Soc Trang speeds up river sand exploitation, considering the option of using sea sand for the expressway

PHƯƠNG ANH |

Soc Trang - The province is urgently exploiting river sand, and at the same time implementing procedures to use sea sand for the expressway section through Soc Trang province.

Increasing mining capacity

Recorded at the MS01 sand mine on the Hau River, in the territory of Phong Nam and An Lac Tay communes (Ke Sach district, Soc Trang province), the exploitation activities took place very urgently. Here, there are 2 trawlers and dozens of transport ships lining up to enter and exit the mine. This sand mine is exploited by Cuu Long Concrete Joint Stock Company, supplying materials for packages 9 and 10 of the Chau Doc - Can Tho - Soc Trang Expressway Component 4 Project (Component Project 4).

Currently, the exploitation capacity at MS01 mine has been increased to 4,000 m3/day, more than 2 times higher than the original capacity. As of mid-April 2025, the mine has exploited 1.182 million m3 of sand and it is expected that this figure will continue to increase to 715,000 m3 in June.

Nguoi dan giam sat khai thac cat tai mo cat MS01. Anh: Phuong Anh
People monitor sand mining at MS01 sand mine to serve the construction of the expressway project through Soc Trang province. Photo: Phuong Anh

According to Mr. Thach Minh Hoai - Director of Project Management Board 2, investor of Component Project 4 - as of April 17, the total volume of sand from mines in the province that has been exploited and supplied to the Project has reached about 1.182 million m3. It is expected that by June 2025, the volume will reach 3.3/6.6 million m3.

To reduce pressure on river sand mines in Soc Trang, Project Management Board 2 has also recommended that relevant units consider transferring the volume of river sand from specific mines in An Giang and Dong Thap provinces (assigned to the North-South Expressway Project in the East) to Component Project 4 after the other projects complete the sand casting work.

To date, Component Project 4 has reached 30.1% of the contract value, with the progress of the packages ranging from 24.15% - 40.9%.

Using sea sand for highways

According to Project Management Board 2, to solve the remaining shortage of 3.3 million m3, Soc Trang province has considered the option of using sea sand from sub-areas B1.4 and B1.5. Currently, the People's Committee of Soc Trang province has issued a confirmation for the B1.4 sea sand mine and the contractor has submitted documents to the Ministry of Agriculture and Environment to assign the sea area.

The leaders of Project Management Board 2 also informed that - through reviewing and surveying the salinity along the route, there are only about 3.2 km of the end of the route (total volume of filled sand is about 283,000 m3) through shrimp ponds, with suitable conditions to use sea sand (according to Instruction document No. 9156/BTNMT-MT dated December 26, 2024 of the Ministry of Natural Resources and Environment).

Due to urgent needs, the contractor of Construction Corporation No. 1 used river sand to fill the foundation of this section with a volume of about 180,000 m3. With the remaining demand for sea sand at suitable locations being about 100,000 m3 (3.2 km at the end of the section bordering Nam Song Hau National Highway), other sections have unsuitable natural conditions due to being sweet areas for growing water rice and fruit trees.

The Government Office has just issued Notice No. 203/TB-VPCP conclusions of the Prime Minister Pham Minh Chinh on a business trip and working with ministries and localities on the situation of investment in developing transport infrastructure in the Mekong Delta area. In terms of materials, the Prime Minister requested investors (including the People's Committee of Soc Trang Province) to actively review and decide according to its competence for the pilot use of sea sand as materials to build background according to the guidance of the Ministry of Construction and the Ministry of Agriculture and the Environment to reduce the pressure of river sand.

The Prime Minister agreed on the principle of the transfer of materials granted according to a specific mechanism that is still reserved but no longer needs to exploit and transfer sand volume after unloading from the project to apply a specific mechanism to another project (applying specific mechanism) to continue exploiting and using to reduce administrative procedures, accelerate the implementation of projects; Special attention, interest does not cause negative, corruption, group interests.

Based on the guidance of the Ministry of Construction, the Ministry of Agriculture and Environment, the People's Committee of Soc Trang province proactively exploits and supplying sea sand for the project according to its competence, and actively works with localities with leveling of leveling materials (sand, stone) to supply the project, not to the project as slow as the past time.

PHƯƠNG ANH
TIN LIÊN QUAN

practical training model at key expressway construction sites

|

The practical training model right at the construction site of the Dong Dang (Lang Son) - Tra Linh (Cao Bang) and Huu Nghi - Chi Lang (Lang Son) projects is opening a new training method focusing on "rectionality", meeting the human resource needs to serve the increasingly high workload in key projects.

Construction of Quy Nhon - Pleiku Expressway, Gia Lai contributes 500 billion VND

|

Gia Lai - In addition to the central capital, the province has allocated an additional 500 billion VND from the local budget to participate in investing in the Quy Nhon - Pleiku expressway project.

Hot weather does not hinder the progress of the Can Tho - Ca Mau expressway

|

Overcoming the heat, engineers and workers constructing the Can Tho - Ca Mau expressway are making continuous efforts to complete the key project on schedule.

Hanoi streets are brilliant with flags celebrating the 30th of April

|

On the occasion of the 50th anniversary of the Liberation of the South and National Reunification Day, from big streets to small alleys in Hanoi, all decorated with national flags, banners, posters, etc.

President granted amnesty to 8,055 prisoners serving prison sentences

|

The President has decided to grant amnesty to 8,055 prisoners serving prison sentences and 1 person whose prison sentence has been temporarily suspended.

The story of the cabinet of Duong Van Minh on April 30, 1975

|

Mr. Nguyen Khac Nhu, who arrested President Duong Van Minh's cabinet with his teammates, recounted the historic moment in the Golden Eagle Palace at noon on April 30, 1975 .

President of the Vietnam General Confederation of Labor attends the launching ceremony of Workers' Month in Phu Tho

|

Phu Tho - President of the Vietnam General Confederation of Labor (VGCL) attended the launching ceremony of Workers' Month at Lam Thao Phosphate and Chemical Suppe Company.

Hanoi spends more than VND5,000 billion to build a road connecting Tu Lien bridge

|

Hanoi - The road connecting Tu Lien bridge (from the intersection of Tu Lien bridge approach road with Truong Sa road to Hanoi - Thai Nguyen expressway) has a total investment of VND 5,076 billion.

practical training model at key expressway construction sites

Bích Liên |

The practical training model right at the construction site of the Dong Dang (Lang Son) - Tra Linh (Cao Bang) and Huu Nghi - Chi Lang (Lang Son) projects is opening a new training method focusing on "rectionality", meeting the human resource needs to serve the increasingly high workload in key projects.

Construction of Quy Nhon - Pleiku Expressway, Gia Lai contributes 500 billion VND

THANH TUẤN |

Gia Lai - In addition to the central capital, the province has allocated an additional 500 billion VND from the local budget to participate in investing in the Quy Nhon - Pleiku expressway project.

Hot weather does not hinder the progress of the Can Tho - Ca Mau expressway

Tạ Quang |

Overcoming the heat, engineers and workers constructing the Can Tho - Ca Mau expressway are making continuous efforts to complete the key project on schedule.