Deputy Prime Minister requests clarification of Long Thanh airport delay

PHẠM ĐÔNG |

The Deputy Prime Minister requested to seriously review and clarify the causes of the delay in progress at Long Thanh airport to promptly have solutions to remove obstacles.

The Government Office issued Notice No. 78/TB-VPCP concluding the meeting of Deputy Prime Minister Tran Hong Ha at the construction site inspection, visiting and wishing Tet to officials and employees at the Long Thanh International Airport project phase 1 (Long Thanh airport).

To promptly rectify and accelerate the project implementation progress, the Deputy Prime Minister requested Airports Corporation of Vietnam (ACV), contractors and relevant agencies and units to seriously review and clarify the causes of existing problems and slow progress (causes due to organizational structure, personnel, slow payment...) to promptly have appropriate solutions to remove them.

In case there is no effective solution, the project cannot be completed on schedule as committed, ACV must proactively report and be responsible to the Government and the Prime Minister for the above delay.

The Deputy Prime Minister requested ACV to immediately work with contractors (including subcontractors) to clarify the reasons leading to the reduction in the number of officials and workers at the construction site, especially at packages and items that are underpasses, with large remaining volumes, in order to jointly find timely solutions.

In the immediate future, it is required that contractors immediately consolidate key officials at the bidding packages to direct and operate the construction site and have specific commitments on the progress of completing the items and bidding packages.

ACV directs the Project Management Board to focus on removing difficulties and obstacles of the project; proactively review the number of existing technical staff at the project to have timely solutions to transfer more projects to support project direction and operation.

On that basis, negotiate with contractors to sign contract appendices to update the implementation progress, forms of advance payment, payment or temporary payment of volumes already implemented in the spirit of removing difficulties, sharing risks, and minimum payment value to ensure sufficient payment of salaries and policies for employees during the Binh Ngo Lunar New Year 2026.

At the same time, ACV directs the supervision consulting unit and the Contractor to review the entire road of the project to build detailed construction progress of each package and item to control, direct and operate to ensure the project is implemented on schedule.

The Ministry of Construction coordinates with the People's Committees of Ho Chi Minh City, Dong Nai province, and Vietnam Expressway Development Investment Corporation to review and direct the acceleration of the implementation of road projects connecting Long Thanh airport with the city center and Tan Son Nhat Airport to ensure synchronous completion with the project.

Dong Nai Provincial People's Committee directed the investor to accelerate the progress and soon complete the fuel pipeline system for aircraft from the headwater port to the project and the drainage system of Long Thanh airport to ensure completion and serve synchronous operation of the project.

Contractors implementing the project focus on completing internal procedures according to regulations to pay for the completed volumes; and at the same time have written proposals and reports to ACV specifically on the status of payment dossiers for the completed volumes, absolutely not allowing shortages of salaries, wages and benefits for employees.

Contractors who do not have valid reasons to delay project progress must be responsible before the law and compensate for damages when affecting the completion progress and operational efficiency of the entire project.

PHẠM ĐÔNG
RELATED NEWS

30 minutes to Long Thanh airport, metro is the optimal option

|

Ho Chi Minh City is accelerating a series of ring road, expressway and metro system projects to shorten travel time to Long Thanh airport.

Deputy Prime Minister directs inspection and review of Long Thanh airport construction progress

|

The Deputy Prime Minister directed ministries, sectors, localities and relevant functional agencies to accelerate the implementation of the Long Thanh airport construction investment project.

Prime Minister Pham Minh Chinh inspects Long Thanh airport before the first flight

|

Dong Nai - On the afternoon of December 14, Prime Minister Pham Minh Chinh and the Central working delegation inspected Long Thanh airport before the first technical flight.

Approving election results, dismissing many personnel in Ho Chi Minh City, Quang Tri, Cao Bang

|

The National Assembly Standing Committee has issued a Resolution approving the results of the election and dismissal of Vice Chairmen of People's Councils (HĐND) in some provinces and cities.

Ho Chi Minh City 26th Tet: People scattered along National Highway 1 waiting for illegal buses to return home

|

Ho Chi Minh City - In the afternoon of February 13 (ie, the 26th of Tet), many people brought luggage to spontaneous parking lots and gas stations along National Highway 1 to wait for "illegal buses" to return to their hometowns for Tet.

Cold air causes rain and cold in the North from New Year's Eve

|

According to the meteorological agency, it is forecast that around the night of the 29th of Tet, a cold air mass will affect the weather in the North.

Gold price update at the closing session on February 13: Continuing to decrease sharply

|

Gold price update at the closing session on February 13: World gold continues to plummet. Domestic gold decreased from 1.5 to 2 million VND/tael.

Ordering technology cars in Hanoi faces difficulties, prices increase sharply near Tet

|

High ride-hailing prices in Hanoi near Tet have forced many people to balance their schedules to reduce costs.

30 minutes to Long Thanh airport, metro is the optimal option

Lê Thanh Phong |

Ho Chi Minh City is accelerating a series of ring road, expressway and metro system projects to shorten travel time to Long Thanh airport.

Deputy Prime Minister directs inspection and review of Long Thanh airport construction progress

PHẠM ĐÔNG |

The Deputy Prime Minister directed ministries, sectors, localities and relevant functional agencies to accelerate the implementation of the Long Thanh airport construction investment project.

Prime Minister Pham Minh Chinh inspects Long Thanh airport before the first flight

HÀ ANH CHIẾN |

Dong Nai - On the afternoon of December 14, Prime Minister Pham Minh Chinh and the Central working delegation inspected Long Thanh airport before the first technical flight.