Speeding up the progress of one of the traffic projects in Hue

PHÚC ĐẠT - NGUYỄN LUÂN |

HUE - The Phong Dien - Dien Loc rescue road project is being accelerated with the goal of completing the entire project before September 2, 2025.

Du an duong cuu ho, cuu nan Phong Dien - Dien Loc tri gia hon 770 ti dong. Du an duoc phe duyet nam 2010 do Ban Quan ly du an Dau tu xay dung cong trinh giao thong TP Hue lam chu dau tu.
The Phong Dien - Dien Loc rescue road project is worth more than 770 billion VND. The project was approved in 2010 by the Hue City Traffic Construction Investment Project Management Board as the investor.
Nam 2012 du an duoc khoi cong. Du an co tong chieu dai toan tuyen hon 16,2km voi diem dau giao voi QL1A tai Phong Dien, diem cuoi la bai bien xa Dien Loc (thi xa Phong Dien).
In 2012, the project was started. The project has a total length of more than 16.2km with the starting point intersecting with National Highway 1A in Phong Dien, the end point being the beach of Dien Loc commune (Phong Dien town).
Theo du kien, du an se phai hoan thien sau 3 nam ke tu ngay khoi cong. The nhung, den thang 1.2025 (tuc da 13 nam), du an van con dang do. Nguyen nhan do du an nay nam trong danh muc cac du an duoc bo tri von tu Chuong trinh xay dung cac tuyen duong cuu ho - cuu nan cua Trung uong. The nhung, sau khi Chinh phu siet chat dau tu cong, du an nay phai tam ngung thi cong.
The project is expected to be completed after 3 years from the start date. However, by January 2025 (ie 13 years), the project is still unfinished. The reason is that this project is included in the list of projects allocated capital from the Central Rescue and Road Construction Program. However, after the Government tightened public investment, this project had to temporarily suspend construction.
Truoc tinh hinh do, thang 1.2024, HDND tinh Thua Thien Hue (nay la HDND TP Hue) da dieu chinh bo sung them hon 100 ti dong. Den thang 8.2024, du an thong xe mot chieu. Du an duoc ki vong se hoan thanh cuoi nam 2024 nhung den nay van con mot so hang muc chua lam xong.
Faced with that situation, in January 2024, the People's Council of Thua Thien Hue province (now the People's Council of Hue city) adjusted and added more than 100 billion VND. By August 2024, the project will be opened to one-way traffic. The project is expected to be completed by the end of 2024, but there are still some items that have not been completed.
Ghi nhan cua PV Bao Lao Dong, hien nha thau dang huy dong kha nhieu may moc, nhan luc, vat lieu de thi cong nhung hang muc cuoi cua du an.
According to the reporter of Lao Dong Newspaper, the contractor is currently mobilizing quite a lot of machinery, human resources, and materials to construct the final items of the project.
Diem noi giua cau vuot duong sat va tuyen duong dang duoc ket noi.
The connection point between the railway overpass and the road is being connected.
Theo bao cao cua Ban Quan ly du an dau tu xay dung cac cong trinh giao thong TP Hue cho biet, du an duong cuu ho, cuu nan Phong Dien - Dien Loc dang buoc vao giai doan nuoc rut voi nhieu hang muc chinh da hoan thanh, tuy nhien van con mot so doan dang tiep tuc thi cong va gap kho khan ve von cung nhu giai phong mat bang.
According to the report of the Hue City Traffic Construction Investment Project Management Board, the Phong Dien - Dien Loc rescue project is entering the final stage with many main items completed, however, there are still some sections that are continuing to be constructed and facing difficulties in capital as well as site clearance.
Hien, doan tuyen Km1+500 – Km9+800, cung voi cau Thiem va cau Bau Bang, da duoc ban giao va dua vao su dung. Doan tu Km9+800 den Km14+500 va nut giao QL49B cung da hoan tat phan nen va mat duong be tong xi mang rong 15m.
Currently, the section Km1+500 - Km9+800, along with Thiem Bridge and Bau Bang Bridge, has been handed over and put into use. The section from Km9+800 to Km14+500 and the QL49B intersection have also completed the foundation and road surface of 15m wide cement concrete.
Cong trinh cau vuot duong sat, voi chieu dai 66,3m, gom hai don nguyen rong 31m, hien da hoan thanh don nguyen ben phai va dang thi cong mat cau don nguyen ben trai, du kien hoan thanh truoc ngay 30.6.2025.
The railway overpass project, with a length of 66.3m, including two units of 31m wide, has completed the right unit and is constructing the left unit bridge surface, expected to be completed before June 30, 2025.
Phuong tien luu thong tren phan duong da hoan thien.
Vehicles on the completed road.
Doan Km0 – Km1+500 ben phai tuyen co ban hoan thanh, trong khi ben trai tuyen da xong phan nen, tuong chan, thoat nuoc va dang duoc day nhanh tien do thi cong voi muc tieu hoan thien toan bo truoc 2.9.2025.
Section Km0 - Km1+500 on the right of the basic route is completed, while the left of the route has completed the background, wall, drainage and is being accelerated with the construction goal with the goal of completion before 29.2025.
PHÚC ĐẠT - NGUYỄN LUÂN
TIN LIÊN QUAN

