Vinh Hao - Phan Thiet Expressway faces difficulties due to site clearance problems

Duy Tuấn |

Lam Dong - items related to the Vinh Hao - Phan Thiet expressway are facing problems with site clearance, affecting progress.

On September 10, Mr. Pham Quoc Huy - Executive Director of the Vinh Hao - Phan Thiet Expressway Project, Deputy Director of Project Management Board 7 (Ministry of Construction) said that he had sent a petition to Lam Dong Provincial People's Committee to propose resolving the existing problems and problems related to site clearance for the Vinh Hao - Phan Thiet Expressway items.

According to Mr. Huy, after the Vinh Hao - Phan Thiet expressway was put into operation, the units continued to construct items to best serve people and vehicles traveling on the route such as: Rest stops and Traffic monitoring and operation system - ITS.

Cao toc Vinh Hao - Phan Thiet doan nut giao Ma Lam. Anh: Duy Tuan
Vinh Hao - Phan Thiet Expressway at Ma Lam intersection. Photo: Duy Tuan

The Vinh Hao - Phan Thiet Expressway plans 2 locations as rest stops at Km205+092 and Km144+560. The rest stop at Km205+092 is under construction.

At Km144+560, the locality has only handed over a part of the site of about 1.67/10.86 ha, the remaining area cannot determine the time to hand over the site for construction. Due to the small, un continuous site, the contractor has not been able to carry out the construction.

Similarly, the traffic turning road item under the Traffic Management Monitoring System at Cho Lau, Dai Ninh, and Ma Lam intersections has not yet been handed over. The reason is that local authorities do not accept deposit applications, waiting for specific instructions.

This puts the construction progress at risk of being delayed compared to the requirements for putting the project into operation by the end of 2025.

Tram dung nghi dang thi cong tai Km205+092. Anh: Duy Tuan
The rest stop is under construction at Km205+092. Photo: Duy Tuan

Regarding site clearance capital, the total allocated capital is 113.4 billion VND. However, up to now, only 8.82 billion VND has been disbursed, the remaining amount must be disbursed before the end of 2025, and the capital cannot be extended to the following year.

The settlement of site clearance capital has not yet been completed. Some items have not completed the procedures for submission, while the Ministry of Construction requires completion by September 2025 at the latest.

To ensure progress, Project Management Board 7 requested Lam Dong Provincial People's Committee to direct relevant departments, branches and localities to focus on removing obstacles.

With the Km144+560 rest stop, it is necessary to promptly resolve the dispute, and at the same time mobilize people to hand over at least 2 hectares of land continuously in September to promptly deploy essential items.

Cac nhan vien thi cong day cap cho He thong giam sat dieu hanh giao thong tren cao toc. Anh: Duy Tuan
Staff constructing cables for the Expressway Traffic Control Monitoring System. Photo: Duy Tuan

For locations of the road turning around vehicles, Project Management Board 7 recommends that departments and branches have clear instructions for the commune to coordinate in reclaiming land, mobilizing people to agree, ensuring the completion of construction in October 2025 and putting it into operation by the end of the year.

With site clearance capital, the local Board requested to speed up the disbursement progress this year. Otherwise, the locality will have to balance and allocate capital to pay for unfinished and undisbursed work contents

The Vinh Hao - Phan Thiet Expressway is more than 100 km long through Lam Dong province, opened to traffic from May 2023, and is a section of the North - South Expressway in the East. The route has 4 lanes, with a maximum speed of 90 km/h.

Duy Tuấn
RELATED NEWS

More landslides, sand, overflow onto Vinh Hao - Phan Thiet Expressway

|

Lam Dong - Heavy rain, rocks and soil from above collapsed again, overflowing onto the Vinh Hao - Phan Thiet expressway, about 300m from the landslide on September 2.

Proposal to install surveillance cameras and invest in the emergency lane of Vinh Hao - Phan Thiet expressway

|

Lam Dong proposed installing surveillance cameras and investing in an emergency lane after a particularly serious accident on the Vinh Hao - Phan Thiet highway that killed 3 people.

The shape of 2 rest stops on the Vinh Hao - Phan Thiet Expressway is revealed

|

Lam Dong - The items of gas station, parking lot, service house... at the km205 rest stop on the Vinh Hao - Phan Thiet expressway are gradually taking shape.

Organizing a ceremony to commemorate the one-year anniversary of the death of 67 victims of Lang Nu

|

Lao Cai - On September 10, local authorities and people held a memorial service for the victims of Lang Nu village who died due to storm No. 3 (Yagi).

Criticizing the Hai Phong Department of Construction after the incident of passengers being refused to board a ferry to leave the island

|

Hai Phong - Permanent Vice Chairman of the City People's Committee Le Anh Quan has just directed to overcome the operating situation at Dong Bai - Cai Vieng ferry terminal.

iPhone 17 Air, 17 Pro criticized for being expensive when launched

|

The newly launched iPhone 17 series did not receive many positive reviews, as Apple has not yet made improvements to AI, while the prices of some models are higher than previous years.

Protecting businesses from fake news and false information in the digital environment

|

Vingroup Corporation's civil lawsuit, reporting to the authorities and sending documents to the Embassies about 68 domestic and foreign organizations and individuals reporting false information about the corporation on the Internet is considered a timely act in self-defense and protection of the legitimate rights of enterprises. This incident also shows the need to increase the responsibility of management agencies and social media users in the context of Vietnam having many solutions to unblock the driving force for private economic development - becoming the most important driving force of the national economy in the spirit of Resolution 68 on private economic development.

online scams in Cambodia, Myanmar defraud tens of billions of USD of Americans

|

The US has sanctioned a series of online scams in Cambodia and Myanmar for appropriating tens of billions of dollars from the American people in 2024 alone.

More landslides, sand, overflow onto Vinh Hao - Phan Thiet Expressway

Duy Tuấn |

Lam Dong - Heavy rain, rocks and soil from above collapsed again, overflowing onto the Vinh Hao - Phan Thiet expressway, about 300m from the landslide on September 2.

Proposal to install surveillance cameras and invest in the emergency lane of Vinh Hao - Phan Thiet expressway

Duy Tuấn |

Lam Dong proposed installing surveillance cameras and investing in an emergency lane after a particularly serious accident on the Vinh Hao - Phan Thiet highway that killed 3 people.

The shape of 2 rest stops on the Vinh Hao - Phan Thiet Expressway is revealed

Duy Tuấn |

Lam Dong - The items of gas station, parking lot, service house... at the km205 rest stop on the Vinh Hao - Phan Thiet expressway are gradually taking shape.