The two villages of Phang Cu and Hang Chua, Sang Nhe commune, are residential areas of nearly 150 households (over 700 people - mainly ethnic minorities) who still do not have grid electricity.
According to the design, the project has an investment scale including a 35kV medium-voltage power line about 4 km long, building 48 power pole positions, 2 transformer stations; along with a 4.4 km long low-voltage power line system with nearly 200 electricity meters, ensuring safe and stable access to the national grid to each household.
Representative of the sponsoring and construction unit, Mr. Pham Van Quynh - AIT Company said that the unit has mobilized manpower and machinery, deploying leveling from January 6, determined to complete the project on schedule, ensuring quality and safety with the forces.
The project will be completed and "powered" before February 3, 2026, right on the occasion of the Lunar New Year.
When the project is completed, nearly 150 households in the two villages of Phang Cu and Hang Chua will be able to celebrate Tet in the light of the national power grid for the first time.