Coal warehouse of Vung Ang II Thermal Power Plant collapsed due to storm, more than 6 months have not been completed

TRẦN TUẤN |

Ha Tinh - More than 6 months since the collapse of the coal storage warehouse of Vung Ang II Thermal Power Plant caused by storm No. 10, the recovery has not yet been completed.

On April 6, in an exchange with a reporter from Lao Dong Newspaper, Mr. Hoang Trong Binh - Deputy General Director of Vung Ang II Thermal Power Co., Ltd. said that up to this point, the remediation of the coal storage warehouse collapse of Vung Ang II Thermal Power Plant caused by storm No. 10 in 2025 has not been completed.

According to Mr. Binh, the installation of equipment inside the coal warehouse has been completed, but the roof has only been repaired about 10%, and it is expected to be repaired by September 2026.

Regarding the solution to overcome the coal storage roof, it still retains the design, without changing the area, we only increase the thickness of the steel pipes, increase the load-bearing capacity of the steel pipes and bolts," Mr. Binh shared.

Also according to Mr. Binh, it is estimated that the cost of repairing the damage to the coal storage shelf (excluding equipment) caused by storm No. 10 will cost about 20 million USD. These losses are partially paid by the insurance company.

The Deputy General Director of Vung Ang II Thermal Power Co., Ltd. also informed that, according to the plan, tomorrow (April 7), Unit No. 2 of Vung Ang II Thermal Power Plant will officially go into operation. Previously, in March 2026, this Unit No. 2 was successfully test-operated.

Vung Ang II Thermal Power Plant is invested by Vung Ang II Thermal Power Co., Ltd. (VAPCO), started construction at the end of 2021, with a total investment of about 2.2 billion USD.

The plant is located in Vung Ang ward, Vung Ang Economic Zone, Ha Tinh province. According to the design, the plant has 2 units with a total designed capacity of 1,330 MW (capacity of each unit 665 MW).

On July 22, 2025, Unit No. 1 was officially put into commercial operation.

TRẦN TUẤN
RELATED NEWS

Quang Ninh Thermal Power Joint Stock Company urgently invests in improving the environment

|

Quang Ninh - Quang Ninh Thermal Power Joint Stock Company is preparing to invest in the project to upgrade and renovate the exhaust gas treatment system with a total investment of 3,853 billion VND.

Suspend the operation of a coal-fired power plant for over 40 years if fuel is not transferred

|

The project clearly states that new coal-fired power plants with a lifespan of over 40 years must not be built and operated if they cannot be converted to fuel.

Test operation of Unit No. 2 of Vung Ang II Thermal Power Plant worth 2.2 billion USD

|

Ha Tinh - Vung Ang II Thermal Power Plant with a total investment of about 2.2 billion USD has just successfully test-operated unit No. 2.

Revealing the plan to end the Iran conflict, waiting for a decision within the day

|

Iran and the US received a plan to end the conflict and reopen the Strait of Hormuz, a well-informed source revealed on April 6.

Academic transcripts, degrees integrated on VNeID: Progress in building education data

|

From May 15, 2026, transcripts and diplomas, certificates will be integrated on the VNeID application, serving for lookup and use in many administrative procedures.

Thailand announces initial results of mysterious missing 57 million tons of fuel

|

Huge amount of fuel mysteriously disappeared, Thai authorities suspect involvement in illegal fuel transit and storage activities.

Gold prices plummet, trading is smooth

|

On April 6, gold prices adjusted down, gold stores continued to be bustling in the buying direction.

Quang Ninh Thermal Power Joint Stock Company urgently invests in improving the environment

Nguyễn Hùng |

Quang Ninh - Quang Ninh Thermal Power Joint Stock Company is preparing to invest in the project to upgrade and renovate the exhaust gas treatment system with a total investment of 3,853 billion VND.

Suspend the operation of a coal-fired power plant for over 40 years if fuel is not transferred

PHẠM ĐÔNG |

The project clearly states that new coal-fired power plants with a lifespan of over 40 years must not be built and operated if they cannot be converted to fuel.

Test operation of Unit No. 2 of Vung Ang II Thermal Power Plant worth 2.2 billion USD

TRẦN TUẤN |

Ha Tinh - Vung Ang II Thermal Power Plant with a total investment of about 2.2 billion USD has just successfully test-operated unit No. 2.