Ha Dong District reclaims land for 2 important routes

HỮU CHÁNH |

Hanoi - Ha Dong District is focusing on reclaiming land for site clearance to implement the project to build Ring Road 4 and expand National Highway 6 through the area.

The investment project to build the Ring Road 4 in the Capital Region, the section passing through Ha Dong District (Hanoi) is about 5.5km long, the total land area that needs to be cleared is about 68.16ha, located in 4 wards: Phu Lam, Phu Luong, Dong Mai and Yen Nghia.

Up to now, the People's Committee of Ha Dong district has appraised and approved the compensation and support plan for the 66.7ha of land of 1,665 organizations and households in the Ring Road 4 project implementation planning. The total approved amount is 778.05 billion VND, reaching 97.6% of the plan.

Along with approving the compensation and support plan for land, the People's Committee of Ha Dong district has also issued decisions approving the compensation and support plan for electricity, water, and telecommunications items with a total value of 78.12 billion VND. Of which, the electricity item is 29.69 billion VND; water is 33.8 billion VND; telecommunications is 14.63 billion VND.

Huong tuyen Vanh dai 4 doan qua dia ban quan Ha Dong. Anh: UBND quan Ha Dong
The route of Ring Road 4 through Ha Dong district. Photo: Ha Dong District People's Committee

Regarding the relocation of graves, Ha Dong district has relocated 1,578/1,583 graves and handled newly arising graves. Currently, there are 4 burial graves that have not been completed for 3 years and 1 newly arising ownerless grave waiting to be handled.

In the process of developing a compensation, support and resettlement plan according to the provisions of the 2024 Land Law (effective from August 1, 2024), Ha Dong district encountered a number of difficulties and problems related to determining land prices. The District People's Committee promptly reported to the authorities for resolution.

Currently, Ha Dong district continues to propagate and mobilize the remaining cases to promptly hand over the site for the project.

For cases of intentional non-receiving compensation and not handing over the site, the District People's Committee will draw up a record, issue a decision on enforcement and organize compulsory land recovery in accordance with legal regulations.

In addition to Ring Road 4, Ha Dong District is also implementing steps to reclaim land and clear land to implement the project to expand National Highway 6 through the area, with a length of nearly 6km.

According to the People's Committee of Ha Dong District, component project 1.1 - compensation, support and resettlement for site clearance has a total estimated investment of about VND 3,886 billion, capital from the city budget and the central budget.

The total land area to be recovered for the project is about 26.46 hectares, involving 1,146 households and individuals. The number of households expected to be resettled is about 317 households.

To carry out the site clearance for the project to upgrade and renovate National Highway 6 through Ha Dong district, up to now, the Ha Dong District Investment and Construction Project Management Board has coordinated with the People's Committees of wards with recovered land to complete the measurement work on site.

Accordingly, Bien Giang ward has 360 plots of land; Yen Nghia ward has 378 plots of land; Dong Mai ward has 266 plots of land; Phu Lam ward has 56 plots of land and Phu La ward has 6 plots of land within the boundary, limiting land acquisition.

Quoc lo 6 doan qua quan Ha Dong sap duoc mo rong. Anh: Huu Chanh
Ha Dong District will reclaim land from more than 1,100 households to expand National Highway 6. Photo: Huu Chanh

The Ha Dong District Construction Investment Project Management Board has worked with the Hanoi Land Registration Office and the People's Committees of wards whose land was recovered to implement the project to agree on the measurement records.

Along with that, the Project Management Board has sent documents related to compensation and support policies and site clearance to households whose land has been recovered and the wards have organized the dissemination of compensation and support policies for all organizations and individuals whose land has been recovered.

In order to accelerate the site clearance, the People's Committee of Ha Dong District said that in the coming time to continue directing the relevant wards and units to coordinate with the consulting unit to complete the measurement, sign the expected records in April 2025 and transfer the file to the branch of the Land Registration Office of the District Land Evaluation of Technical Dossiers of the Land Par parcel.

HỮU CHÁNH
TIN LIÊN QUAN

Completing the Ring Road 4 parallel road in October is impossible

|

Hanoi - The completion of the Ring Road 4 parallel road in October is impossible, because the site handover progress of localities is too slow.

Land reclamation for 1,146 households in Ha Dong to open a 60m wide arterial road

|

Hanoi - Ha Dong District plans to reclaim land from 1,146 households to construct the expansion of 6km of National Highway 6 through the area.

Accelerating the construction of Hanoi Ring Road 4, many sections have been revealed

|

Hanoi - The packages of the Ring Road 4 parallel road project are being accelerated to complete in 2025.

Chips prove the vibrant and substantial situation of Vietnam - China cooperation

|

45 cooperation documents are a telling number, demonstrating the vibrant, substantial, diverse, and increasingly close intertwined interest of Vietnam and China.

General Phan Van Giang works with the Standing Committee of Lang Son Provincial Party Committee

|

On the afternoon of April 16, General Phan Van Giang, Member of the Politburo, Minister of Defense had a meeting with the Standing Committee of Lang Son Provincial Party Committee.

Vingroup proposes to build a 121 km long Hanoi - Quang Ninh passenger railway

|

The Hanoi - Quang Ninh passenger railway project is proposed to be invested with a length of about 121 km and a maximum design speed of 300 km/h.

Expected pilot Procuracy sued civil case in 6 provinces and cities

|

The pilot of the People's Procuracy (VKSND) sued the civil case in 6 provinces and cities to protect the civil rights of the subjects that are vulnerable groups.

Gold price is peaked over 115 million VND/tael, people in Ho Chi Minh City still buy

|

Ho Chi Minh City - On April 16, the gold market in Ho Chi Minh City continued to witness the momentum, with SJC gold price reaching more than 115 million dong/tael.

Completing the Ring Road 4 parallel road in October is impossible

HỮU CHÁNH |

Hanoi - The completion of the Ring Road 4 parallel road in October is impossible, because the site handover progress of localities is too slow.

Land reclamation for 1,146 households in Ha Dong to open a 60m wide arterial road

HỮU CHÁNH |

Hanoi - Ha Dong District plans to reclaim land from 1,146 households to construct the expansion of 6km of National Highway 6 through the area.

Accelerating the construction of Hanoi Ring Road 4, many sections have been revealed

HỮU CHÁNH |

Hanoi - The packages of the Ring Road 4 parallel road project are being accelerated to complete in 2025.