On January 13, Binh Duong Electronic Information Portal reported that the People's Committee of Binh Duong province issued a decision to internally adjust the 2024 public investment plan for 16 projects.
Of which, 11 projects were adjusted down by 562 billion VND. Component project 1 of site clearance for Ho Chi Minh City Ring Road 4 from Thu Bien Bridge to Saigon River had the largest capital reduction, 500 billion VND.
At the same time, the investment capital in 5 projects was adjusted to increase by 562 billion VND, including: the project to upgrade DT 746 road from Go bridge to Hieu Liem ferry, increased by 37 billion VND;
Project to upgrade and expand DT 748 road from Phu Thu intersection to My Phuoc town's Northern beltway, increased by 464 billion VND;
The Bung Biep - Suoi Cat drainage project was adjusted to increase by 51 billion VND; the project to dredge and reinforce Cai stream from Tho Ut bridge to Dong Nai river increased by 5.5 billion VND;
Nguyen Tri Phuong road project from Tho Ngu bridge to Thay Nang bridge, adjusted to increase by 4.6 billion VND.
Internal adjustment of public investment plans for 16 projects is one of the solutions to accelerate the disbursement of public investment capital. Thereby, projects with the ability to attract capital have more resources to accelerate construction progress and completion.
In recent days, leaders of Binh Duong Provincial People's Committee have inspected and surveyed to urge the progress of public investment projects in the area.
50 days and nights of capital disbursement competition
On November 12, the People's Committee of Binh Duong province held a meeting to deploy the 50-day and night peak plan to compete in disbursing the public investment capital plan in 2024.
The plan aims to highly concentrate and mobilize maximum resources to implement tasks and solutions to promote disbursement of public investment capital in the remaining time of 2024; speed up progress and complete key projects of the province...
Strive to achieve 100% of the disbursement rate of the public investment plan of the whole province by December 31, 2024, of which the disbursement rate of key projects without problems must reach over 80%.