Two highly anticipated transport projects in Hanoi are nearing completion

HỮU CHÁNH |

Hanoi - Two important traffic projects in Long Bien and Nam Tu Liem are approaching the finish line, expected to be inaugurated on the occasion of the 70th anniversary of the Liberation of the Capital (October 10).

Nearly 6 years ago, in December 2018, Long Bien District (Hanoi) started the project to build a road connecting Nguyen Van Cu Street to the end of the resettlement area of ​​Ngoc Thuy Ward. The total investment of this project is about 1,200 billion VND.

Long Bien District is expected to complete a 1.5km long road with a 40m cross-section and 6 lanes by 2020.

However, the project could not be completed as originally planned due to difficulties in site clearance and many changes in policies.

a
The road connecting Nguyen Van Cu - Ngoc Thuy (Long Bien, Hanoi) is expected to be inaugurated on October 10. Photo: Huu Chanh

According to the Long Bien District Construction Investment Project Management Board (representing the investor), to implement the project, it is necessary to recover land from about 485 households, individuals and organizations, of which about 176 households will be resettled. To date, the site clearance work has been basically completed.

As of mid-September, the project has basically completed main items such as asphalt pavement, sidewalk paving, tree system, lighting...

Currently, the contractor is focusing on completing some items such as paving the sidewalk and asphalting the road surface at the end of the route (Ngoc Thuy intersection).

s
Workers are paving the remaining sidewalks. Photo: Huu Chanh
a
Hong Tien overpass - the highlight of the completed project. Photo: Huu Chanh

The highlight of the route is the steel overpass at the Hong Tien - Nguyen Van Cu intersection, which has basically completed all items. The project has a length and approach road of about 400m, designed with 2 lanes for motor vehicles and 2 lanes for mixed vehicles.

The project is expected to be inaugurated on the occasion of the 70th anniversary of the Capital Liberation Day (October 10), creating a smooth route from Dong Tru Bridge through Thuong Thanh, Ngoc Thuy, Ngoc Lam, Bo De, Long Bien, and Thach Ban wards connecting to the Hanoi - Hai Phong expressway.

a
The road cross-section is 40m wide with 6 lanes. At the intersection, it is expanded to 7 lanes. Photo: Huu Chanh

10km away, the Le Quang Dao extended road construction project will also be completed and technically opened to traffic on October 10.

The project is about 2.6km long, starting at the intersection with Thang Long Avenue, Nam Tu Liem district, and ending at Duong Noi urban area, Ha Dong district.

The project has a total investment of more than 700 billion VND, of which construction costs are more than 408 billion VND.

q
The Le Quang Dao extended road has completed over 80% of the work. Photo: Huu Chanh

According to the design, the route will have inter-regional road standards, a cross-section of 40m with 6 lanes, and a design speed of 60 km/h. The section connecting to Thang Long Avenue (about 110m long) will have a cross-section width of 100m.

The representative of the investor, the Nam Tu Liem District Construction Investment Project Management Board, said that to implement the Le Quang Dao extended road project, about 11.86 hectares must be reclaimed. Currently, the problem of site clearance has been resolved.

a
A nearly 1km long section of the route has basically completed all items. Photo: Huu Chanh

Currently, the intersection with Thang Long Avenue to Dai Linh Street (Nam Tu Liem, Hanoi) nearly 1km long has basically completed the main items.

This road section is paved with stone sidewalks, asphalt pavement, trees, lighting system and fire fighting water supply system.

Meanwhile, the remaining section from Dai Linh Street to the end of the route is under construction, waiting for connection.

a
Workers are constructing the remaining section to complete it on schedule. Photo: Huu Chanh

To complete the project on October 10, the investor is currently directing the contractor to mobilize maximum machinery, workers, and engineers to work in 3 shifts continuously to ensure the project's progress.

The route, when completed, is expected to help shorten travel time between Nam Tu Liem and Ha Dong districts, reducing traffic pressure on many routes in the area.

