16 km of Bien Hoa - Vung Tau expressway to be technically opened to traffic by the end of April

HÀ ANH CHIẾN |

Dong Nai - Component project 1 of the Bien Hoa - Vung Tau expressway, 16 km long, ensures technical traffic opening according to the direction of the Provincial People's Committee.

On April 25, the Dong Nai Provincial Construction Investment Project Management Board said that 16 km of Bien Hoa - Vung Tau expressway belonging to component project 1 is being accelerated by contractors, constructed urgently, and so far the construction output has reached more than 82%, ensuring technical traffic opening according to the direction of the Provincial People's Committee.

According to reporters of Lao Dong Newspaper, currently on the entire route, there are contractors constructing asphalt concrete paving.

At package No. 18 of component project 1 of the Bien Hoa - Vung Tau expressway, the contractor is carrying out the final stages to strive for technical traffic opening before April 30 and completion and commissioning in June 2026.

This bidding package has a contract value of 1,479 billion VND, constructed in the section from Km0+000 to Km6+200. In the contractor consortium, Trungnam E&C plays a key role in many important construction fronts, including roadbed, weak soil treatment, asphalt concrete paving, culvert systems and cross-passes, with the consistent requirement of ensuring progress, quality and safety.

To date, package No. 18 has reached more than 70% of the volume, of which the main route has reached more than 80%.

The Project Management Board is urgently completing the final traffic items such as installing guardrails, medians, anti-glare nets, painting road markings, traffic safety systems, making roadside concrete and related auxiliary items, with the goal of completing the main tasks to technically open traffic before April 30, in accordance with commitments to Dong Nai province.

Previously, on April 9, Chairman of Dong Nai Provincial People's Committee Nguyen Van Ut inspected the actual construction progress at component project 1 of the Bien Hoa - Vung Tau expressway and set a target to complete the opening of the component project 1 of the Bien Hoa - Vung Tau expressway by the end of April 2026.

Images of urgent construction at package No. 18, component project 1 of Bien Hoa - Vung Tau expressway:

Gói thầu số 18, dự án thành phần 1 cao tốc Biên Hòa - Vũng Tàu đang thảm nhựa. Ảnh: HAC
Package No. 18, component project 1 of the Bien Hoa - Vung Tau expressway is being asphalted. Photo: HAC
Việc thảm nhựa được nhà thầu tiến hành thảm nhiều lớp, đảm bảo tiêu chuẩn chất lượng. Ảnh: HAC
The contractor carries out multi-layer asphalt pavement, ensuring quality standards. Photo: HAC
Thi công dải phân cách đang được thi công gấp rút. Ảnh: HAC
The median strip construction is being carried out urgently. Photo: HAC
Lắp tôn hộ lan được công nhân thi công khẩn trương, gấp rút kịp tiến độ. Ảnh: HAC
The installation of corrugated iron guardrails is being carried out by workers urgently and hastily, keeping up with the schedule. Photo: HAC
Nhà thầu đang khẩn trương hoàn thiện các hạng mục giao thông cuối cùng như lắp tôn hộ lan, dải phân cách, lưới chống chói, sơn vạch kẻ đường, hệ thống an toàn giao thông, làm bê tông lề đường. Ảnh: HAC
The contractor is urgently completing the final traffic items such as installing guardrails, medians, anti-glare nets, painting road markings, traffic safety systems, and making roadside concrete. Photo: HAC
Hạng mục cầu vượt đường Phùng Hưng đang được khẩn trương thi công. Ảnh: HAC
The Phung Hung overpass item is being urgently constructed. Photo: HAC
Theo tiến độ, 16km dự án thành phần 1 cao tốc Biên Hòa - Vũng Tàu thông xe kỹ thuật cuối tháng 4.2026. Ảnh: HAC
According to the schedule, 16 km of component project 1 of the Bien Hoa - Vung Tau expressway will be technically opened to traffic at the end of April 2026. Photo: HAC
Việc thi công diễn ra khẩn trương. Ảnh: HAC
Construction is taking place urgently. Photo: HAC
Nhà thầu tranh thủ thảm nhựa lúc điều kiện thuận lợi. Ảnh: HAC
Contractors take advantage of asphalt paving when conditions are favorable. Photo: HAC
Máy móc được huy động tối đa. Ảnh: HAC
Machinery is mobilized to the maximum. Photo: HAC
Dự án thành phần 1 cao tốc Biên Hòa - Vũng Tàu có chiều dài 16km. Đây là dự án thành phần do tỉnh Đồng Nai triển khai thực hiện. Ảnh: HAC
Component project 1 of the Bien Hoa - Vung Tau expressway is 16 km long. This is a component project implemented by Dong Nai province. Photo: HAC

