Dong Nai will terminate contract with contractor for 16km delayed Bien Hoa - Vung Tau expressway

HÀ ANH CHIẾN |

Dong Nai - Component project 1, Bien Hoa - Vung Tau expressway section passing through the province has a length of 16km, with the goal of opening to traffic at the end of April 2026.

On April 9, Chairman of the Provincial People's Committee Nguyen Van Ut and the working delegation inspected the construction progress of component project 1, Bien Hoa - Vung Tau expressway.

Component project 1, Bien Hoa - Vung Tau expressway section passing through Dong Nai province has a length of 16km. In phase 1, the expressway is invested and built with a scale of 4 lanes, design speed of 100 km/h.

The project has 2 construction packages under construction, and so far the realized value has reached 78% of the signed contract value.

At the inspection, Chairman of the Provincial People's Committee Nguyen Van Ut assessed that the current construction progress has not met the requirements.

This project, Dong Nai province sets a target to complete and open to traffic by the end of April 2026. Therefore, the Provincial People's Committee assigned the Provincial Construction Investment Project Management Board to work with construction contractors. Chairman of the Provincial People's Committee Nguyen Van Ut requested to decisively terminate the contract with the slow construction contractor at the project, and cannot allow the situation of slow construction to continue.

The Chairman of Dong Nai Provincial People's Committee also assigned the Provincial Construction Investment Project Management Board to review the construction progress of contractors, identify construction units that have not met requirements, and the Provincial People's Committee will work specifically.

On the same day, Chairman of the Provincial People's Committee Nguyen Van Ut and the working delegation also inspected the construction progress of the central road project of Bien Hoa city (in Tran Bien ward, Dong Nai province), road 25B project and road 25C project.

HÀ ANH CHIẾN
RELATED NEWS

Do not interrupt the construction of the Dong Dang - Tra Linh expressway

|

Cao Bang - Local authorities are looking for many options so that the Dong Dang - Tra Linh expressway does not have to stop construction due to rising fuel prices.

Traffic police strictly control the entire expressway, blocking violations from the entrance

|

The traffic police force coordinated with local police to strictly control from intersections to expressways, promptly detecting and handling many traffic violations.

After 3 years, the expressway worth more than 5,200 billion VND connecting Thang Long - Hoa Binh Avenue is still facing site clearance issues

|

Hanoi - Investing more than 5,200 billion VND, the road project connecting Thang Long Avenue to Hoa Lac - Hoa Binh expressway still has "remaining" land that has not been cleared.

President Trump threatens strongly if Iran does not comply with the ceasefire agreement

|

President Donald Trump warned that the US would escalate military action if Iran does not fully implement its agreed commitments.

Electric vehicles explode, Ministry of Industry and Trade responds to electricity supply capacity

|

According to the Ministry of Industry and Trade, the challenge is not the total electricity for electric vehicles but the development of a synchronous power grid with charging infrastructure, avoiding local overload.

More than 400 businesses with revenue over 1,000 billion VND/year declare losses

|

The tax authority said that there are more than 400 businesses with revenue from 1,000 billion VND per year but declared losses.

Live volleyball VTV Binh Dien Long An vs Thanh Hoa at the national championship

|

Live match between VTV Binh Dien Long An and Thanh Hoa at the national volleyball championship, taking place at 5:00 PM today (April 9).

Ho Chi Minh City Department of Culture and Sports fined the organizers of the "Southern Love 4" show

|

The Ho Chi Minh City Department of Culture and Sports has issued a decision to sanction administrative violations against the organizers of the show "Tu Tinh Phuong Nam 4".

Do not interrupt the construction of the Dong Dang - Tra Linh expressway

Tân Văn |

Cao Bang - Local authorities are looking for many options so that the Dong Dang - Tra Linh expressway does not have to stop construction due to rising fuel prices.

Traffic police strictly control the entire expressway, blocking violations from the entrance

Tô Thế - Tiến Ngô |

The traffic police force coordinated with local police to strictly control from intersections to expressways, promptly detecting and handling many traffic violations.

After 3 years, the expressway worth more than 5,200 billion VND connecting Thang Long - Hoa Binh Avenue is still facing site clearance issues

Minh Nguyễn - Thanh Bình |

Hanoi - Investing more than 5,200 billion VND, the road project connecting Thang Long Avenue to Hoa Lac - Hoa Binh expressway still has "remaining" land that has not been cleared.