2 domestic wastewater treatment plants that have only been used for 1 year have broken down

TRẦN TUẤN |

Ha Tinh - After being built and put into operation for a year, 2 domestic wastewater treatment models in Cam Nhuong commune (Cam Xuyen district) have been damaged and devastated.

According to a reporter from Lao Dong Newspaper, the domestic wastewater treatment model for Tan Dinh and Lien Thanh villages (Cam Nhuong commune) has been devastated after many years of inactivity.

The settling tank system, self-destroying tunnels, machinery, equipment... are all in a state of damage, rust, and serious degradation. Around, weeds grow wildly, becoming a place for mice and flies to live, which are both dirty and shabby.

Mr. Nguyen Van Thanh - Head of Tan Dinh village - said that in 2020, the pilot model of domestic wastewater treatment for residential clusters and people in Tan Dinh village was implemented, making people very excited. However, the project has been damaged after a few months of use.

Since 2021, the project has stopped operating after many unsuccessful repairs. From there, the hope of a model for treating domestic wastewater of more than 330 households in Tan Dinh village is gone.

At the same time in 2020, a similar domestic wastewater treatment model was implemented in Lien Thanh village but it also quickly deteriorated and could not operate.

More than 300 households in this village are also helpless when domestic wastewater is discharged directly into the environment without being treated.

Mr. Nguyen Van Hung - Chairman of Cam Nhuong Commune People's Committee - said that the two models of domestic wastewater treatment for Tan Dinh and Lien Thanh residential areas operating using homemade technology, on a small scale and at low capacity are ineffective.

Cong trinh xu ly nuoc thai sinh hoat o thon Lien Thanh bo hoang. Anh: Tran Tuan.
The domestic wastewater treatment plant in Lien Thanh village is abandoned. Photo: Tran Tuan.

These are 2 projects invested in by the Central New Rural Coordination Office - Ministry of Agriculture and Rural Development (now the Ministry of Agriculture and Environment) in coordination with the Center for Environmental Technology Analysis and Transfer (Institute of Agricultural Environment) in 2020.

Faced with the situation of the project being damaged early and not being effective, the Cam Nhuong commune government has proposed that the superiors invest in building a large-scale, more modern domestic wastewater treatment plant.

Thereby, it is possible to effectively and stably treat domestic wastewater in the long term to minimize environmental pollution, limit the impact on Thien Cam sea tourism area when this commune is connected to Thien Cam sea.

TRẦN TUẤN
TIN LIÊN QUAN

Fire two stilt houses in Dak Lak Nghi due to damage to electrical equipment

|

Dak Lak - a fire occurred in Lak district, caused two houses of stilts of the local people to be damaged.

Many sections of National Highway 29 are seriously damaged

|

National Highway 29 connecting Dak Lak and Phu Yen is seriously degraded, causing difficulties for traffic and freight transport. The two provinces are completing the submission, proposing that the Central Government soon allocate funds for upgrading and repairing.

Current status of more than 8km of National Highway 91B is broken after patching

|

Hau Giang - National Highway 91B through Hau Giang province is deteriorating and is expected to start construction in early 2026.

Discovering violations at a housing project, the Government Inspectorate recommends the Ministry of Public Security to intervene

|

The Government Inspectorate requested the Ministry of Public Security to receive information and documents for consideration and investigation with the Hoa Lan Housing Project (Ward 8, Vinh Long City).

Motorcycle emission inspection facilities must be more than 50m from hospitals

|

Currently, the Government is still developing a roadmap to apply motorbike emission testing.

Dong Bac Corporation proposes bauxite exploitation associated with security and defense tasks

|

Quang Ninh - Dong Bac Corporation is implementing procedures to prepare for investment in bauxite mining projects associated with security and defense tasks in the Central Highlands.

HCMC shaping the future on a new foundation, aspiring to reach global level

|

Ho Chi Minh City is shaping the future on the basis of new space and resources, aiming to become a smart, modern, green-growing global city.

The smallest administrative unit of Hanoi after the arrangement

|

Hanoi - After implementing the arrangement of administrative units, Cua Nam ward is expected to be the newest administrative unit with an area of 1.65km2.

Fire two stilt houses in Dak Lak Nghi due to damage to electrical equipment

BẢO TRUNG |

Dak Lak - a fire occurred in Lak district, caused two houses of stilts of the local people to be damaged.

Many sections of National Highway 29 are seriously damaged

BẢO TRUNG |

National Highway 29 connecting Dak Lak and Phu Yen is seriously degraded, causing difficulties for traffic and freight transport. The two provinces are completing the submission, proposing that the Central Government soon allocate funds for upgrading and repairing.

Current status of more than 8km of National Highway 91B is broken after patching

Tạ Quang |

Hau Giang - National Highway 91B through Hau Giang province is deteriorating and is expected to start construction in early 2026.