Latest images of the Hanoi Ring Road 4 project

HỮU CHÁNH |

Hanoi - Contractors are speeding up the construction progress, bringing the Ring Road 4 parallel road project to the finish line in October 2025 under the direction of the Chairman of the City People's Committee.

Present at the Ring Road 4 parallel road section through Thuong Tin district (Hanoi) on March 22, Lao Dong Newspaper reporters noted that the project has had many clear changes after 21 months since the groundbreaking date.

At the construction site, many machines, workers, and engineers are mobilized to construct project items, and there is almost no time for machine noise.

Package No. 11 (Component project 2.1, construction of the Hanoi Ring Road 4 parallel road) is undertaken by the joint venture of the contractor, Cienco4 Group Joint Stock Company - Hoang Long Construction and Trading Joint Stock Company - Song Hong Joint Stock Company. The total length of the route through Thuong Tin district is about more than 9km.

Vanh dai 4 doan qua huyen Thuong Tin da lo dien hinh hai sau hon 20 thang thi cong. Anh: Huu Chanh
The shape of the Ring Road 4 section through Thuong Tin district (Hanoi) has been revealed after about 21 months since the groundbreaking date. Photo: Huu Chanh
May moc, cong nhan thi cong hang muc tham nhua mat duong. Anh: Huu Chanh
Machinery and workers constructing asphalt pavement items. Photo: Huu Chanh

Mr. Tran Viet Son - Commander of Package 11 - contractor of Cienco 4 said that on the section where the contractor is responsible for construction, there are about 20 specialized locomotives, with nearly 40 workers working.

Currently, some locations are being treated with weak soil. About 1.3km is being paved with asphalt concrete.

According to Mr. Son, with the cleared site, basic progress is guaranteed. The locations of land clearance problems mainly concern power lines, underground and above-ground works. The city is currently implementing the relocation work, expected to be completed in March.

x
The bridge over To Lich River cannot be constructed synchronously due to problems with the power system. Photo: Huu Chanh

According to the contractor's representative, many sections within the project scope must have weak soil treatment, the minimum relocation time must be from 6-9 months. Meanwhile, the section across To Lich Bridge is still stuck with power lines, causing difficulties for the contractor.

According to the Hanoi Traffic Construction Investment Project Management Board, the city has so far approved and reclaimed 787.75/798.65 hectares, reaching 98.64%, with the remaining 10.9 hectares not yet cleared in Me Linh, Dan Phuong, Hoai Duc districts and Ha Dong district.

The city has received 776.97/785.42 hectares of land, equivalent to 48.36/52.73km, reaching 91.7%. However, there are still many interruptions and bean sprouts on the route (about 18 sections have not been handed over the site, about 4.38km long).

a
Ring Road 4 through Thuong Tin district is about 9km long. Photo: Huu Chanh

Regarding the progress of the implementation of component projects through Hanoi, after 21 months from the groundbreaking date, 4 construction packages of component project 2.1 - Construction of parallel roads (urban roads) have been simultaneously deployed by contractors on the area of land handed over, equivalent to 48.35/52.43km with 32 construction points (23 road points, 9 bridge points).

To date, the volume of roadbed sand filling is about 85.01%; roadbed filling is about 62.27%; crushed stone aggregate is about 35.04%.

Theo ke hoach, duong song hanh Vanh dai 4 se hoan thanh trong nam 2025. Anh: Huu Chanh
According to the plan, the Ring Road 4 parallel road will be completed in 2025. Photo: Huu Chanh

Regarding the Ring Road 4 project, Chairman of the City People's Committee Tran Sy Thanh recently requested the People's Committees of districts and towns to continue to focus on implementation and completely resolve the remaining land area that must be recovered and completed before April 15. This is the deadline, no later allowed.

Regarding the implementation of construction investment component projects, for component project 2.1 (parallel road construction), the City Traffic Construction Investment Project Management Board urges contractors to complete in October 2025, welcoming the City Party Congress.

HỮU CHÁNH
TIN LIÊN QUAN

Removing obstacles to site clearance for Tam Trinh road expansion project

|

Hanoi - Many policies beneficial to people subject to site clearance for the Tam Trinh road expansion project have been submitted to the city by the competent authorities for consideration.

Hanoi finalizes the start date of the Ring Road 4 expressway

|

Hanoi - The city requires the Traffic Construction Investment Project Management Board to ensure the progress of the Ring Road 4 expressway on the occasion of May 19.

Kim Dong - Giai Phong tunnel construction site on the eve of Tet

|

Construction started in October 2022, and the Kim Dong - Giai Phong underpass project has so far completed over 50% of its progress.

Many households in Buon Ma Thuot are upset because of continuous water outages

|

Dak Lak - Many areas in Buon Ma Thuot city are constantly cut off from water, causing people to lack clean water for daily activities during the dry season.

The army mobilizes and appoints 12 officers of Military Region 1

|

On the afternoon of March 31, the Standing Committee of the Party Committee of Military Region 1 held a conference to hand over decisions on the transfer and appointment of cadres from agencies and units in the Military Region.

Ms. Cao Thi Hoa An holds the position of Secretary of Phu Yen Provincial Party Committee

|

Phu Yen - On the afternoon of March 31, Phu Yen Provincial Party Committee held a Conference to implement the Politburo's Decision on personnel work.

Chairman of Ho Chi Minh City People's Committee assigns the task of investing in 7 metro lines

|

HCMC - The HCMC Urban Railway Management Board (MAUR) will be the investor of 7 metro lines from now until 2035.

The Ministry of Culture assigns the Radio and Television Department to investigate the ViruSs case

|

The incident between streamer ViruSs and rapper Phao, Ngoc kem, Emma Nhat Khanh... has received attention in recent days.

Removing obstacles to site clearance for Tam Trinh road expansion project

HỮU CHÁNH |

Hanoi - Many policies beneficial to people subject to site clearance for the Tam Trinh road expansion project have been submitted to the city by the competent authorities for consideration.

Hanoi finalizes the start date of the Ring Road 4 expressway

KHÁNH AN |

Hanoi - The city requires the Traffic Construction Investment Project Management Board to ensure the progress of the Ring Road 4 expressway on the occasion of May 19.

Kim Dong - Giai Phong tunnel construction site on the eve of Tet

NGỌC THÙY |

Construction started in October 2022, and the Kim Dong - Giai Phong underpass project has so far completed over 50% of its progress.