Deputy Prime Minister Tran Hong Ha inspects key projects in Quang Tri

|

Deputy Prime Minister Tran Hong Ha inspected the progress of two key projects, Quang Tri Airport and My Thuy Port Area.

Quang Ngai provincial leaders explain the reasons for a series of key projects being behind schedule

|

Quang Ngai - A series of key projects are behind schedule due to land and planning problems. The provincial leaders pledged to resolve the issue and speed up capital disbursement.

Hue adjusts road construction project for 7 years but still not completed

|

After 7 years of delay, the Mai - Tan My market road project worth nearly 200 billion VND in Hue is still unfinished. The Hue City People's Committee has just decided to adjust the project, change the capital source and extend the implementation period to the end of 2025.

serious accident in Ca Mau, truck burned down, 2 people died

|

Ca Mau - After two motorbikes collided, two people were thrown onto the road and were run over and killed by a truck, the truck caught fire fiercely.

Dozens of irrigation works in Lao Cai damaged after floods

|

Lao Cai - Heavy rain over the past few days has caused serious damage to the irrigation system in the area.

Psychological pressure is relieved, stocks wait for cash flow to explode

|

The current stock market sentiment is quite diverse. Some individual investors are somewhat optimistic, while some are still cautious.

Found two sisters missing while looking for jobs in Hanoi

|

Nghe An - Two sisters went to Hanoi to find a job in the summer and then went missing. After the authorities and police intervened, the two students were found safe.

Phuong My Chi's facial expression and surprise proposal to Tran Thanh in Em xinh say hi

|

Phuong My Chi is showing off as a prominent face in Em xinh say hi, and could be the winner of this race.

Deputy Prime Minister Tran Hong Ha inspects key projects in Quang Tri

HƯNG THƠ |

Deputy Prime Minister Tran Hong Ha inspected the progress of two key projects, Quang Tri Airport and My Thuy Port Area.

Quang Ngai provincial leaders explain the reasons for a series of key projects being behind schedule

VIÊN NGUYỄN |

Quang Ngai - A series of key projects are behind schedule due to land and planning problems. The provincial leaders pledged to resolve the issue and speed up capital disbursement.

Hue adjusts road construction project for 7 years but still not completed

PHÚC ĐẠT - NGUYỄN LUÂN |

After 7 years of delay, the Mai - Tan My market road project worth nearly 200 billion VND in Hue is still unfinished. The Hue City People's Committee has just decided to adjust the project, change the capital source and extend the implementation period to the end of 2025.