Wasteful projects in Thanh Hoa are being monitored by the Central Government

QUÁCH DU |

15 years after the groundbreaking date, the Hoi Xuan hydropower project (in Thanh Hoa) is still "inactive", with degraded and rusted infrastructure.

The Hoi Xuan hydropower project (in Phu Xuan commune, Quan Hoa district) has a total investment of more than VND 3,300 billion and was implemented 15 years ago. However, up to now, this project is still abandoned, machinery and materials are thrown everywhere, and weeds are growing wildly.

Du
The Hoi Xuan hydropower project (in Thanh Hoa) has been left unused after 15 years of construction. Photo: Quach Du

The Hoi Xuan hydropower project (in Phu Xuan commune, Quan Hoa district, Thanh Hoa province) has a total investment of more than VND 3,300 billion, capacity of 102 MW, and was started in 2010. The initial investor was Vietnam Electricity Construction Joint Stock Corporation.

After a period of extensive construction, in 2014, the project implementation was delayed and in the same year, the project was transferred to Dong Mekong Production and Construction Trading Services Company.

Do bo khong nhieu nam, cac hang muc thuoc du an bi xuong cap, hoen gi. Anh: Quach Du
Due to many years of abandonment, the items of the Hoi Xuan hydropower project have now deteriorated and rusted. Photo: Quach Du

In 2016, the project was resumed, however, from around 2019 to now, this project has stopped construction, the reason given is due to lack of capital.

In reality, 15 years after the groundbreaking date, there are no longer any construction activities in this project, equipment, machinery, and materials are "shelved" and rusted.

Many people living around the project area said that in the past 6 years (since 2019), this project has not been implemented, greatly affecting the lives and work of the people. Many areas of land in the project area cannot be cultivated, leading to a shortage of cropland. Meanwhile, many households have not yet received compensation as well as support policies due to the impact of the project.

Co cay moc um tum xung quanh du an. Anh: Quach Du
Grass and trees grow wildly around the project. Photo: Quach Du

According to the representative of the People's Committee of Quan Hoa district, the Hoi Xuan hydropower project is behind schedule and under construction, affecting the lives of many households in the project area. More than 655 hectares of land in the reservoir area of the hydropower project are affected, thousands of households are affected, of which about 500 households have to be resettled to new residences.

Up to now, many households have not received compensation or do not have resettlement areas, causing many difficulties in life.

The Hoi Xuan Hydropower Project is one of 4 cases and incidents with signs of waste that have just been included in the Central Steering Committee on preventing and combating corruption, waste and negativity for monitoring and direction.

On March 25, in Hanoi, the Standing Committee of the Central Steering Committee on preventing and combating corruption, waste and negativity held a meeting. At this meeting, the Standing Committee of the Steering Committee agreed to include 4 cases and incidents with signs of waste in the scope of the Steering Committee's monitoring and direction, including:

(1) The case of "Violating regulations on management and use of State assets causing loss and waste" related to violations at the Trade and Administrative Center Building Project, Vietnam Cement Corporation (VICEM).

(2) Hoi Xuan Hydropower Project, Thanh Hoa Province.

(3) Project to build the headquarters of the Ministry of Foreign Affairs.

(4) Sub-project 2 (Lim - Pha Lai), part of the Yen Vien - Pha Lai - Ha Long - Cai Lan railway project.

QUÁCH DU
TIN LIÊN QUAN

3 projects are added to the land use plan of Nam Tu Liem district

|

Hanoi - Add 3 projects, with a total area of about 82.7 hectares of land to the list of works and projects implemented in the 2025 land use plan of Nam Tu Liem district.

10-year project becomes a pollution hot spot

|

Hanoi - After nearly 10 years of construction, the project to build a road connecting Do Duc Duc Street to Me Tri Street is still in a messy and shabby state.

Many people leave the resettlement area in the 4,400 billion VND project

|

Dak Lak - Many people have left resettlement area No. 2 of the Krong Pac upstream reservoir project worth more than VND4,400 billion due to lack of land for cultivation.

Put 4 cases and incidents with signs of waste under the monitoring of the Central Steering Committee

|

The Standing Committee of the Central Steering Committee on preventing and combating corruption, waste and negativity agreed to include a number of cases and incidents with signs of waste in the scope of monitoring.

Suitable conditions for exploiting Ha Long Bay using hot air balloons

|

Quang Ninh - The Department of Culture, Sports and Tourism of Quang Ninh has just responded in writing to the unit registering to exploit Ha Long Bay tourism products using hot air balloons.

Living in a dilapidated ancient villa in Ba Dinh district

|

After a period of use, the villa at 65 Nguyen Thai Hoc (Ba Dinh District, Hanoi) has seriously degraded.

Thailand stabilizes after earthquake, investigates the only building collapse

|

Thailand has returned to normal conditions after the terrible earthquake in Myanmar shook the capital Bangkok.

Overturned on the highway, a teacher suffered a traumatic brain injury

|

Nghe An - The car overturned on the Dien Chau - Bai Vot highway, causing 12 people to be hospitalized for emergency treatment, including a teacher with a traumatic brain injury.

3 projects are added to the land use plan of Nam Tu Liem district

KHÁNH AN |

Hanoi - Add 3 projects, with a total area of about 82.7 hectares of land to the list of works and projects implemented in the 2025 land use plan of Nam Tu Liem district.

10-year project becomes a pollution hot spot

Minh Hạnh |

Hanoi - After nearly 10 years of construction, the project to build a road connecting Do Duc Duc Street to Me Tri Street is still in a messy and shabby state.

Many people leave the resettlement area in the 4,400 billion VND project

BẢO TRUNG |

Dak Lak - Many people have left resettlement area No. 2 of the Krong Pac upstream reservoir project worth more than VND4,400 billion due to lack of land for cultivation.

Put 4 cases and incidents with signs of waste under the monitoring of the Central Steering Committee

Vương Trần |

The Standing Committee of the Central Steering Committee on preventing and combating corruption, waste and negativity agreed to include a number of cases and incidents with signs of waste in the scope of monitoring.