Prime Minister requests technical opening of Huu Nghi - Chi Lang expressway before April 30, 2026

Khánh Linh |

Lang Son - Prime Minister Pham Minh Chinh requested Deo Ca Group to mobilize human resources and machinery to clear the Huu Nghi - Chi Lang expressway before April 30, 2026.

On the evening of February 19th (the 3rd day of the first lunar month), Prime Minister Pham Minh Chinh inspected the site and wished Tet to officials and workers constructing the Huu Nghi - Chi Lang border gate expressway project.

a
The Prime Minister's working delegation visits and directs on the route. Photo: Tuan Linh

At the Km45 construction site (Nhan Ly commune) and IC03 intersection (Ky Lua ward), the Prime Minister visited and inquired about the construction progress, living conditions, and policies for workers.

The Prime Minister acknowledged the spirit of working throughout Tet of units with the motto "3 shifts 4 shifts", "through Tet holidays, through holidays" to ensure progress.

Prime Minister listens to reports and directs at the construction site. Photo: Tuan Linh

The Prime Minister requested contractors, engineers, and workers to continue to emulate, maintain discipline, ensure quality and labor safety.

Local authorities are required to pay attention to the lives of workers, care for people affected by the project, and at the same time strengthen inspection, supervision and remove obstacles in the implementation process.

With Deo Ca contractor, the Prime Minister requested to mobilize more machinery, equipment, and manpower to accelerate progress, towards the goal of technical traffic opening of the entire route on April 30, 2026.

a
Prime Minister, leaders of the Ministry of Construction and leaders of Lang Son province present gifts to officials and workers of the project. Photo: Tuan Linh

Huu Nghi - Chi Lang border gate expressway is nearly 60 km long, passing through 7 communes and wards of Lang Son province, with a total investment of more than 11,000 billion VND, started on April 21, 2024. This is the first section of the North - South expressway axis in the East.

According to reports at the construction site, the project has mobilized nearly 3,000 officials, engineers, and workers with hundreds of construction teams.

In the context of mountainous terrain, complex geology and harsh weather, the units organized continuous construction to ensure progress, and by December 19, 2025, the route was opened.

When completed, the project is expected to increase connectivity in the northern border gate area, promote trade and socio-economic development of Lang Son and its vicinity.

Khánh Linh
RELATED NEWS

Prime Minister inspects and encourages police forces on duty during Tet

|

Prime Minister Pham Minh Chinh visited, wished Tet and inspected the on-duty work to ensure order, safety and security of officers and soldiers of 2 police units.

Prime Minister praises units for rapid completion of pontoon bridge across Lo River

|

Prime Minister Pham Minh Chinh praised the "lightning-fast" units that completed the pontoon bridge across the Lo River, opening to traffic on the morning of the 29th of Tet.

Huu Nghi - Chi Lang expressway is ready to clear hot spots on National Highway 1

|

Lang Son - Huu Nghi - Chi Lang expressway will only be temporarily activated when National Highway 1 is locally congested.

Cars are congested, queuing in long lines on Dai Ninh Pass during peak traffic hours

|

Lam Dong - From noon on the 4th day of Tet, cars were congested and lined up for many kilometers on Dai Ninh Pass due to damaged road surfaces causing traffic difficulties.

Stock market awaits new boosts

|

In the context of increasingly fierce capital flow competition, the Vietnamese stock market needs to rely more on the actual profit growth of enterprises.

Running shows throughout Tet with the lion and dragon dance troupe in Can Tho

|

Can Tho - Behind each performance is the enthusiasm and the arduous training process of the members of the lion and dragon dance troupe to bring joy to Tet.

Lunar New Year tourism 2026 bustling from North to South

|

The Binh Ngo Lunar New Year 2026 holiday lasts 9 days, tourism activities tend to grow in many key localities across the country.

Roadmap to return to Ho Chi Minh City after Tet to avoid traffic jams, people can refer to

|

The number of vehicles returning to the city is forecast to increase sharply in the last days of the Tet holiday, people should refer to the routes to Ho Chi Minh City later to avoid congestion at the gateways.

Prime Minister inspects and encourages police forces on duty during Tet

PHẠM ĐÔNG |

Prime Minister Pham Minh Chinh visited, wished Tet and inspected the on-duty work to ensure order, safety and security of officers and soldiers of 2 police units.

Prime Minister praises units for rapid completion of pontoon bridge across Lo River

PHẠM ĐÔNG |

Prime Minister Pham Minh Chinh praised the "lightning-fast" units that completed the pontoon bridge across the Lo River, opening to traffic on the morning of the 29th of Tet.

Huu Nghi - Chi Lang expressway is ready to clear hot spots on National Highway 1

Khánh Linh |

Lang Son - Huu Nghi - Chi Lang expressway will only be temporarily activated when National Highway 1 is locally congested.