The appearance of 34km of Bien Hoa - Vung Tau expressway through Dong Nai opened to traffic at the end of April

HÀ ANH CHIẾN |

Dong Nai - 34km of Bien Hoa - Vung Tau expressway through Dong Nai is completing the final stages to open to traffic along with 19.5km of Ho Chi Minh City by the end of April 2026.

The Bien Hoa - Vung Tau expressway project through Dong Nai province and Ho Chi Minh City has a total length of nearly 54km, divided into 3 component projects.

While component project 3 passing through Ho Chi Minh City (19.5km long) was technically opened to traffic in April 2025, the remaining 2 component projects passing through Dong Nai province (34km long) are completing the final items for operation on April 30, 2026.

The biggest difficulty at component project 1 (about 16km long) has reached about 80% of the contract value. Mr. Ho Van Ha - Vice Chairman of Dong Nai Provincial People's Committee requested to ensure traffic opening by the end of April 2026 to operate synchronously with other component projects of the project.

Điểm đầu cao tốc Biên Hòa - Vũng Tàu tại dự án thành phần 1 đoạn qua tỉnh Đồng Nai. Ảnh: HAC
The starting point of the Bien Hoa - Vung Tau expressway at component project 1 section passing through Dong Nai province. Photo: HAC

According to the reporter of Lao Dong Newspaper, at the starting point of component project 1, intersecting with Vo Nguyen Giap street, Phuoc Tan ward, Dong Nai province, asphalt has been paved and construction is being completed. The contractor is installing median strips, long mon racks...

As for component project 2, construction units are urgently completing the final stages of the project to ensure operating conditions.

Key tasks such as asphalt paving, median strip construction, fences, lighting systems, traffic safety warning systems, signs... have been basically completed and are implementing the connection of traffic routes to merge into the Bien Hoa - Vung Tau expressway.

Dự án thành phần 2 cao tốc Biên Hòa - Vũng Tàu đang dần hoàn thiện để đưa vào khai thác vào cuối tháng 4.2026. Ảnh: HAC
Component project 2 of the Bien Hoa - Vung Tau expressway is gradually being completed to be put into operation at the end of April 2026. Photo: HAC

Project Management Board 85 (investor of component project 2) has sent a report to the Ministry of Construction and requested to adjust the postponement of the temporary operation of the main route to April 2026, and adjust the traffic organization plan.

On the other hand, due to contractors encountering some difficulties, the progress of completing the remaining items is slow; some items must be adjusted and supplemented, such as the current condition of the road surface of Bung Mon street (connecting vehicles to enter the expressway from National Highway 51 according to the adjusted traffic organization plan) has been heavily damaged and degraded, many "potholes and craters" locations need to be repaired to ensure safe traffic.

Along with that, contractors also have to supplement and construct some temporary service road sections...

According to the plan, the Bien Hoa-Vung Tau expressway will be fully opened to traffic on April 30, 2026.

Image of 34km of Bien Hoa - Vung Tau expressway through Dong Nai opened to traffic at the end of April:

Toàn cảnh nút giao đa tầng nơi dự án thành phần 2 cao tốc Biên Hòa - Vũng Tàu đi qua, kết nối cao tốc TPHCM - Long Thành - Dầu Giây, sân bay Long Thành...
Overview of the multi-layered intersection where component project 2 of the Bien Hoa - Vung Tau expressway passes through, connecting the Ho Chi Minh City - Long Thanh - Dau Giay expressway, Long Thanh airport...
Các làn xe chạy trên cao tốc Biên Hòa - Vũng Tàu đã sẵn sàng chờ đưa vào khai thác. Ảnh: HAC
Lanes, turns... on the Bien Hoa - Vung Tau expressway are ready to be put into operation. Photo: HAC
Cầu vượt đoạn hướng từ quốc lộ 51 vào đường Bưng Môn để vào cao tốc. Ảnh: HAC
Overpass section from National Highway 51 to Bung Mon street to enter the expressway. Photo: HAC
Công nhân thi công gấp rút kịp tiến độ đưa dự án vào khai thác. Ảnh: HAC
Construction workers are rushing to meet the schedule to put the project into operation. Photo: HAC
Hàng loạt biển báo tại nút giao đa tầng trên cao tốc Biên Hòa - Vũng Tàu. Ảnh: HAC
A series of traffic signs at the multi-layered intersection on the Bien Hoa - Vung Tau expressway. Photo: HAC
Hướng TPHCM đi Đồng Nai trên cao tốc Biên Hòa - Vũng Tàu. Ảnh: HAC
Direction to Ho Chi Minh City on the Bien Hoa - Vung Tau expressway. Photo: HAC
Hướng đi Đồng Nai trên cao tốc Biên Hòa - Vũng Tàu. Ảnh: HAC
Direction to Dong Nai on the Bien Hoa - Vung Tau expressway. Photo: HAC
 Khi đưa vào khai thác, các phương tiện được phép lưu thông với vận tốc từ 60 đến 100km/giờ. Ảnh: HAC
When put into operation, vehicles are allowed to travel at speeds from 60 to 100km/h. Photo: HAC
Còn tại dự án thành phần 1 nhiều đoạn đã thảm nhựa. Ảnh: HAC
And at component project 1, many sections have been asphalted. Photo: HAC
Tiến độ dự án thành phần 1 cũng đưa vào khai thác đồng bộ trong tháng 4.2026. Ảnh: HAC
The progress of component project 1 will also be put into synchronous operation in April 2026. Photo: HAC
HÀ ANH CHIẾN
RELATED NEWS

