HCMC expands 2- expressway access road to 8 lanes to eliminate traffic jams

MINH QUÂN |

Ho Chi Minh City is preparing to start expanding the approach routes of the two expressways Ho Chi Minh City - Long Thanh - Dau Giay and Ho Chi Minh City - Trung Luong to 8 lanes.

Double expansion of Ho Chi Minh City - Long Thanh Expressway

The 55km long Ho Chi Minh City - Long Thanh - Dau Giay Expressway, including 4 lanes, has been put into operation since 2016 with a total investment of more than VND 20,600 billion.

However, after nearly a decade of use, the traffic volume on this route has increased by an average of 10.45%/year, causing the section from An Phu intersection to Bien Hoa - Vung Tau expressway intersection to exceed 25% of its capacity, causing serious congestion.

According to the Ho Chi Minh City Department of Transport, to solve this situation, the expressway expansion project is divided into two sections.

Section 1 (from An Phu intersection to Ring Road 2, 3.2km long) implemented by Ho Chi Minh City, was approved by the Ho Chi Minh City People's Council in July 2024.

This expressway will be expanded from 4 to 8 lanes, while expanding Muong Kenh bridge and Do Xuan Hop overpass.

With a total capital of nearly 1,000 billion VND from the Ho Chi Minh City budget, the project is expected to start construction in September 2025 and be completed in 2027.

Duong dan cao toc TPHCM - Long Thanh thuong xuyen un tac. Anh: Anh Tu
The Ho Chi Minh City - Long Thanh Expressway is often congested. Photo: Anh Tu

Section 2 (from Ring Road 2 to Bien Hoa - Vung Tau Expressway, about 22km long) will be implemented by the Ministry of Construction with a total capital of about VND15,000 billion.

In particular, the section from Ring Road 2 to Ring Road 3 will be upgraded to 8 lanes; the section from Ring Road 3 to Bien Hoa - Vung Tau intersection will be expanded to 10 lanes.

To speed up progress, the Ministry of Construction has proposed that the Prime Minister assign this ministry as the investor to shorten the implementation time and complete related procedures.

If approved, the project will start construction in the third quarter of 2025 and be basically completed in December 2026.

2,350 billion VND to expand the Ho Chi Minh City - Trung Luong expressway

The Ho Chi Minh City - Trung Luong - My Thuan Expressway expansion project was approved for investment in February 2025.

The project will be implemented under the public-private partnership (PPP) method, expected to start construction in the second quarter of 2025 and be completed in 2028.

The total length of the expanded route is about 98km, divided into two parts. The Ho Chi Minh City - Trung Luong Expressway will be upgraded to 8 lanes, with 2 additional emergency lanes.

The Trung Luong - My Thuan Expressway, including My Thuan 2 Bridge, will be expanded to 6 lanes and 2 emergency lanes.

Ket xe duong dan cao toc TPHCM - Trung Luong qua TPHCM.  Anh: Chan Phuc
Traffic congestion on the Ho Chi Minh City - Trung Luong Expressway through Ho Chi Minh City. Photo: Chan Phuc

To synchronize with this expressway, the Ho Chi Minh City Department of Transport said that the city will expand two branches of the approach roads: Binh Thuan - Cho Dem 9.5km long) and Tan Tao - Cho Dem 3.7km long.

Both of these routes will meet the scale of 6 lanes for motor vehicles and 2 mixed lanes. Three overpasses on Tran Dai Nghia, Tran Van Giau and Bui Thanh Khiet streets will also be built.

The total investment of the project is about 2,350 billion VND from the Ho Chi Minh City budget.

Currently, the Ho Chi Minh City Department of Transport has been assigned the task of preparing for investment, expected to submit to the Ho Chi Minh City People's Council for approval and start construction in 2025, to be completed in 2028.

MINH QUÂN
TIN LIÊN QUAN

HCMC is about to start construction of a 60m wide road connecting Binh Duong

|

HCMC - The road connecting Go Dua intersection to Ho Chi Minh City - Chon Thanh Expressway, 1.65km long and 60m wide, will be approved for investment in April, starting construction in the first quarter of 2026.

HCMC completes and starts construction of a series of large projects in 2025

|

Ho Chi Minh City completes An Phu intersection, Tran Quoc Hoan - Cong Hoa connecting road, Tham Luong canal and starts construction of Saigon River pedestrian bridge, Ring Road 2, Nguyen Khoi bridge...

The Eastern Artery Road of Ho Chi Minh City has not been expanded for 15 years

|

HCMC - After 15 years of implementation, the project to expand Hanoi Highway and National Highway 1 - the eastern gateway route of HCMC is still unfinished due to land clearance problems for 176 households.

Binh Duong General Hospital informs about the delay in handing over the body

|

HCMC - On July 14, Binh Duong General Hospital clearly informed the process and explained the delay in handing over the body of the patient who died before arriving at the hospital.

Husband goes to work far away, is stunned when he hears the news of his wife and children dying at home due to landslides

|

Lao Cai - While the mother and child in Xuan Ai commune were sleeping, the hill behind the house collapsed, mud collapsed, killing the two victims.

The difficulty of Vietnamese broadcasters when buying the copyright for the 2026 World Cup

|

In addition to the high copyright price for the 2026 World Cup broadcast, Vietnamese broadcasters are also facing the problem of "smuggling" that has not been completely handled.

Innovation in thinking, improving the effectiveness of internal political security protection

|

On July 13 and 14, in Hanoi, the Party Committee of the Department of Internal Political Security (ANCTNB), Ministry of Public Security held the 2nd Congress, term 2025-2030. Senior General Pham The Tung, member of the Standing Committee of the Central Public Security Party Committee, Deputy Minister of Public Security attended and directed the congress.

The case of dozens of workers being owed wages in Dien Bien, businesses continue to promise

|

Dien Bien - The case of dozens of workers being owed wages, the enterprise promised to repay the debt in July. Previously, this enterprise committed to repay the debt before June 30 and then broke the promise.

HCMC is about to start construction of a 60m wide road connecting Binh Duong

MINH QUÂN |

HCMC - The road connecting Go Dua intersection to Ho Chi Minh City - Chon Thanh Expressway, 1.65km long and 60m wide, will be approved for investment in April, starting construction in the first quarter of 2026.

HCMC completes and starts construction of a series of large projects in 2025

MINH QUÂN |

Ho Chi Minh City completes An Phu intersection, Tran Quoc Hoan - Cong Hoa connecting road, Tham Luong canal and starts construction of Saigon River pedestrian bridge, Ring Road 2, Nguyen Khoi bridge...

The Eastern Artery Road of Ho Chi Minh City has not been expanded for 15 years

MINH QUÂN |

HCMC - After 15 years of implementation, the project to expand Hanoi Highway and National Highway 1 - the eastern gateway route of HCMC is still unfinished due to land clearance problems for 176 households.