The project to build a resettlement area in Yen Thuy district, the old Hoa Binh province aims to ensure housing and relocation capacity for at least 18 households in the landslide and storm areas of Tan Thanh and Son Thuy communes in the old Mai Chau district (Tan Mai commune, Phu Tho province after the merger).
This is a Group C project, approved under Decision No. 1468/QD-UBND of the old Hoa Binh Provincial People's Committee, with a total investment of 25 billion VND, invested by the Hoa Binh Project Management Board. The implementation period of this project is 1 year.
According to the investigation of Lao Dong Newspaper reporters, on August 23, the Hoa Binh Project Management Board announced the bidding for Package No. 12: Construction and installation of construction equipment for the project.
Package No. 12 is in the construction sector, widely bid online, the package price is more than 21.2 billion VND from the central budget reserve in 2024 for some localities to overcome the consequences of storm No. 3 and floods after the storm.
In the coming time, after the contractor selection results are approved by the investor, the contractor will implement the construction of a resettlement area to ensure housing, meeting the ability to relocate at least 18 households in the landslide area due to storms and floods of Tan Thanh and Son Thuy communes in Mai Chau district (Tan Mai commune, Phu Tho province after the merger).
The work items include:
Typing the ground on an area of about 2.32 hectares.
Construct internal traffic routes for new residential areas, roads connecting households in residential areas, serving the basic travel needs of residential areas, roadbed width 13.5m, roadway width 7.5m, sidewalks 6m (both sides).
Construct a traffic route connecting the traffic system in the area to the resettlement area on the basis of the existing road (including the removal of degraded and damaged structures) with a length of about 150m.
System of intersections, roads; Brick-paved sidewalks; Road signal system.
Along with that, the contractor will construct a water supply, drainage and wastewater treatment system; electricity supply and lighting system; technical hao system.
The deadline for completing the package is 90 days from the effective date of the contract, including Saturdays, Sundays, and holidays according to regulations.