Dong Nai will terminate contract with contractor for 16km delayed Bien Hoa - Vung Tau expressway

|

Dong Nai - Component project 1, Bien Hoa - Vung Tau expressway section passing through the province has a length of 16km, with the goal of opening to traffic at the end of April 2026.

Ho Chi Minh City traffic plan for 37km of Bien Hoa - Vung Tau expressway

|

Dong Nai - The investor of component project 2 of the Bien Hoa - Vung Tau expressway has reported on the traffic organization plan connecting Ho Chi Minh City with more than 37km of the expressway to be put into operation soon.

Bien Hoa - Vung Tau expressway opens to traffic one day early, benefits one day

|

Ho Chi Minh City proposes that the Ministry of Construction allow the opening of phase 1 of the Bien Hoa - Vung Tau expressway on March 30, 2026, the section from Long Thanh intersection to National Highway 56.

Ho Chi Minh City proposes to open the Bien Hoa - Vung Tau expressway on March 30

|

Ho Chi Minh City proposes that the Ministry of Construction allow the opening of phase 1 of the Bien Hoa - Vung Tau expressway on March 30, 2026.

Live Vietnam futsal team vs Australia, 3rd place match in Southeast Asian Championship

|

Live football match of Vietnam futsal team against Australia in the 3rd place match of the 2026 Southeast Asian Futsal Championship at 5:00 PM today (April 12).

Fire scene at a wood exhibition area in Ha Tinh, a smoke column tens of meters high

|

Ha Tinh - A large fire occurred at a wood exhibition area in Thanh Sen ward in the middle of the day, black smoke was billowing, functional forces controlled the scene.

National Assembly deputies propose Hanoi to allow conditional sidewalk parking

|

Delegate Nguyen Van Canh said that Hanoi needs to have stronger incentives to attract the construction of underground and high-rise parking lots; allowing partial parking on sidewalks.

Inside a 35-year-old apartment building in Hanoi before being renovated and rebuilt

|

After the households proactively handed over the land, the project to renovate the old apartment building No. 51 Huynh Thuc Khang, Hanoi is ready for demolition and reconstruction.

Dong Nai will terminate contract with contractor for 16km delayed Bien Hoa - Vung Tau expressway

HÀ ANH CHIẾN |

Dong Nai - Component project 1, Bien Hoa - Vung Tau expressway section passing through the province has a length of 16km, with the goal of opening to traffic at the end of April 2026.

Ho Chi Minh City traffic plan for 37km of Bien Hoa - Vung Tau expressway

HÀ ANH CHIẾN |

Dong Nai - The investor of component project 2 of the Bien Hoa - Vung Tau expressway has reported on the traffic organization plan connecting Ho Chi Minh City with more than 37km of the expressway to be put into operation soon.

Bien Hoa - Vung Tau expressway opens to traffic one day early, benefits one day

Lê Thanh Phong |

Ho Chi Minh City proposes that the Ministry of Construction allow the opening of phase 1 of the Bien Hoa - Vung Tau expressway on March 30, 2026, the section from Long Thanh intersection to National Highway 56.

Ho Chi Minh City proposes to open the Bien Hoa - Vung Tau expressway on March 30

MINH QUÂN |

Ho Chi Minh City proposes that the Ministry of Construction allow the opening of phase 1 of the Bien Hoa - Vung Tau expressway on March 30, 2026.