Minister of Health explains why Bach Mai and Viet Duc Hospitals, facility 2, have not yet operated

PHẠM ĐÔNG |

The Minister of Health explained why the Bach Mai and Viet Duc Hospital project, facility 2, completed the rough construction but has not yet been operational.

On April 10, the National Assembly discussed in groups on socio-economic development plans, state budget; practice of thrift and combat of wastefulness.

National Assembly Deputy Vu Van Tien (Hai Phong Delegation) expressed concern about the results of practicing thrift and combating wastefulness in Government Report No. 165.

Firstly, the report has pointed out that some localities and ministries have built and implemented the program of practicing thrift and combating waste not seriously, not seriously.

Second, the number of ministries, branches, localities, and businesses that have not complied with regulations on the time for issuing thrift practice programs against wastefulness or are slow, and have not reported results of thrift practice against wastefulness has increased compared to previous years.

Đại biểu Quốc hội Vũ Văn Tiến nói về các dự án lãng phí. Ảnh: Phạm Đông
National Assembly Deputy Vu Van Tien talks about wasteful projects. Photo: Pham Dong

According to the delegate, waste is not for anyone's family, but when seeing a wasteful project, everyone's heart aches.

In Hanoi, the Ministry of Foreign Affairs headquarters only has half of the unit put into operation, and half of the unit is overgrown with weeds.

Passing through the operating headquarters of Vietnam Cement Corporation on Pham Hung street, the case has been prosecuted, but to this day it is still "stubborn with age" with a building of several dozen floors," the delegate cited.

Next is Viet Duc Hospital, Bach Mai Hospital facility 2. The delegate said that the case has prosecuted and arrested many defendants but has not yet been put into operation.

The delegate asked when these 2 hospitals will go into operation? This is the concern and remorse of millions of voters who are waiting for the Government and the Prime Minister of the new term to direct decisively.

At group 8, Minister of Health Dao Hong Lan explained that although these 2 projects have completed the rough construction, they have not yet been operational.

The Minister said: "The backlog project has lasted for up to 10 years, in which violations have arisen right from the contract signing stage. Therefore, if only requiring no legalization of violations, it will be very difficult to handle thoroughly.

We choose the approach of acknowledging and accepting the violations that have occurred as a basis for proposing solutions to remove them. At the same time, it is necessary to clearly identify: officials who participate in handling and overcoming old violations will not be considered violators, in order to avoid being held responsible later for "knowing wrong but still doing it" in the process of resolving backlogs.

The Minister added that the core thing is to come up with appropriate handling solutions, ensuring no elements of corruption or negativity, and daring to do it for the common good. Otherwise, allowing a large project to continue to be prolonged will cause even more serious consequences.

Regarding the fact that the project has not yet been put into operation, the Minister said that the reason is that when handling each specific project, especially the hospital project, many subsequent procedures still need to be completed.

Regarding construction, the project is basically completed, the facilities are very good, it can be said that it is no different from a 5-star hotel, spacious, clean and beautiful," the Minister informed.

One of the important key points is related to completing fire prevention and fighting (PCCC), the Minister said: The project was built 10 years ago, so the regulations on PCCC are applied according to the old law.

Now, when re-evaluating, it is necessary to comply with new regulations with stricter requirements, leading to many problems. Some items must be adjusted, such as dismantling walls, adding doors, and then re-implementing the approval process.

Up to this point, after a very long time, the fire prevention and fighting plan has been approved. However, after approval, it is necessary to continue to construct adjustments, dismantle, and renovate some items to meet new requirements," the Minister informed.

Even the verification stage encounters many obstacles, many points are not consistent with current decrees and regulations.

PHẠM ĐÔNG
RELATED NEWS

Viet Duc Hospital has 3 more affiliated facilities in Hanoi and Hai Phong

|

The General Hospital of Agriculture was reorganized into facilities under Viet Duc Hospital.

Minister of Health Dao Hong Lan: Comprehensive people's health care, from early, remote and right from the grassroots level

|

The 14th National Congress of the Party took place from January 19-25, 2026. Reporters of Health and Life Newspaper exchanged with Member of the Party Central Committee, Minister of Health Dao Hong Lan about the implementation of Resolution 72-NQ/TW dated September 9, 2025 of the Politburo, along with key solutions to remove long-standing bottlenecks in the health sector, strongly shifting from the "treatment" mindset to comprehensive health care according to the cycle of life, putting people at the center.

Mr. Pham Gia Tuc becomes Standing Deputy Prime Minister

|

Deputy Prime Minister Pham Gia Tuc holds the position of Standing Deputy Secretary of the Government Party Committee, performing the duties of Standing Deputy Prime Minister.

Bac Phuoc Kien Residential Area Project removed from the list of commercial housing pilots

|

Ho Chi Minh City - Quoc Cuong Gia Lai's important project has been removed from the list of commercial housing pilot projects due to not meeting the conditions for participation.

6 Deputy Secretaries of the Ho Chi Minh City Party Committee assigned a series of key tasks

|

Ho Chi Minh City - 6 Deputy Secretaries of the City Party Committee are assigned specific tasks, associated with key areas to ensure continuous and effective administration.

Ho Chi Minh City Department of Food Safety informs about the case of many students suspected of food poisoning

|

Ho Chi Minh City - The Ho Chi Minh City Department of Food Safety has established an investigation team to handle a suspected food poisoning case at Binh Quoi Tay Elementary School.

Laborers struggle to make a living in the early summer heat

|

In the hot sunny weather in Hanoi, many outdoor workers are still quietly clinging to make a living because life does not allow them to stop.

Mr. Le Ngoc Chau holds the position of Secretary of Hai Phong City Party Committee

|

Hai Phong - On the morning of April 10, Hai Phong held a conference to announce the Politburo's decision approving Mr. Le Ngoc Chau to hold the position of Secretary of the City Party Committee.

Bộ Công an thông tin về vụ án xảy ra tại 2 bệnh viện và Viện Pháp y tâm thần Trung ương

PHẠM ĐÔNG |

Bộ Công an đã ban hành kết luận điều tra, đề nghị truy tố 10 bị can trong vụ án tại 2 bệnh viện; thu hồi 10 tỉ đồng trong vụ Viện Pháp y tâm thần Trung ương.

Viet Duc Hospital has 3 more affiliated facilities in Hanoi and Hai Phong

PHẠM ĐÔNG |

The General Hospital of Agriculture was reorganized into facilities under Viet Duc Hospital.

Minister of Health Dao Hong Lan: Comprehensive people's health care, from early, remote and right from the grassroots level

Theo Thái Bình/Sức khỏe và Đời sống |

The 14th National Congress of the Party took place from January 19-25, 2026. Reporters of Health and Life Newspaper exchanged with Member of the Party Central Committee, Minister of Health Dao Hong Lan about the implementation of Resolution 72-NQ/TW dated September 9, 2025 of the Politburo, along with key solutions to remove long-standing bottlenecks in the health sector, strongly shifting from the "treatment" mindset to comprehensive health care according to the cycle of life, putting people at the center.