The artery more than 21km is being expanded in Hanoi

HỮU CHÁNH |

Hanoi - The project of expanding Highway 6 is being constructed in Chuong My district, while the section through Ha Dong is being implemented ground clearance.

The project of upgrading and renovating Highway 6 (section of Ba La - Xuan Mai) was started at the end of 2022. The project has a total length of about 21.7 km (the section passing Ha Dong district is 5.92km long; the section passing Chuong My district is 15.87km long).

In Ha Dong district, the total land area of ​​the project is about 26.46 hectares, related to 1,146 households and individuals. The number of households plans to arrange resettlement is about 317 households.

Bien Giang ward area has 360 land plots; Yen Nghia ward 378 land plots; Dong Mai ward 266 land plots; Phu Lam ward 56 land plots and Phu La ward have 6 plots of land within the boundary, only land acquisition.

Quoc lo 6 doan qua quan Ha Dong (Ha Noi). Anh: Huu Chanh
Highway 6 section passing Ha Dong District (Hanoi). Photo: Huu Chanh

Up to now, the Management Board of Ha Dong District Construction Investment Project has coordinated with the People's Committees of wards with land with land withdrawal to complete the measurement work in the field; Working with the Hanoi Land Registration Office, People's Committees of wards with land were recovered to implement the project to unify the measurement dossier.

The Project Management Board has sent documents related to compensation policies to support and clear site to households with land with the recovered land and wards have organized the dissemination of compensation policies to support all organizations and individuals with land with the recovered land.

In order to accelerate the site clearance, the People's Committee of Ha Dong District said that it has directed the relevant wards and units to coordinate with the consulting unit to complete the measurement, sign the expected dossier in April 2025 and transfer the dossier to the district land registration office to appraise the technical dossier of the land parcel.

In Chuong My district, the locality has handed over the ground to the investor and the contractor with an area of ​​about 57.58ha, reaching 67.45% (public land and agricultural land) to implement the project construction.

According to the leader of the People's Committee of Chuong My District, this project in the area still has problems with the confirmation of the origin of the land, the application of the site clearance policy mechanism to transitional from the 2013 Land Law to the Land Law 2024.

In addition, within the scope of ground clearance, the project has underground infrastructure works must move and recover national defense land to change the purpose of use to serve the purpose of socio -economic development, tomb movement ...

The People's Committee of Chuong My District reported to the City People's Committee, departments and branches to ask for direction to remove obstacles and try to complete the site clearance in the first quarter of 2026.

Tai goi thau so 3 cua du an (doan tu Km22+220 - Km25+030) nha thau dang
In Package 3 - Project of expanding Highway 6 (paragraph from Km22+220 - Km25+030, Chuong My District), the contractor is focusing on machinery and construction manpower to ensure progress. According to the design, the posterior line section has a cross-section of 50-60m, 80km/h. Photo: Huu Chanh
Hien tai don vi da co ban hoan thanh lap dat hao ky thuat, cong thoat nuoc o phan mo rong va dang day nhanh thi cong san lap, lu nen…
Currently, the contractor has basically completed the installation of technical trenches, sewers at the extension and is accelerating construction, background ... Photo: Huu Chanh
O khu vuc cuoi cua goi thau so 3 (doan qua Khu Cong nghiep Phu Nghia), nha thau da rao chan de phuc vu thi cong cau Dong Tru.
At the end of the bidding package No. 3 (section passing Phu Nghia Industrial Park), the contractor fenced to serve the construction of Dong Tru bridge. Photo: Huu Chanh
Du kien dau tuan toi, nha thau se trien khai thi cong cau Dong Tru.
In addition to Dong Tru Bridge, on the route, there is also a sewer of Box (sewer) and six other bridges, including: Mai Linh, Tan Truong, Quan Lat, Xuan Mai, Bui River and Nam Lu. Photo: Huu Chanh
Cac cau kien be tong da duoc duc san de phuc vu thi cong cau Dong Tru.
The concrete components have been preferred to serve the construction of bronze bridges. Photo: Huu Chanh
Ky su tien hanh quan trac moi truong khu vuc trien khai thi cong cau
Engineers conducting environmental monitoring areas for construction of bridges. Photo: Huu Chanh
Mot doan duong mo rong cua goi thau so 3 da co ban hoan thanh.
A extended road of Package 3 (the previous section of Phu Nghia Industrial Park) has basically completed. Photo: Huu Chanh
Tai goi thau so 4 cua du an, nha thau dang thi cong phan nen…
At the project package No. 4 of the project, the contractor is constructing the background and sewer system on the side of the road. Photo: Huu Chanh
Nhieu doan cua du an van chua the trien khai do vuong mac giai phong mat bang.
Chuong My district strives to complete the ground clearance in the first quarter of 2026. The whole project is expected to be completed in 2027, helping to overcome congestion, synchronously connecting technical infrastructure, contributing to socio -economic development for Ha Dong District, Chuong My District in particular and Hanoi City in general. Photo: Huu Chanh
HỮU CHÁNH
TIN LIÊN QUAN

Hanoi is recovering land, starting the expansion of arterial sugar in June

|

Hanoi - The main road of more than 3km is expected to start construction in June 2025, after many years of land clearance problems.

Hanoi to build underpass worth nearly VND3,000 billion, upgrade arterial roads

|

Hanoi is about to implement the Hoang Quoc Viet - Pham Van Dong underpass construction project and the project to upgrade provincial road 427 through Thuong Tin, with a total capital of about VND 3,650 billion.

Ha Dong District reclaims land for 2 important routes

|

Hanoi - Ha Dong District is focusing on reclaiming land for site clearance to implement the project to build Ring Road 4 and expand National Highway 6 through the area.

Signing the Protocol on export of chili, passion fruit, bird's nest ... to China

|

The Ministry of Agriculture and Environment has signed the Protocol on the export of chili, passion fruit, bird's nest, rice bran to China, and agrees to cooperate in environmental protection and science.

The Mobile Police Command praised, honoring 80 advanced examples

|

Hanoi - Mobile Police Command (Ministry of Public Security) praised and honored 80 advanced individuals in the emulation movement "For national security".

A dairy business admits the advertisement, must apologize

|

While information about hundreds of fake milk brands were exposed, causing a stir in the public opinion, another dairy company had advertising behavior, had to apologize.

Construction broke water pipes, thousands of households lacking water

|

Nghe An - The process of expanding construction of National Highway 46, underground water pipeline broke, causing thousands of households in Kim Lien commune to fall into the situation of losing their daily life for many days.

Proposing notice of not executing death penalty to the person requested to extradite

|

The Draft Law on Conductors has just submitted to the Standing Committee of the National Assembly for the opinion on the notice of not executing the death penalty for the person requested to extradite.

Hanoi is recovering land, starting the expansion of arterial sugar in June

HỮU CHÁNH |

Hanoi - The main road of more than 3km is expected to start construction in June 2025, after many years of land clearance problems.

Hanoi to build underpass worth nearly VND3,000 billion, upgrade arterial roads

HỮU CHÁNH |

Hanoi is about to implement the Hoang Quoc Viet - Pham Van Dong underpass construction project and the project to upgrade provincial road 427 through Thuong Tin, with a total capital of about VND 3,650 billion.

Ha Dong District reclaims land for 2 important routes

HỮU CHÁNH |

Hanoi - Ha Dong District is focusing on reclaiming land for site clearance to implement the project to build Ring Road 4 and expand National Highway 6 through the area.