Hanoi has 2 weeks left to hand over enough land to build Ring Road 4

HỮU CHÁNH |

Hanoi - Districts must complete site clearance for the Ring Road 4 project before April 15 according to the direction of the Chairman of the City People's Committee.

The investment project to build the Ring Road 4 of the Capital Region through Hanoi is about 58km long, passing through 7 districts including Soc Son, Me Linh, Dan Phuong, Hoai Duc, Ha Dong, Thanh Oai and Thuong Tin.

According to the report of the Hanoi Traffic Construction Investment Project Management Board, the city has so far received 776.97/785.42 hectares of land, equivalent to 48.36/52.73km, reaching 91.7%.

However, there are still many interruptions and bean sprouts along the route with a total length of more than 4.3km.

According to the Hanoi Traffic Construction Investment Project Management Board, the remaining site is located at locations for relocating floating underground works and some locations of residential land and garden land scattered in districts that are facing changes in compensation mechanisms and policies.

s
The residential area of Tan Chau village (Chu Phan commune, Me Linh, Hanoi) has not been cleared. Photo: Huu Chanh

According to Lao Dong in package No. 8, the construction of the parallel road of Ring Road 4 through Soc Son and Me Linh districts, while the 2 residential areas in Dai Thinh and Chu Phan communes (Me Linh district) have not yet been handed over the site for the project.

In package No. 9, the construction of Ring Road 4 through Dan Phuong and Hoai Duc districts is now stuck with 3 residential areas in Duc Thuong, Dong La communes (Hoai Duc) and Ha Mo commune (Dan Phuong).

"Currently, relevant units are relocating underground and above-ground technical infrastructure to hand over the site to the contractor. We do not know the date of handover of the site for the project's construction in 3 residential areas" - Mr. Nguyen Hoang Hai, Commander of Package 9 (contractor Vinaconex) shared with Lao Dong Newspaper reporter.

s
Some households in Ha Mo commune (Dan Phuong, Hanoi) within the construction area of Ring Road 4 have not yet handed over the site. Photo: Huu Chanh

In the area within the construction area of Hong Ha bridge in Hong Ha commune (Dan Phuong district) and Van Khe (Me Linh district), many households have not yet agreed to hand over the site for the project.

Similarly, some sections of the site in package No. 10, construction of parallel roads through Ha Dong district and Thanh Oai district; package No. 11, section through Thuong Tin district, has not been handed over to the contractor by the locality for construction.

The construction works are mainly residential areas, factories, underground and above-ground technical infrastructure.

s
The bridge project in Thuong Tin district cannot be constructed synchronously due to power lines. Photo: Huu Chanh

Regarding the site clearance for the Ring Road 4 project, Chairman of the Hanoi People's Committee Tran Sy Thanh recently requested districts to completely resolve the remaining land area that must be recovered and completed before April 15. According to Mr. Thanh, this is the last time, no later is allowed.

Thus, there are about 2 weeks left for districts to complete the site clearance for the Ring Road 4 project through Hanoi.

The Chairman of the City People's Committee also assigned Me Linh district to continue focusing on site clearance in the area to ensure completion on schedule as mentioned above.

In case a household has a proposal that is contrary to regulations, violates site clearance policies, intentionally complicates or opposes, or affects the progress of the investment project, consider applying administrative enforcement measures to reclaim land to ensure progress.

The Chairman of the Hanoi People's Committee assigned two Vice Chairmen, Mr. Duong Duc Tuan and Mr. Nguyen Trong Dong, to continue to direct and completely resolve difficulties and problems in Me Linh.

For Component Project 2.1 (construction of parallel roads), the Chairman of the Hanoi People's Committee assigned the Traffic Construction Investment Project Management Board to urge contractors to complete the project in October 2025, welcoming the City Party Congress.

HỮU CHÁNH
TIN LIÊN QUAN

River-crossing bridges and railways on Hanoi's Ring Road 4 take shape

|

Hanoi - The three river-crossing bridges and railway of the Ring Road 4 parallel road project through Me Linh district have been revealed and are under construction.

Hanoi reclaims land for Ring Road 1, accelerates progress of Ring Road 4

|

Hanoi is focusing on reclaiming land for the construction of Ring Road 1 from Hoang Cau to Voi Phuc, accelerating the completion of the Ring Road 4 parallel road in the fourth quarter of 2025.

Latest images of the Hanoi Ring Road 4 project

|

Hanoi - Contractors are speeding up the construction progress, bringing the Ring Road 4 parallel road project to the finish line in October 2025 under the direction of the Chairman of the City People's Committee.

A resident's house in Da Lat caught fire fiercely at night

|

Lam Dong - The fire broke out and burst fiercely at a house in Da Lat city. Those present tried to put out the fire, but failed.

Special notice on the funeral of comrade Khamtay Siphandone

|

Vietnam will hold a funeral for comrade Khamtay Siphandone according to the National Funeral Rites for 2 days, from April 4 to 5, 2025.

Restaurant fire in Hanoi

|

Hanoi - The fire that broke out at a restaurant in Nam Tu Liem district late in the afternoon of April 3, 2025 caused panic among people.

The death anniversary of Hung Vuong's great monk in Phu Tho is a grand festival

|

Phu Tho - The Hung Temple historical relic site is being decorated with many colors from the cultural funds of 13 districts, cities and towns in the area.

Lam Dong reforms to become an attractive destination for investors

|

Lam Dong - The locality is committed to strongly reforming administrative procedures, aiming to make the province an attractive destination for investors.

River-crossing bridges and railways on Hanoi's Ring Road 4 take shape

HỮU CHÁNH |

Hanoi - The three river-crossing bridges and railway of the Ring Road 4 parallel road project through Me Linh district have been revealed and are under construction.

Hanoi reclaims land for Ring Road 1, accelerates progress of Ring Road 4

HỮU CHÁNH |

Hanoi is focusing on reclaiming land for the construction of Ring Road 1 from Hoang Cau to Voi Phuc, accelerating the completion of the Ring Road 4 parallel road in the fourth quarter of 2025.

Latest images of the Hanoi Ring Road 4 project

HỮU CHÁNH |

Hanoi - Contractors are speeding up the construction progress, bringing the Ring Road 4 parallel road project to the finish line in October 2025 under the direction of the Chairman of the City People's Committee.