Overview of the traffic project connecting tourist areas in Hai Phong

Mai Dung |

By March 28, the 6.2 km route connecting Do Son tourist area with the center of Hai Phong city had reached more than 90% progress, ready to be put into use on April 30 and May 1.

Du an dau tu xay dung tuyen duong noi tu duong bo ven bien den nga ba Van Bun (quan Do Son, Hai Phong) dai 6,2 km voi tong muc dau tu gan 960 ti dong. Du an duoc ki vong ket noi khu du lich Do Son voi trung tam thanh pho; tao dieu kien cho cac phuong phia Tay quan Do Son chuyen dich co cau theo huong do thi hoa. Tuyen duong sau khi hoan thanh se tao da phat trien cac hoat dong thuong mai, dich vu, du lich; thu hut nguon von dau tu vao cac khu dat o, san xuat kinh doanh, dich vu du lich phu hop voi noi dung dinh huong quy hoach tong the phat trien kinh te-xa hoi quan Do Son den nam 2020, tam nhin den nam 2025.
The investment project to build a road connecting the coastal road to Van Bun intersection (Do Son district, Hai Phong) is 6.2 km long with a total investment of nearly 960 billion VND. The project is expected to connect Do Son tourist area with the city center; creating conditions for the wards in the West of Do Son district to change their structure towards urbanization. After completion, the route will create momentum for the development of commercial, service and tourism activities; attract investment capital in residential land, production and business, and tourism services in accordance with the content of the overall planning for socio-economic development of Do Son district until 2020, with a vision to 2025.

2
The scale of the project is to build a new 3.38 km long road section and upgrade a 2.82 km long road section. Both sections have soft, high-altitude road surface structure A1. On the investment route, 2 bridges will be built with a technical infrastructure system at the intersection, water supply system, rainwater drainage, wastewater, technical ditches, low-voltage power, lighting, sidewalks, and synchronous trees.

Sau gan 4 nam trien khai, du an dang trong giai doan hoan thien, chuan bi “ve dich“. Ghi nhan cua PV Lao Dong, doan tu nga tu giao duong truc phuong Bang La (quan Do Son) ve phia duong bo ven bien hien da xong nhieu hang muc nhu mat duong, cay xanh, dien chieu sang.
After nearly 4 years of implementation, the project is in the completion stage, preparing to "reach the finish line". According to Lao Dong reporter, the section from the intersection of the Bang La ward axis road (Do Son district) towards the coastal road has now completed many items such as road surface, trees, lighting.

Trong chieu 21.3, cong nhan dang thi cong lat gach terazo 300x300 via he cua doan gan nga tu voi duong truc phuong Bang La.
Workers are paving the sidewalk with 300x300 terrazzo tiles near the intersection with the Bang La ward axis road.

4
The remaining section from the intersection of Bang La Axis Road towards Van Bun Intersection (Ly Thai To Street, Do Son District) has completed the paving of layer 1, the median strip.

d
According to information from the Do Son District Construction Investment Project Management Board, by March 28, the construction package had completed about 90% of the work volume compared to the contract value. The B1 and B2 bridge items have been completed. Most sections of the route will be paved in April. Some other items such as lighting construction, tree planting, and site clearance will be completed before April 15, 2025.
6
Despite difficulties due to scarce materials and high prices, many trucks carrying materials to other projects in Do Son district hinder the construction process, however, the Do Son District Investment and Construction Project Management Board coordinated to remove difficulties with contractors, strive to complete and put the project into use during the April 30 and May 1 holidays.

Panorama of the road connecting from the coastal road to Van Bun intersection (Do Son district, Hai Phong). Video: Mai Dung

Mai Dung
TIN LIÊN QUAN

750 Hai Phong union officials receive occupational safety training

|

On March 25, the Hai Phong City Labor Federation held a conference to assess the current state of labor safety in the area and provide training on labor safety and hygiene in 2025.

Hai Phong leases more than 100 hectares of land for Tien Thanh Industrial Park project

|

The People's Committee of Hai Phong City has just issued a decision to lease more than 100 hectares of land to Tien Thanh Industrial Park Investment Joint Stock Company.

Wave of gold withdrawal from Europe and the US amid gold price fluctuations

|

In the context of strong fluctuations in gold prices, Turkey is one of the countries that quickly brings gold from the US and Europe back to the country.

People stay up all night lining up with bricks, asphalt chairs waiting to buy tickets to watch the VTV Cup final

|

A large number of fans were present in front of Vinh Phuc Stadium (Phu Tho) to wait for tickets to the final match of the VTV Cup 2025.

Assigning specific tasks to the Chairman and Vice Chairman of the Ho Chi Minh City People's Committee

|

HCMC - The HCMC People's Committee has just issued a decision to assign work to the Chairman, Vice Chairmen and members of the HCMC People's Committee for the 2021 - 2026 term.

Benchmark scores for grade 10 admission to 4 specialized schools in Hanoi in 2025

|

The benchmark score for grade 10 of 4 high schools for the 2025-2026 school year has been announced by the Hanoi Department of Education and Training.

750 Hai Phong union officials receive occupational safety training

Mai Dung |

On March 25, the Hai Phong City Labor Federation held a conference to assess the current state of labor safety in the area and provide training on labor safety and hygiene in 2025.

Giả khách hàng rồi xịt hơi cay để cướp tiền ở Hải Phòng

Hoàng Khôi |

Ngày 25.3, Công an TP Hải Phòng cho biết, Công an xã Tân Minh (huyện Tiên Lãng) vừa kịp thời bắt giữ đối tượng cướp tài sản.

Hai Phong leases more than 100 hectares of land for Tien Thanh Industrial Park project

Mai Dung |

The People's Committee of Hai Phong City has just issued a decision to lease more than 100 hectares of land to Tien Thanh Industrial Park Investment Joint Stock Company.