32 households donated land to carry out the 65 billion VND river embankment construction project

TRẦN TUẤN |

Ha Tinh - To implement the Ngan Sau River Bank Erosion Repair Project, 32 households in Village 2 and Village 5, Ha Linh Commune (Huong Khe) donated land with an area of ​​thousands of square meters.

According to Lao Dong Newspaper reporters, the Project to Overcome Erosion of the Ngan Sau River Bank through Village 2 and Village 5, Ha Linh Commune is currently being implemented by the Joint Venture of Hoang Long and Hoang Lai Companies with maximum machinery and human resources to speed up the construction progress after completing 100% of the site handover.

The implementation of this project is very practical for the people of village 2 and village 5, Ha Linh commune, living on the banks of the Ngan Sau river. Therefore, when the project was approved, through propaganda and mobilization by the government, the people were very supportive.

Mr. Bui Ngoc Du - Chairman of Ha Linh Commune People's Committee - said that the Ngan Sau River embankment project through Village 2 and Village 5 of Ha Linh Commune brought excitement to the people. Therefore, during the site clearance process, all 32 affected households donated land with a total area of ​​over 3,200m2.

Nguyen Anh Tuan - Director of the Project Management Board of Construction Investment of Huong Khe district - informed that the Project to overcome landslides on the banks of Ngan Sau river through village 2 and village 5 of Ha Linh commune has a length of 1.5km invested by the People's Committee of Huong Khe district.

The project has a total investment of 65 billion VND. Of which, 60 billion VND comes from the central budget to overcome the consequences of natural disasters, and 5 billion VND is counterpart capital from the People's Committee of Huong Khe district.

Du an dang duoc day nhanh tien do thi cong de kip giai ngan von Trung uong ho tro trong nam 2024. Anh: Tran Tuan.
The project is being accelerated to disburse central government support capital in 2024. Photo: Tran Tuan.

After completing the procedures and selecting the contractor, the Project will be implemented from November 1, 2024. According to the schedule, the project must be basically completed by December 31, 2024 to be able to disburse the Central Government's public investment capital in 2024; by January 31, 2025, the entire project must be completed to disburse local capital.

“Fortunately, the project received the consent of the people, who donated 100% of the land affected by the project. We only compensated for assets and trees on the land with a total cost of more than 2 billion VND. Thanks to that, we were able to hand over 100% of the site early so that the contractor could speed up the construction progress,” Mr. Tuan shared.

According to Mr. Tuan, with such a tight deadline, the joint contractor Hoang Long and Hoang Lai Company is currently focusing on speeding up the construction progress in 3 shifts and 4 crews. In favorable weather, construction will be carried out at night. In rainy and windy weather, construction of suitable items such as casting components, bending steel...

The Ngan Sau River Bank Erosion Repair Project through Village 2 and Village 5, Ha Linh Commune is one of seven natural disaster recovery projects from the Central reserve budget in 2023 being implemented in Ha Tinh.

Recently, the People's Committee of Ha Tinh province has repeatedly issued documents urging the progress of these 7 projects to promptly disburse the central government's support capital before December 31, 2024.

TRẦN TUẤN
TIN LIÊN QUAN

Requesting 3 units to report the 208,000 VND bread case at Noi Bai airport before July 11

|

The Civil Aviation Authority of Vietnam has just requested units to report the 208,000 VND banh mi case at Noi Bai airport before July 11.

Continue to reorganize mass organizations assigned by the Party and the State

|

The Party Committee of the Vietnam Fatherland Front and Central organizations will lead and direct the continued reorganization of mass associations assigned by the Party and State to operate under the Vietnam Fatherland Front, in the direction of reducing the number, streamlining the internal apparatus, and operating practically and effectively.

Buying Vietlott lottery on the day of giving birth, a worker won more than 16 billion VND

|

A man has just received the Vietlott Jackpot 2 lottery draw Power 6/55 QSMT No. 01210 with a value of more than 16 billion VND.

Mr. Thaksin declares belief in the integrity of Paetongtarn's daughter

|

Former Thai Prime Minister Thaksin Shinawatra shared his views on the situation in Thailand and the suspension of his daughter, Ms. Paetongtarn, from the position of Prime Minister.

There have been conclusions about the person who shot down the MH17 passenger plane

|

The Malaysia MH17 plane crash due to shelling in 2014, with 298 passengers on board, has been determined.

Nam Pan Hydropower Plant workers receive full wages after being reported by Lao Dong Newspaper

|

Son La - The Nam Pan 5 Hydropower Construction Workers' Team has received full salary after being reported by Lao Dong Newspaper.

Mẹ và con là hộ cận nghèo, cùng hiến đất xây trường

HƯNG THƠ - ANH VŨ |

Quảng Trị - Nhiều năm trước, bà Lan hiến đất xây trường học. Bây giờ, học sinh đông, trường chật, con trai bà Lan lại hiến thêm đất để xây trường mới.

Bản nghèo hiến đất mở đường giữ rừng nguyên sinh

Nguyễn Tùng |

Bản Bung là nơi sinh sống của gần 50 hộ dân người Dao, người Tày nằm trong lõi khu bảo tồn thiên nhiên Tát Kẻ - Bản Bung (huyện Na Hang, Tuyên Quang). Cuộc sống của đồng bào hàng chục năm cứ bình dị trôi qua dưới tán rừng nguyên sinh.

Để có thêm nhiều hộ dân thấy việc hiến đất "là vinh dự"

Hoàng Văn Minh |

Hai hộ dân tại huyện Lệ Thủy (Quảng Bình) hiến đất để phục vụ dự án cao tốc Bắc - Nam với quan điểm: “Hiến đất, góp sức cho dự án quốc gia là vinh dự“.