Immediate actions to complete 3,000 km of expressway in 2025

PHẠM ĐÔNG |

The Prime Minister requested to speed up site clearance and exploitation of construction materials for expressway projects to complete 3,000 km in 2025.

Politburo member and Prime Minister Pham Minh Chinh has just signed Official Dispatch No. 48/CD-TTg dated April 22, 2025 on accelerating the progress of site clearance and exploitation of construction materials for projects to complete 3,000 km of expressway in 2025.

According to the telegram, some localities are still slow to implement compensation, resettlement support, relocation of technical infrastructure, and construction material mines as required by the Prime Minister, affecting the progress of projects.

To speed up progress, the Prime Minister requested provinces with large volumes of site clearance such as Dong Nai (Bien Hoa - Vung Tau project), Khanh Hoa (Khanh Hoa - Buon Ma Thuot project), Lang Son (Huu Nghi - Chi Lang project), Binh Duong (Ho Chi Minh City Ring Road 3 project), Quang Tri (Van Ninh - Cam Lo project) to mobilize the entire political system to complete all site clearance before April 30, without delay.

Nghe An, Dong Nai, Binh Thuan, Khanh Hoa, Ninh Thuan, Quang Binh, Quang Tri, Quang Ngai, Hau Giang, Kien Giang, Phu Yen provinces urgently hand over the site for rest stops on the North - South expressway in the East before April 30, 2025.

The provinces of Dong Nai, Khanh Hoa, Dak Lak, Binh Duong, Long An in coordination with Vietnam Electricity Group (EVN) will complete the relocation of high-voltage power lines before April 30, 2025, without affecting the construction progress.

Quang Tri province (Van Ninh - Cam Lo project) urgently completes the relocation of technical infrastructure systems on service roads and level crossings at the overpass of National Highway 9D, National Highway 9A, and Tam Hiep.

Da Nang (Hoa Lien - Tuy Loan project) speeds up licensing procedures, increases the capacity of stone quarries according to regulations, to be completed before April 25, 2025.

Phu Yen province (Quy Nhon - Chi Thanh project) urgently completes procedures to increase the capacity of Phu Yen Road Road ownership and Support Joint Stock Company's quarry before April 30, 2025.

Dak Lak province (Khanh Hoa - Buon Ma Thuot project) completes procedures for approving the lease of Ea Kenh mine land according to regulations before April 30, 2025.

Dong Thap and An Giang provinces complete the procedures to adjust the Confirmation of mines granted under special mechanisms in accordance with regulations before April 30, 2025.

Tien Giang and Ben Tre provinces have completed licensing the remaining 3 sand mines; Vinh Long, Tien Giang and Ben Tre provinces have increased their mine capacity to meet the needs in 2025 according to regulations before April 25, 2025.

An Giang province will soon allocate stone sources at Antraco mines according to regulations to prioritize the supply of key projects in the area with a plan to complete in 2025.

Ho Chi Minh City and the provinces of Dong Nai and Binh Duong (Ho Chi Minh City Ring Road 3 project), Dong Thap (An Huu - Cao Lanh project) review and re-set the progress, be proactive in material sources, have appropriate and effective technical treatment solutions, and do not delay the project completion progress. Strive to complete in 2025.

The Ministry of Industry and Trade and EVN Group have directed and supported localities to urgently direct relevant units to speed up the completion of relocation of high-voltage power lines.

The Ministry of Construction closely coordinates with localities, investors and ministries and branches to direct investors and contractors to organize construction in 3 shifts, 4 teams, throughout holidays, holidays, Tet, not enough working days, taking advantage of working at night: with the spirit of "overcoming the sun to overcome the rain, not losing to wind and storm", "only discussing work, not backtracking" to speed up construction progress, meeting progress.

PHẠM ĐÔNG
TIN LIÊN QUAN

Urgently compensate people with dead rice next to the Can Tho - Ca Mau Expressway

|

The Deputy Prime Minister requested an urgent review, statistics and compensation for damages to people with dead rice next to the Can Tho - Ca Mau Expressway.

The shape of the expressway from Cao Bang to Ca Mau has been seen

|

The Prime Minister emphasized that he had seen the shape of the expressway from Cao Bang to Ca Mau and assigned tasks and finalized the implementation progress of the projects.

deadline for completing the Chau Doc - Can Tho - Soc Trang expressway

|

The Prime Minister requested to restore the delayed progress, completing the Chau Doc - Can Tho - Soc Trang expressway in June 2026.

Hoi Xuan Hydropower Plant is under monitoring, the Inspectorate points out the responsibility of Thanh Hoa Provincial People's Committee

|

The Government Inspectorate has clearly identified the responsibilities of the investor, the People's Committee of Thanh Hoa province, the Ministry of Industry and Trade... in the Hoi Xuan Hydropower Project.

Cadres prioritized by Hanoi as Ward and Commune Secretaries after the reorganization

|

Hanoi - For the position of Commune Secretary after the arrangement, the city will prioritize considering cadres who are City Party Committee members or District-level Secretaries.

Urgently compensate people with dead rice next to the Can Tho - Ca Mau Expressway

PHẠM ĐÔNG |

The Deputy Prime Minister requested an urgent review, statistics and compensation for damages to people with dead rice next to the Can Tho - Ca Mau Expressway.

The shape of the expressway from Cao Bang to Ca Mau has been seen

PHẠM ĐÔNG |

The Prime Minister emphasized that he had seen the shape of the expressway from Cao Bang to Ca Mau and assigned tasks and finalized the implementation progress of the projects.

deadline for completing the Chau Doc - Can Tho - Soc Trang expressway

PHẠM ĐÔNG |

The Prime Minister requested to restore the delayed progress, completing the Chau Doc - Can Tho - Soc Trang expressway in June 2026.