HỮU CHÁNH
TIN LIÊN QUAN

Trên công trường đường rộng 120-180m đang thi công ở Hà Nội

HỮU CHÁNH |

Dự án đường nối cao tốc Hà Nội - Hòa Bình đang triển khai thi công các hạng mục cầu vượt đường quy hoạch, thuộc địa bàn xã Tiến Xuân, Thạch Thất, Hà Nội.

Đường cửa ngõ Hà Nội sắp được mở rộng gấp 5, vốn 2.300 tỉ đồng

HỮU CHÁNH |

Hà Nội - Đường cửa ngõ phía Nam thường xuyên ùn tắc đang được nghiên cứu mở rộng gấp 5 lần, vốn đầu tư 2.300 tỉ đồng.

Đường 1.300 tỉ ở Hà Nội đạt 95% khối lượng rồi "đắp chiếu"

HỮU CHÁNH |

Hà Nội - Đạt 95% khối lượng và nhận đủ mặt bằng thi công song đoạn vành đai 2,1km, vốn 1.300 tỉ đồng vẫn chưa hẹn ngày về đích.

Sửa Luật Công đoàn phải phù hợp với thể chế chính trị

Bảo Hân - Hải Nguyễn |

Chiều 8.10, Tổng Liên đoàn Lao động Việt Nam tổ chức tham vấn ý kiến các đồng chí nguyên lãnh đạo Tổng Liên đoàn về dự thảo Luật Công đoàn (sửa đổi).

Lật xe khách ở Nghệ An, 2 người phụ nữ tử vong

QUANG ĐẠI |

Nghệ An - Đang lưu thông trên Quốc lộ 7C, xe khách mất lái lao xuống ruộng làm 2 người tử vong.

Sinh viên "tố" phải ăn cơm thừa canh cặn, ĐH Bách khoa Hà Nội nói gì?

Tường Vân |

Phó Giám đốc Đại học Bách khoa Hà Nội khẳng định, việc cho sinh viên ăn canh thừa là không thể chấp nhận và kiên quyết sẽ xử lí, khắc phục tình trạng trên.

Bò thả rông, rượt nhau giữa đường phố ở Đà Nẵng

Trần Thi |

Dù đã được kiến nghị nhiều năm nay nhưng tình trạng bò thả rông tại một số tuyến đường ở TP Đà Nẵng vẫn xảy ra, gây nguy hiểm cho người tham gia giao thông.

Em họ Trương Mỹ Lan giúp chị gái chiếm đoạt hơn 26.000 tỉ

Tâm Tú |

TPHCM - Trong phần tranh luận tại phiên tòa ngày 8.10, em họ Trương Mỹ Lan - Trương Vincent Kinh hối hận khi giúp sức chị gái chiếm đoạt hơn 26.000 tỉ đồng.

Trên công trường đường rộng 120-180m đang thi công ở Hà Nội

HỮU CHÁNH |

Dự án đường nối cao tốc Hà Nội - Hòa Bình đang triển khai thi công các hạng mục cầu vượt đường quy hoạch, thuộc địa bàn xã Tiến Xuân, Thạch Thất, Hà Nội.

Đường cửa ngõ Hà Nội sắp được mở rộng gấp 5, vốn 2.300 tỉ đồng

HỮU CHÁNH |

Hà Nội - Đường cửa ngõ phía Nam thường xuyên ùn tắc đang được nghiên cứu mở rộng gấp 5 lần, vốn đầu tư 2.300 tỉ đồng.

Đường 1.300 tỉ ở Hà Nội đạt 95% khối lượng rồi "đắp chiếu"

HỮU CHÁNH |

Hà Nội - Đạt 95% khối lượng và nhận đủ mặt bằng thi công song đoạn vành đai 2,1km, vốn 1.300 tỉ đồng vẫn chưa hẹn ngày về đích.