The Lo River Bridge is bare of steel and the accusation from heaven

Lê Thanh Phong |

Phu Tho Provincial Police have initiated a criminal case of "Violating construction regulations causing serious consequences" occurring at the Lo River bridge project.

The Lo River Bridge has a total investment of 215 billion VND, the contractor is Urban and Industrial Park Development Investment Joint Stock Company.

Previously, Lao Dong Newspaper reported that after 10 years of use, the Lo River bridge is now in a state of disrepair. After the water level of the Lo River receded, it was discovered that the T3 pillar was damaged, exposing the steel truss.

Fortunately, the damage to the bridge piers was exposed thanks to the receding water, which could cause unsafety. The authorities have announced a ban on cars traveling through the Lo River bridge.

If there is no "favor" of the river, the management agency will still let heavy trucks travel through the bridge, not knowing what the consequences will be.

Information about the damage to the Lo River bridge pillars after the river water level dropped was raised at the National Assembly forum on November 6, delegate Nguyen Anh Tri (Hanoi National Assembly delegation) said: "The supervision consultants know but do not say anything. Looking at the bridge pillars, the whole land is in the middle, it is extremely strange and I see a feeling of oppression....

The damaged bridge piers were exposed, the contractor sent a document to the People's Committee of Phu Tho province and the Department of Construction to propose repairing and overcoming the bridge damage with capital from the enterprise.

Of course, the Lo River Bridge must be repaired to ensure safety, but it is necessary to carry out consultation and inspection steps to come up with an effective handling plan.

But there are also things that cannot be easily fixed, because it is necessary to clarify whether or not there are other "damages" hidden behind the damage of the bridge piers.

Therefore, based on the collected documents and evidence, the Investigation Police Agency issued a decision to prosecute a criminal case to investigate and clarify the responsibilities of relevant organizations and individuals.

The new bridge has been damaged for 10 years, and there is no one to take responsibility.

The withdrawal of the Lo River Bridge pillars showing that there are many poor quality construction works that can "hide" the eyes of the world but are unlikely to " miss" nature.

A storm, a water, a wind can also express all the things that were thought to be easily hidden.

There are many works such as electric poles, embankments, dykes, and culverts that have been exposed by nature to the truth about quality, which are the accusations of heaven.

And, from the indictment of heaven, there may come a day when the people involved receive the indictment and it is announced at the trial.

If you want to avoid receiving accusations from the sky or from the prosecution agency, it is best to do it for real, the project must ensure quality.

Lê Thanh Phong
RELATED NEWS

Current status of the Lo River Bridge and many weak bridges in Phu Tho

|

Phu Tho - In addition to the Lo River Bridge, there are many other bridges in the province that are in a state of disrepair and need to be repaired, limiting their load.

The contractor for the Song Lo bridge proposed to repair the damage

|

Phu Tho - The contractor for the Song Lo bridge has proposed that the Provincial People's Committee and the Department of Construction repair and repair the bridge damage with corporate capital.

Lo River Bridge is severely damaged, National Assembly deputies question the quality of construction

|

National Assembly deputies questioned the quality of construction, supervision and acceptance at the Lo River bridge (Phu Tho) when it appeared to be severely damaged.

5 consecutive fishing boats sank in one morning in Lam Dong

|

Lam Dong - The rising and flowing water in the river caused 2 fishing boats to sink at Phan Ri port and 3 boats to sink at La Gi port.

Thousands of audiences line up to wait for G-DRAGON concert in Hung Yen

|

Thousands of G-DRAGON fans flocked to Vinhomes Ocean Park 3 Hung Yen area, lining up to check-in the Korean star's music night.

Tay Ninh issues emergency notice of flood on Vam Co Dong and Vam Co Tay rivers

|

On the morning of November 8, the Tay Ninh Provincial Hydrometeorological Station issued an urgent notice on the flood situation on the Vam Co Dong, Vam Co Tay rivers and the Dong Thap Muoi area.

Quang Tri Provincial People's Committee directs review of Deputy Director of the Department of Health

|

Quang Tri - The Provincial People's Committee directed the review of Mr. Le Thanh Tuan due to errors in appraisal of documents and violations of the Law on Anti-Corruption.

Building Tuyen Quang to develop, steadfastly in the era of national growth

|

Tuyen Quang - On November 8, the Vietnam Fatherland Front Committee (VFF) of Tuyen Quang province held the 1st Congress of Delegates for the 2025-2030 term.

Current status of the Lo River Bridge and many weak bridges in Phu Tho

Tô Công |

Phu Tho - In addition to the Lo River Bridge, there are many other bridges in the province that are in a state of disrepair and need to be repaired, limiting their load.

Khởi tố hình sự vụ án cầu sông Lô trơ cốt thép

Tô Công |

Công an tỉnh Phú Thọ đã ra Quyết định khởi tố vụ án hình sự “Vi phạm quy định về xây dựng gây hậu quả nghiêm trọng” xảy ra tại công trình cầu sông Lô.

The contractor for the Song Lo bridge proposed to repair the damage

Tô Công |

Phu Tho - The contractor for the Song Lo bridge has proposed that the Provincial People's Committee and the Department of Construction repair and repair the bridge damage with corporate capital.

Lo River Bridge is severely damaged, National Assembly deputies question the quality of construction

CAO NGUYÊN |

National Assembly deputies questioned the quality of construction, supervision and acceptance at the Lo River bridge (Phu Tho) when it appeared to be severely damaged.