Early compensation for people affected by Cai Khe boat lock construction

Lê Thanh Phong |

Construction of Cai Khe boat lock project caused many houses in Can Tho to sink, crack and be deeply flooded.

Just heavy rain, residential areas near Cai Khe boat dock project are deeply flooded, streets become rivers, houses become reservoirs. Households have to cope with flood water, extremely miserable.

This area has never been flooded before, even during the historic high tide in 2022.

People said that the construction unit came down to check the flooding situation and promised to fix the sewer, but so far it has not been done.

The Cai Khe boat lock project is a package under the Can Tho City Development and Urban Resilience Project (Project 3), which started in September 2022. After nearly 2 years of construction, the project has been completed.

The flood risk management system for Can Tho city, but caused flooding to a residential area, this is unacceptable.

The first thing is that relevant units must compensate for houses that have sunk, cracked, or damaged due to the impact of the Cai Khe boat lock construction project.

Many households have sent complaints to the government and the Can Tho City Project Management Board. Responsible agencies and units must visit people's homes to consider and compensate for damages to the people.

Mr. Tran Van Phu Lam, whose four houses were damaged, said: “I know this is a key project and also a common benefit of the city. However, up to now, the project has been completed but I have not received compensation for the damage. I really hope that the agencies, departments and branches will soon support to overcome the consequences and compensate my family appropriately for the damage.”

People say it makes sense, the government must listen and resolve it.

The second is to solve the flooding problem for the area affected by the Cai Khe boat lock project.

Households here have to live in flooded houses, disrupting all activities, from traveling, eating, to studying. The elderly, children, and sick people all have to wade in the water, the environment is dirty, and susceptible to disease.

The Cai Khe boat lock project, with an investment of 437 billion VND, is a package under the Can Tho City Development and Urban Resilience Project. The people are very happy to receive this, but first of all, they have to compensate for damage to houses and repair the sewer system so that people are not flooded, so that people can "immediately enhance their resilience".

Lê Thanh Phong
TIN LIÊN QUAN

Advance payment of 2.5 billion to compensate for houses cracked due to construction of boat dock

|

Can Tho - The construction unit of Cai Khe Boat Dock project will advance 2.5 billion VND to pay compensation to households affected during the construction process.

Starting construction of Bao Loc - Lien Khuong expressway worth nearly 18,000 billion VND

|

Lam Dong - Bao Loc - Lien Khuong Expressway has a total investment of nearly VND18,000 billion, will shorten travel time between Ho Chi Minh City - Da Lat from 6 hours to 3 hours.

VinFast inaugurates electric car factory in Ha Tinh

|

Ha Tinh - On the morning of June 29, VinFast Company held the inauguration ceremony of VinFast Ha Tinh Electric Car Factory in Vung Ang Economic Zone.

Gia Lai has a new Director of the Provincial Police

|

Gia Lai - Major General Le Quang Nhan, Director of Binh Dinh Provincial Police, holds the position of Director of the new Gia Lai Provincial Police after the merger.

Many scandals have not been closed, Hoang Huong Pharmaceuticals still blatantly violate

|

Hoang Huong Pharmaceuticals, despite being fined many times, continuously violate advertising and business regulations. Is the current referee not strong enough to prevent re-offending?

Expanding the Ho Chi Minh City - Long Thanh Expressway with VND16,386 billion must select a capable contractor

|

Dong Nai - The project to expand the Ho Chi Minh City - Long Thanh expressway section, nearly 22km long, connects Ho Chi Minh City with Bien Hoa - Vung Tau expressway and Long Thanh airport.

Ảnh hưởng thi công âu thuyền, nhà dân bị ngập sâu trong nước

YẾN PHƯƠNG - TẠ QUANG |

Việc thi công công trình Âu thuyền Cái Khế đã khiến nhiều nhà dân tại TP Cần Thơ bị lún, nứt nghiêm trọng và ngập sâu trong nước.

Advance payment of 2.5 billion to compensate for houses cracked due to construction of boat dock

YẾN PHƯƠNG - TẠ QUANG |

Can Tho - The construction unit of Cai Khe Boat Dock project will advance 2.5 billion VND to pay compensation to households affected during the construction process.

Âu thuyền hoàn thành, nhà dân bị lún nứt chưa được bồi thường

YẾN PHƯƠNG - TẠ QUANG |

Cần Thơ - Công trình Âu thuyền Cái Khế đã hoàn thành nhưng nhiều hộ dân bị lún, nứt do thi công vẫn chưa nhận được bồi thường.

Thi công âu thuyền Cái Khế 436 tỉ đồng ở Cần Thơ

Tạ Quang |

Cần Thơ - Hiện tại, nhà thầu thi công Âu thuyền Cái Khế đang triển khai song song nhiều mũi thi công, các nhân công thực hiện 3 ca 4 kíp, thay phiên nhau làm tăng ca ngày, đêm để hoàn thiện công trình.