According to the plan, before April 30, 2026, the main section of component project 2, Bien Hoa - Vung Tau expressway, more than 18 km long from Long Thanh intersection to the end point of the project connecting to component project 3 in Ho Chi Minh City will be put into temporary operation and agreed in the initial phase to only allow cars with fewer than 9 seats to circulate.

HÀ ANH CHIẾN
RELATED NEWS

Bien Hoa - Vung Tau expressway, initial phase only allows vehicles under 9 seats to circulate

|

Dong Nai - 18 km of Bien Hoa - Vung Tau expressway section from Long Thanh intersection to Ho Chi Minh City, the first phase only allows cars with fewer than 9 seats to circulate.

The appearance of 34km of Bien Hoa - Vung Tau expressway through Dong Nai opened to traffic at the end of April

|

Dong Nai - 34km of Bien Hoa - Vung Tau expressway through Dong Nai is completing the final stages to open to traffic along with 19.5km of Ho Chi Minh City by the end of April 2026.

Dong Nai will terminate contract with contractor for 16km delayed Bien Hoa - Vung Tau expressway

|

Dong Nai - Component project 1, Bien Hoa - Vung Tau expressway section passing through the province has a length of 16km, with the goal of opening to traffic at the end of April 2026.

16km of Bien Hoa - Vung Tau expressway is expected to be technically opened to traffic at the end of April

|

Dong Nai - Bien Hoa - Vung Tau expressway section from Vo Nguyen Giap intersection (National Highway 1) towards Ho Chi Minh City, 16km long, is expected to be technically opened to traffic at the end of April.

Suspension of activities of Khanh Hoa Provincial Yoga Federation

|

Khanh Hoa - The Provincial People's Committee has just issued a decision to temporarily suspend operations for the Khanh Hoa Provincial Yoga Federation, starting from April 25, 2026.

Images inside the series of caves just discovered in Phong Nha - Ke Bang

|

Quang Tri - Images inside the caves just discovered by explorers in Phong Nha - Ke Bang reveal many scientific values and tourism potentials.

Cultural house "grows" in the middle of the road in Ninh Binh's most populous ward

|

Ninh Binh - A corrugated iron cultural house is erected right in the middle of the road in a residential area in Nam Dinh ward.

Base salary is only 56% of the regional minimum wage, many differences in salary payment mechanism

|

The 56% gap between the base salary and the regional minimum wage is not only an income gap, but also reflects differences in the wage payment model between the two regions.

Bien Hoa - Vung Tau expressway, initial phase only allows vehicles under 9 seats to circulate

HÀ ANH CHIẾN |

Dong Nai - 18 km of Bien Hoa - Vung Tau expressway section from Long Thanh intersection to Ho Chi Minh City, the first phase only allows cars with fewer than 9 seats to circulate.

The appearance of 34km of Bien Hoa - Vung Tau expressway through Dong Nai opened to traffic at the end of April

HÀ ANH CHIẾN |

Dong Nai - 34km of Bien Hoa - Vung Tau expressway through Dong Nai is completing the final stages to open to traffic along with 19.5km of Ho Chi Minh City by the end of April 2026.

Dong Nai will terminate contract with contractor for 16km delayed Bien Hoa - Vung Tau expressway

HÀ ANH CHIẾN |

Dong Nai - Component project 1, Bien Hoa - Vung Tau expressway section passing through the province has a length of 16km, with the goal of opening to traffic at the end of April 2026.

16km of Bien Hoa - Vung Tau expressway is expected to be technically opened to traffic at the end of April

HÀ ANH CHIẾN |

Dong Nai - Bien Hoa - Vung Tau expressway section from Vo Nguyen Giap intersection (National Highway 1) towards Ho Chi Minh City, 16km long, is expected to be technically opened to traffic at the end of April.