According to Resolution No. 76/NQ-HDND dated December 9, 2021 of the People's Council of Quang Ninh province, the total capital of the medium-term public investment plan for the period 2021-2025 of Quang Ninh is 92,155 billion VND. This capital includes: 4,105 billion VND of central budget capital; 87,199 billion VND of local budget balance capital (provincial budget 60,871 billion VND, district budget 26,328 billion VND); 851 billion VND of re-borrowed capital from the Government.
Through the process of adjusting and supplementing arising capital sources, the total medium-term public investment capital for the 2021-2025 period is currently VND 95,752 billion, VND 3,597 billion higher than the beginning of the period, an increase of VND 26,647 billion compared to the 2016-2020 period.
Medium-term public investment capital for 2021-2025 from the provincial budget is allocated in detail for 319 projects; district budget capital is allocated in detail for 635 projects completed from the previous phase, 372 transitional projects and 1,937 newly started projects.
According to the monitoring results of the People's Council of Quang Ninh province, up to now, the provincial budget has played a leading role in implementing key projects and target programs, contributing to promoting socio-economic development and narrowing the gap between regions. The allocation of the medium-term public investment plan has closely followed the principle of concentration, not dispersion; ensuring the order of priority and allocating resources to implement projects under the national target program.
The efficiency of public investment in the 2021-2025 period has gradually improved, with many completed transport infrastructure projects with inter-regional connectivity and great impact, such as: Van Don - Tien Yen Expressway, Ha Long - Cam Pha coastal road, Love Bridge, Binh Minh Bridge; and comprehensive programs for socio-economic development in ethnic minority, mountainous, border and island areas, contributing to improving people's living conditions, bringing Quang Ninh to the finish line of the national target program on new rural construction earlier than the whole country.
However, there are still many projects and programs in the 2021-2025 medium-term public investment plan that have not been approved.
In addition to the two projects that have just been approved for investment policy by the 22nd Session of the Quang Ninh Provincial People's Council in order to allocate capital in time for the year-end meeting (Project to upgrade and expand Provincial Road 327 connecting Dong Trieu City to Uong Bi City and Project to upgrade Provincial Road 330, section from Ba Che Town to Provincial Road 342), many other projects have not completed the procedures to submit to competent authorities for approval of investment policy.
Including: Project to build additional items of the provincial Social Protection Center; Provincial General Hospital - Facility 2; Project to expand Bai Chay Hospital; Project to improve capacity for Quang Ninh provincial forest rangers on forest protection management and fire prevention and fighting in the period of 2024-2025; Rural transport program in Co To district.
To ensure the completion of the goals and targets of the 2021-2025 medium-term public investment plan, the Provincial People's Council requests the Provincial People's Committee to direct relevant agencies and units to urgently review and evaluate the entire medium-term public investment plan with state budget capital for the period 2021-2025, propose solutions; prepare investment for projects that have been approved by the Party Committee to urgently speed up the completion of investment procedures (approval of investment policies, approval of projects), as a basis for reporting to the Provincial People's Council to allocate the 2025 plan.