Underpass under railway in Hanoi under construction in new phase

HỮU CHÁNH |

Two years since the groundbreaking ceremony, the Hanoi underground railway tunnel project has reached 50% progress and is entering a new phase of construction.

Present at the Kim Dong - Giai Phong underpass construction site (Hoang Mai district, Hanoi) in early November 2024, Lao Dong reporters recorded dozens of workers busy constructing the closed and open tunnel areas in the direction of Kim Dong - Giai Phong street.

Mr. Ho Duc Phuc - Director of Kim Dong Tunnel Management Board - said that after 2 years of construction, the project has completed 50% of the volume according to schedule. In which, the Dam Hong tunnel has basically completed the access road, open tunnel, and tunnel structure.

"Taking advantage of favorable weather, the contractor increased workers, engineers, and machinery to focus on the new construction phase in Kim Dong, speeding up the project's progress," said Mr. Phuc.

Mr. Phuc added that Kim Dong currently has no problems with the ground. However, to open the tunnel, the 35kV power line in the railway needs to be removed before the temporary bridge and rails can be deployed to serve the main structure of the tunnel.

However, the investor, the Hanoi Traffic Construction Investment Project Management Board, has yet to relocate or hand over the site to the project. Meanwhile, Dam Hong is stuck with a house and two transformer stations.

"The contractor hopes that the problems will be resolved soon so that construction can be carried out simultaneously across the entire project," said Mr. Phuc.

The Kim Dong - Giai Phong underpass construction project started in October 2022 with a scale of 4 lanes. The project has a total investment of 778 billion VND, expected to be completed after 3 years.

When completed, the underpass will help overcome traffic congestion between Ring Road 2.5 and Giai Phong Street, gradually completing the Ring Road 2.5 route according to the approved plan, ensuring smooth traffic through Giap Bat freight station.

Sau 2 nam tu ngay khoi cong, du an ham chui Kim Dong - Giai Phong da hoan thanh 50% khoi luong da. Nhieu hang muc quan trong cua du an da lo dien hinh hai. Anh: Huu Chanh
After 2 years since the groundbreaking, the Kim Dong - Giai Phong tunnel project (Hoang Mai district, Hanoi) has completed 50% of the volume. Many important items of the project have been revealed. Photo: Huu Chanh
a
The Dam Hong underpass has basically completed the access road, open tunnel, and tunnel structure. Photo: Huu Chanh
a
However, there is still a house here and 2 transformer stations have not been relocated. Photo: Huu Chanh
a
Currently, the contractor is focusing on personnel and machinery to construct the underpass on Kim Dong Street. Photo: Huu Chanh
Cac hang muc thi cong ham chinh dang duoc nha thau tich cuc trien khai. Tren cong truong hang tram cong nhan cung may moc thi cong nhieu mui cung luc.
The contractor is actively implementing the main tunnel construction items. At the construction site, workers and machines are working on many projects at the same time. Photo: Huu Chanh
Phia duong Kim Dong cac cong nhan dang thi cong lap dat ket cau thep be than de thuc hien do betong. Anh: Huu Chanh
On Kim Dong Street, workers are installing the steel structure of the body to pour concrete. Photo: Huu Chanh
thoi diem nay dang la duong gang cua du an nen cong nhan duoc huy dong ve cong truong thi cong dong hon, 3 ca lien tuc, lam ca ngay lan dem.
This is the critical time of the project, so more workers are mobilized to the construction site, 3 shifts continuously, working day and night. Photo: Huu Chanh
Trong anh cong nhan dang thuc hien thi cong cac dot ham ho phia Kim Dong.
In the photo, workers are constructing open tunnel segments on the Kim Dong side. Photo: Huu Chanh
Nha thau dao ham thi cong cac hang muc chinh cua du an.
Tunneling contractors are constructing the main items of the project. Photo: Huu Chanh
Thoi gian toi, khi duong dien 35kV trong duong sat duoc di doi, nha thau se trien khai hang muc cau tam, duong ray phuc vu cho cong tac vao hang muc ket cau chinh cua ham. Anh: Huu Chanh
In the coming time, when the 35kV power line in the railway is relocated, the contractor will deploy temporary bridge and rail works to serve the main structure of the tunnel. Photo: Huu Chanh
Viec rao chan de thi cong ham chui khien giao thong qua day gap nhieu kho khan. Anh: Huu Chanh
The fencing to construct the underpass has caused many difficulties for traffic passing through here. Photo: Huu Chanh
Dong phuong tien co di chuyen cham chut qua nut giao Kim Dong - Giai Phong. Anh: Huu Chanh
Traffic congestion at Kim Dong - Giai Phong intersection. Photo: Huu Chanh
a
According to the plan, the Kim Dong - Giai Phong underpass will be completed in 2025. This is the 5th underpass in the capital built since 2009, after the Kim Lien - Xa Dan, Trung Hoa, Thanh Xuan, and Le Van Luong underpasses. Photo: Huu Chanh
HỮU CHÁNH
TIN LIÊN QUAN

Gold price update morning 11/5: Gold rings continue to decline

|

Gold price update morning 11/5: Domestic gold price continues to decline. World gold price recovers slightly.

Ms. Nguyen Hai Tram is the Standing Deputy Secretary of Tien Giang Provincial Party Committee

|

Tien Giang - Ms. Nguyen Hai Tram was mobilized and appointed to join the Executive Committee, Standing Committee of the Provincial Party Committee and hold the position of Permanent Deputy Secretary of the Tien Giang Provincial Party Committee.

Transfer high-risk invoice list to police

|

The tax authority will continue to coordinate in providing the list of taxpayers with high risks regarding invoices to the police.

US election poll causes shock before G hour

|

One of the most shocking US election polls that took place before the G hour of the US presidential election was in the state of Iowa.

Dump truck crashes into multiple cars waiting at red light, killing 1 person

|

Binh Duong - In Tan Uyen city, a dump truck accident just occurred, causing one person to die on the spot and many vehicles to be damaged.

Colonel Nguyen Huu Phuoc appointed Director of Khanh Hoa Provincial Police

|

Colonel Nguyen Huu Phuoc - Deputy Director of Phu Tho Provincial Police was appointed by the Ministry of Public Security as Director of Khanh Hoa Provincial Police.

Cuối năm 2024, Hà Nội khởi công hầm chui gần 750 tỉ đồng

HỮU CHÁNH |

Hà Nội dự kiến khởi công hầm chui nút giao Cổ Linh - cầu Vĩnh Tuy, vốn đầu tư gần 750 tỉ đồng vào cuối năm 2024.

Hai vị trí sắp xây hầm chui tổng vốn 3.200 tỉ đồng ở Hà Nội

HỮU CHÁNH |

Nút giao Đại lộ Thăng Long - Vành đai 3,5 và nút giao Cổ Linh - đường dẫn cầu Vĩnh Tuy sắp được Hà Nội chi 3.200 tỉ đồng xây hầm chui giúp giảm tải ùn tắc.

Hà Nội sắp xây dựng 2 hầm chui, vốn đầu tư 3.200 tỉ đồng

HỮU CHÁNH |

Dự án hầm chui Cổ Linh và Vành đai 3,5 sắp được Hà Nội đầu tư xây dựng giúp giảm tải ùn tắc, tăng tính kết nối, góp phần phát triển kinh tế - xã hội Thủ đô.