Close-up of cracks and subsidence at the site of the metro tunnel excavation incident
Tô Thế |
Cracks and subsidence appeared at many locations in Lane 7 Giang Van Minh (Hanoi) after the Nhon - Hanoi Railway Station metro tunnel excavation incident.
Tô Thế |
Cracks and subsidence appeared at many locations in Lane 7 Giang Van Minh (Hanoi) after the Nhon - Hanoi Railway Station metro tunnel excavation incident.
|
According to monitoring data from the Nhon - Hanoi Railway Station metro project construction unit, some points in lane 7 Giang Van Minh (Hanoi) have subsidence exceeding the warning threshold.
|
Hanoi - On the night of February 27, people in lane 7 Giang Van Minh - where the problem of spillway equipment for metro tunnel digging occurred - had to be urgently evacuated due to cracks.
|
After 5 days of the incident of overflowing allowances during the digging of the Nhon - Hanoi Railway Station metro tunnel, the repair work has been basically completed.
|
Live broadcast of the match between U23 Vietnam and U23 UAE in the quarter-finals of the 2026 AFC U23 Championship, taking place at 10:30 PM today (January 16).
|
Thanh Hoa - The Police Agency has initiated a criminal case related to a particularly serious traffic accident on the highway that killed 4 people.
|
Live football match between U23 Japan vs U23 Jordan in the quarter-finals of the 2026 AFC U23 Championship at 6:30 PM tonight (January 16).
|
Voters at the Ministry of Culture, Sports and Tourism voted to agree to introduce Ms. Lam Thi Phuong Thanh, Standing Deputy Minister, to run for National Assembly Deputy of the 16th term.
|
Dong Nai - The Thu Thiem - Long Thanh railway project has a total estimated investment of about 84,753 billion VND, completed in 2031.
Tô Thế |
According to monitoring data from the Nhon - Hanoi Railway Station metro project construction unit, some points in lane 7 Giang Van Minh (Hanoi) have subsidence exceeding the warning threshold.
Tô Thế |
Hanoi - On the night of February 27, people in lane 7 Giang Van Minh - where the problem of spillway equipment for metro tunnel digging occurred - had to be urgently evacuated due to cracks.
Tô Thế |
After 5 days of the incident of overflowing allowances during the digging of the Nhon - Hanoi Railway Station metro tunnel, the repair work has been basically completed.