Land reclamation for 1,146 households in Ha Dong to open a 60m wide arterial road

HỮU CHÁNH |

Hanoi - Ha Dong District plans to reclaim land from 1,146 households to construct the expansion of 6km of National Highway 6 through the area.

The project to upgrade and renovate National Highway 6 (Ba La - Xuan Mai section) was approved by the Hanoi People's Committee in Decision No. 969/QD-UBND dated March 18, 2022.

The project started construction at the end of 2022 with a total length of about 21.7km (the section through Ha Dong district is 5.92km long; the section through Chuong My district is 15.87km long).

According to the design, the route is 50-60m wide, with a design speed of 80km/h. On the route, there is a box culvert (Tuan culvert) and seven bridges including: Mai Linh, Dong Tru, Tan Truong, Quan Lat, Xuan Mai, Song Bui and Nam Lu.

The project has four main intersections, including intersections of different levels (where two or more roads intersect at different elevations) with National Highway 21A, the North-South axis road and Ring Road 4.

The People's Committee of Ha Dong District is the investor of component project 1.1 on compensation, support and resettlement for site clearance of the project, with a preliminary total estimated investment of about VND 3,886 billion; capital from the city budget and the central budget.

The total land area to be recovered for the project is about 26.46 hectares, involving 1,146 households and individuals. The number of households expected to be resettled is about 317 households.

To carry out the site clearance for the project to upgrade and renovate National Highway 6 through Ha Dong district, up to now, the Ha Dong District Investment and Construction Project Management Board has coordinated with the People's Committees of wards with recovered land to complete the measurement work on site.

Accordingly, Bien Giang ward has 360 plots of land; Yen Nghia ward has 378 plots of land; Dong Mai ward has 266 plots of land; Phu Lam ward has 56 plots of land and Phu La ward has 6 plots of land within the boundary, limiting land acquisition.

Quoc lo 6 doan qua quan Ha Dong, Ha Noi. Anh: Huu Chanh
National Highway 6 section through Ha Dong district, Hanoi. Photo: Huu Chanh

The Ha Dong District Construction Investment Project Management Board has worked with the Hanoi Land Registration Office and the People's Committees of wards whose land was recovered to implement the project to agree on the measurement records.

Along with that, the Management Board has sent documents related to compensation and support policies and site clearance to households whose land has been recovered and the wards have organized the dissemination of compensation and support policies for all organizations and individuals whose land has been recovered.

In order to accelerate the site clearance, the People's Committee of Ha Dong District said that the next time will continue to direct the relevant wards and units to coordinate with the consulting unit to complete the measurement, sign the expected dossier in April 2025 and transfer the file to the district land registration office to appraise the technical dossier of the land parcel.

In Chuong My district, by the end of 2024, the locality has handed over the site to the investor and contractor with an area of about 57.58 hectares, reaching 67.45% (public land and agricultural land) to implement the project.

For the remaining area, Chuong My district strives to complete site clearance in the first quarter of 2026.

The National Highway 6 expansion project is expected to be completed in 2027, hoping to overcome congestion, synchronously connect technical infrastructure, and contribute to the socio-economic development of Ha Dong district, Chuong My district in particular and Hanoi city in general.

HỮU CHÁNH
TIN LIÊN QUAN

A trillion-dong project under construction for more than a decade

|

Hanoi Many apartment buildings in Ha Dong district have been under construction for more than a decade, causing waste of resources and public outrage.

Image of the 6-lane road about to open to traffic connecting 2 districts of Hanoi

|

Hanoi - The road is more than 2.5km long, meeting 6 lanes, and is completing the final items, preparing to technically open to traffic after 27 months of construction.

Hanoi reclaims land from more than 300 households to build 2 roads 30-93.3m wide

|

Hanoi will reclaim land from 316 households and organize the construction of two important transport projects in Hoang Mai and Tay Ho districts.

The former Vice Chairman of the People's Committee of Ba Ria - Vung Tau province becomes the new Deputy Secretary of the Ho Chi Minh City Party Committee

|

HCMC - Mr. Dang Minh Thong - Vice Chairman of the People's Committee of Ba Ria - Vung Tau province (old) was appointed to the position of Deputy Secretary of the new Ho Chi Minh City Party Committee.

Robots support people in completing administrative procedures on the first day of the operation of the two-level government in Ho Chi Minh City

|

HCMC - On the first day of operating the two-level government model, the Thu Duc Ward Public Administration Service Center made an impression when using robots to serve people.

The Ministry of Finance requests clarification on the case of cutting down trees, what did Secretary Ayun Pa say?

|

Gia Lai - The Secretary of Ayun Pa Ward affirmed that he will require agencies and units to strictly manage public assets, especially urban trees.

Just need... 2.5 points for 3 subjects passed in public grade 10

|

Dak Lak - At the end of the 10th grade entrance exam, many high schools in the area have very low benchmark scores. Some schools only consider admission scores as 2.5 points.

How to handle new administrative procedures of the largest ward in Hanoi

|

Hanoi - From July 1, the two-level local government will officially operate. Recorded in Hong Ha ward, people were able to handle administrative procedures quickly.

A trillion-dong project under construction for more than a decade

Minh Hạnh |

Hanoi Many apartment buildings in Ha Dong district have been under construction for more than a decade, causing waste of resources and public outrage.

Image of the 6-lane road about to open to traffic connecting 2 districts of Hanoi

HỮU CHÁNH |

Hanoi - The road is more than 2.5km long, meeting 6 lanes, and is completing the final items, preparing to technically open to traffic after 27 months of construction.

Hanoi reclaims land from more than 300 households to build 2 roads 30-93.3m wide

HỮU CHÁNH |

Hanoi will reclaim land from 316 households and organize the construction of two important transport projects in Hoang Mai and Tay Ho districts.