to Son Tay town, connecting inter-regional traffic.

These routes also connect with the city's planned roads to reduce the load on National Highway 32, facilitating people's travel as well as promoting the capital's socio-economic development.

 doan 1 tuyen duong Tay Thang Long tu duong Vo Chi Cong den Pham Van Dong voi chieu dai khoang 2km da hoan thanh dau tu xay dung.
The Tay Thang Long section from Vo Chi Cong Street to Pham Van Dong Street, about 2km long, has completed construction investment. In the photo is the starting point of the project, at the Vo Chi Cong intersection. Photo: Huu Chanh
a
The route has a cross-section of about 60m, accommodating 10 lanes. Photo: Huu Chanh
Doan 2 tu duong Pham Van Dong den Van Tien Dung dang trong qua trinh trien khai thi cong. Doan tuyen co chieu dai hon 3km, mat cat ngang 60m voi tong muc dau tu gan 1.500 ti dong.
The section from Pham Van Dong to Van Tien Dung streets is under construction with a length of 3.2km, total investment of nearly 1,500 billion VND. Photo: Huu Chanh
Cong trinh khoi cong tu nam 2019, du kien hoan thanh nam 2024 nhung den nay moi hoan thanh khoang 50% khoi luong cong viec.
Construction started in 2019 and was expected to be completed in 2021, but so far only about 50% of the work has been completed. Photo: Huu Chanh
Hien quan Bac Tu Liem dang tap trung thao go cac vuong mac, som hoan thanh cong tac giai phong mat bang, day nhanh tien do du an.
The reason for the delay is due to many difficulties in site clearance. Bac Tu Liem District is focusing on removing obstacles, completing site clearance work soon, and speeding up the project's progress. Photo: Huu Chanh
Voi doan 3 dai 3km tu duong Van Tien Dung den nut giao duong Vanh dai 3,5 da duoc thi cong hoan thien, dap ung 10 lan xe.
The more than 3km long section from Van Tien Dung Street to the intersection of Ring Road 3.5 has been completed. Photo: Huu Chanh
a
The system of trees, lighting, median strips, and sidewalks on the route has been completed. Photo: Huu Chanh
a
The cross-section of the road is about 60m. Photo: Huu Chanh
Dang chu y, trong giai doan 2021 - 2025, doan 4 tuyen duong Tay Thang Long (tu nut giao Vanh dai 3,5 den duong kenh Dan Hoai, huyen Dan Phuong) voi tong von dau tu gan 1.300 ti dong se duoc dau tu xay dung.
Notably, in the period of 2021 - 2025, Tay Thang Long road (from the intersection of Ring Road 3.5 to Dan Hoai canal road, Dan Phuong district) with a total investment of nearly 1,300 billion VND will be invested in construction. In the photo is the starting point of the project. Photo: Huu Chanh
Theo quy hoach, doan tuyen co chieu dai khoang 5,8km, quy mo mat cat ngang rong 40-60,5m (loai duong truc chinh do thi) la truc duong huyet mach va quan trong phia Nam song Hong nham ket noi duong Tay Thang Long voi duong Vanh dai 3,5 va duong Vanh dai 4.
According to the plan, the route is about 5.8km long, with a cross-section width of 40-60.5m (urban main road type) and is an important and vital road south of the Red River to connect Tay Thang Long road with Ring Road 3.5 and Ring Road 4. Photo: Dan Phuong District People's Committee
Doan tuyen con lai cua truc Tay Thang Long tu duong kenh Dan Hoai (Dan Phuong) den thi xa Son Tay dai khoang 20km chua duoc dau tu xay dung.
There are currently 3 sections of the West Thang Long axis, about 18km long, that have not yet been invested in construction. As a key traffic project of the capital, the West Thang Long route, when completed, will play an important role in connecting and developing the western area of ​​Hanoi. Photo: Huu Chanh
HỮU CHÁNH
TIN LIÊN QUAN

Hanoi plans to reclaim land from more than 300 households to open a 60m wide road

|

Hanoi - Ha Dong District plans to reclaim land from more than 300 households with a total area of ​​about 30 hectares to widen National Highway 6 to 50-60m.

5 years waiting for 10-lane road, capital of nearly 1,500 billion VND in Hanoi

|

Hanoi - Construction started in 2019 and was expected to be completed after 2 years, but to date, the project to build Tay Thang Long road, more than 3km long and costing nearly 1,500 billion VND, is still unfinished.

More good news about the road project connecting Tay Ho with Son Tay town

|

Hanoi is focusing on clearing the ground to complete the second section and is about to invest in building the fourth section of the 33km-long Tay Thang Long axis road, connecting Tay Ho with Son Tay.

Clarifying responsibility for issuing wrong red books on prison land

|

Lam Dong - Provincial inspectors determined that 4.29 hectares of land of Dai Binh Prison had been illegally granted red books by local authorities to 7 households.

Inadequate treatment of officials and workers

|

National Assembly delegates said that the treatment of officials and employees working at drug rehabilitation facilities is not commensurate with the requirements and tasks of the job.

Nam Dinh has a new Provincial Party Secretary

|

Nam Dinh - Mr. Dang Khanh Toan was mobilized and appointed by the Politburo to hold the position of Secretary of Nam Dinh Provincial Party Committee.

Go Cong sea dike "fluctuates" before monsoon season

|

Tien Giang - Some sections of the Go Cong sea dike are degraded, local authorities in Go Cong Dong district have proposed investing in wave-reducing dikes.

Sad news

|

Mr. Ignatius Do Van Luan, born in 1956, father of comrade Do Thi Yen Phuong, father-in-law of comrade Nguyen Van Quang - reporter of Lao Dong Newspaper working at the Representative Office in the Mekong Delta, passed away at 2:00 p.m. on November 13, 2024, October 13, Giap Thin year. He was 68 years old.

Hanoi plans to reclaim land from more than 300 households to open a 60m wide road

HỮU CHÁNH |

Hanoi - Ha Dong District plans to reclaim land from more than 300 households with a total area of ​​about 30 hectares to widen National Highway 6 to 50-60m.

5 years waiting for 10-lane road, capital of nearly 1,500 billion VND in Hanoi

HỮU CHÁNH |

Hanoi - Construction started in 2019 and was expected to be completed after 2 years, but to date, the project to build Tay Thang Long road, more than 3km long and costing nearly 1,500 billion VND, is still unfinished.

More good news about the road project connecting Tay Ho with Son Tay town

HỮU CHÁNH |

Hanoi is focusing on clearing the ground to complete the second section and is about to invest in building the fourth section of the 33km-long Tay Thang Long axis road, connecting Tay Ho with Son Tay.