Lam Dong - After the Prime Minister directed the inspection and handling of the erosion on the Vinh Hao - Phan Thiet expressway, the Ministry of Construction has issued a new report.

The Ministry of Construction has just issued a document reporting to the Prime Minister on the situation of overcoming the incident caused by heavy rain on the Vinh Hao - Phan Thiet expressway.

According to the Ministry of Construction, the Vinh Hao - Phan Thiet expressway, over 100km long, has been accepted by the State Inspection Council for construction acceptance.

Mot doan cao toc Vinh Hao - Phan Thiet. Anh: Duy Tuan
A section of Vinh Hao - Phan Thiet Expressway. Photo: Duy Tuan

The project was completed and put into operation and use on June 10, 2024; is under warranty, the warranty period is 24 months.

Recently, the weather in Lam Dong province has been complicated, with continuous heavy rain. This has affected traffic safety and construction safety on the expressway.

In particular, at locations Km213+750 (right of the route); Km213+850 (right of the route); Km215+300 (right of the route); Km215+620 (right of the route), erosion of the slope has occurred at the above locations.

Khac phuc cac vi tri xoi lo, ho ham ech tren doan km213 cao toc Vinh Hao - Phan Thiet. Anh: Pham Duy
Authorities are repairing eroded and frog jaw openings on the section km213 of the Vinh Hao - Phan Thiet Expressway. Photo: Pham Duy

Immediately after being affected by prolonged heavy rain, the Ministry of Construction directed Project Management Board 7 (investor) and relevant agencies and units to organize a site inspection to urgently repair the damage.

The Ministry also directed the Vietnam Road Administration (the agency managing and operating the expressway) to deploy initial warning, diversion and remedial measures (clearing sand and soil, temporarily reinforcing the roadbed), ensuring traffic safety and preventing damage from spreading.

"In the coming time, the Ministry will continue to direct relevant agencies and units to carry out the responsibility of project warranty with solutions to ensure long-term stability.

At the same time, review the entire project to promptly detect locations at risk of being affected by storms and floods to find solutions to ensure the project is exploited safely and smoothly," the Ministry of Construction affirmed.

Previously, Lao Dong newspaper reported landslides on slopes and openings on the edge of the ground at some locations on the Vinh Hao - Phan Thiet expressway.

After that, Project Management Board 7 and the route management unit temporarily reinforced and calculated a long-term plan.

Duy Tuấn
RELATED NEWS

Completed repair of erosion on the edge of the road on the Vinh Hao - Phan Thiet Expressway

|

Lam Dong - The concrete edge of the water barrier that was blocked and removed is believed to be the cause of erosion on the road edge on the Vinh Hao - Phan Thiet Expressway and has now been repaired.

Temporarily reinforcing the erosion location on the Vinh Hao - Phan Thiet expressway after Lao Dong Newspaper's reflection

|

Lam Dong - The route management unit has sent workers to temporarily reinforce the eroded location on the Vinh Hao - Phan Thiet expressway immediately after the reflection of Lao Dong Newspaper.

Vinh Hao - Phan Thiet Expressway faces difficulties due to site clearance problems

|

Lam Dong - items related to the Vinh Hao - Phan Thiet expressway are facing problems with site clearance, affecting progress.

200m long mountain crack in Quang Ngai, people urgently evacuated

|

Quang Ngai - The crack appeared on the top of the hill in Dak Plo commune, directly threatening 12 households with more than 54 people. The authorities urgently evacuated the people.

Lai Li Huang wins the 2025 World Chess Championship in China

|

Chess player Lai Ly Huynh surprised everyone when he won the individual standard chess championship at the 2025 World Chess Championship.

Lantern street in Ho Chi Minh City is bustling before the Mid-Autumn Festival

|

Luong Nhu Hoc lantern street in Ho Chi Minh City attracts many visitors nearby during the Mid-Autumn Festival.

Voters in Ho Chi Minh City propose answering whether or not to continue the 10,000 billion VND flood prevention project

|

HCMC - The nearly VND10,000 billion flood prevention project will complete the two large culverts of Ben Nghe and Muong Chuoi first, then put all six culverts into operation in 2026.

Pollution after the landfill burst in Quang Ngai, people are left empty-handed, worried about falling back into poverty

|

Quang Ngai - The waste holes were broken, causing environmental pollution and heavy economic damage to many households in the area.

Completed repair of erosion on the edge of the road on the Vinh Hao - Phan Thiet Expressway

Duy Tuấn |

Lam Dong - The concrete edge of the water barrier that was blocked and removed is believed to be the cause of erosion on the road edge on the Vinh Hao - Phan Thiet Expressway and has now been repaired.

Temporarily reinforcing the erosion location on the Vinh Hao - Phan Thiet expressway after Lao Dong Newspaper's reflection

Duy Tuấn |

Lam Dong - The route management unit has sent workers to temporarily reinforce the eroded location on the Vinh Hao - Phan Thiet expressway immediately after the reflection of Lao Dong Newspaper.

Vinh Hao - Phan Thiet Expressway faces difficulties due to site clearance problems

Duy Tuấn |

Lam Dong - items related to the Vinh Hao - Phan Thiet expressway are facing problems with site clearance, affecting progress.