Handling 2,981 backlog projects, not allowing mistakes to overlap, getting one job at a time

PHẠM ĐÔNG |

The Prime Minister emphasized that in handling 2,981 backlog projects, one thing must be done without another and requested the Central Inspection Committee to continue monitoring.

On July 17, Politburo member and Prime Minister Pham Minh Chinh chaired a national conference to review and evaluate the results of implementing the removal of difficulties and obstacles for projects and land according to Conclusion No. 77-KL/TW of the Politburo, Resolution No. 170/2024/QH15 of the National Assembly and Implement the Politburo's direction on reviewing and removing difficulties and obstacles for projects.

According to the report at the conference, through the latest review, up to now, the whole country has 2,981 backlog projects, which have lasted for many years, with great value and resources of society being wasted.

Concluding the conference, the Prime Minister emphasized that in handling projects and land, "one thing over another is wrong, one thing is for the other".

The Prime Minister said that removing difficulties and obstacles related to projects and land is a difficult, sensitive, unprecedented task, but must be determined to do so.

The implementation process must consider and propose carefully, so it has achieved practical results, removed difficulties and obstacles in many projects and has put into exploitation resources to serve socio-economic development.

The way of doing things and the results are agreed by people and businesses, welcomed and supported. This shows that it is necessary to promote the achieved results and continue to handle the remaining projects.

During the working process, it is necessary to digitize the database; coordinate between relevant ministries, branches and localities with the highest sense of responsibility, not pushing work; must handle the matter according to authority, exceeding authority and report to competent authorities.

According to the Prime Minister, out of a total of 2,981 projects that are currently backlogged and prolonged, there are 3 types. The first group is projects with clear violations; the second group is projects with problems with procedures; the third group is projects with signs of violations.

The Prime Minister requested ministries, branches and localities to continue updating data on the Steering Committee's Information Portal; reviewing, synthesizing, classifying, analyzing and evaluating projects.

Propose a direction for handling in accordance with regulations, on the principle that any issue under the authority of any level or branch should be handled by that level or branch, beyond the authority, and proposed to the competent authority for consideration and handling; ensure the rightful resolution of the people, the right work, the right content, the right scope, and the right subjects.

The Prime Minister requested Steering Committee 751 to continue completing the report to submit to the Politburo for consideration; requested the Central Inspection Committee to continue to perform the supervisory role, closely coordinating with competent authorities to perform this task well.

Thu tuong Chinh phu de nghi Uy ban Kiem tra Trung uong tiep tuc thuc hien vai tro giam sat go kho cho cac du an. Anh: Nhat Bac
The Prime Minister requested the Central Inspection Committee to continue to play the role of supervising and removing difficulties for projects. Photo: Nhat Bac

The Prime Minister requested agencies and localities to closely coordinate with Steering Committee 751 and the Government Party Committee to complete the report to the Politburo in August 2025, with the best possible quality.

In particular, report to ask for opinions on handling issues under the authority of the Politburo, the authority of the National Assembly, issues under the authority of the Government that the Government will resolve, any issues under the authority of ministries, branches and localities that ministries, branches and localities must proactively implement.

Based on the direction of the Politburo, the next steps will be taken according to the authority of each level.

PHẠM ĐÔNG
TIN LIÊN QUAN

Establish 8 working groups led by Government leaders to promote growth

|

The Prime Minister decided to establish 8 working groups to remove obstacles, promote growth and disburse public investment.

Strengthening inspection, combating bidding, and buying and selling of 4 expressway projects

|

The Deputy Prime Minister requested to strengthen inspection work, prevent corruption, negativity, waste, prevent bidding, and buy and sell of 4 expressway projects.

Do not legalize violations in the process of removing projects

|

According to the Permanent Deputy Prime Minister, in the process of removing obstacles for projects, violations must not be legalized, and other negative and negative violations must not arise.

Professor Nguyen Buu Trieu - "The Great Trees" of the Vietnamese Surgery industry passed away

|

Professor Nguyen Buu Trieu - "The Great Trees" of the Vietnamese Surgery industry, passed away last night, July 16 in Hanoi.

Ukraine has a female Prime Minister for the second time in history

|

On July 17, the Ukrainian parliament voted to appoint Yulia Svyrydenko as the country's new prime minister.

Live volleyball Vietnam men's team 1-2 Indonesia: Set 4

|

Live match between the Vietnamese men's volleyball team and Indonesia in the second phase of SEA V.League 2025, taking place at 19:00 on July 17.

Discussion: Green transportation transformation - an irreversible trend

|

In order to protect the environment and improve people's health, Lao Dong Newspaper organized a seminar: Green transportation transformation - an irreversible trend.

Support rate for Ms. Paetongtarn to be reappointed as Prime Minister of Thailand

|

With Prime Minister Paetongtarn Shinawatra suspended from office, Thailand is facing a major turning point with 3 potential scenarios.

Establish 8 working groups led by Government leaders to promote growth

PHẠM ĐÔNG |

The Prime Minister decided to establish 8 working groups to remove obstacles, promote growth and disburse public investment.

Strengthening inspection, combating bidding, and buying and selling of 4 expressway projects

PHẠM ĐÔNG |

The Deputy Prime Minister requested to strengthen inspection work, prevent corruption, negativity, waste, prevent bidding, and buy and sell of 4 expressway projects.

Do not legalize violations in the process of removing projects

ANH HUY |

According to the Permanent Deputy Prime Minister, in the process of removing obstacles for projects, violations must not be legalized, and other negative and negative violations must not arise.