4 vital bridges to relieve traffic jams at the gateway to Ho Chi Minh City are about to open to traffic

TÚ QUÂN |

HCMC - The four bridges Phuoc Long, Tang Long, Tan Ky - Tan Quy and Ba Hom are expected to be completed before Lunar New Year 2025, helping to reduce traffic pressure at the gateways.

Phuoc Long Bridge

On December 18, the main items of Phuoc Long Bridge on Pham Huu Lau Street (connecting District 7 and Nha Be District) were basically completed. Currently, the contractor is focusing on completing the bridge deck and two approach roads, to ensure the progress of opening to traffic before Lunar New Year 2025.

According to the Management Board of Investment and Construction of Traffic Works in Ho Chi Minh City (investor), the Phuoc Long bridge project has completed more than 90% of the work volume.

When put into use, Phuoc Long bridge will reduce traffic load for Phu Xuan 2 bridge on Huynh Tan Phat street and contribute to improving traffic infrastructure in the South of Ho Chi Minh City.

Cau Phuoc Long da co ban hoan thien.  Anh: Anh Tu
Phuoc Long Bridge has been basically completed. Photo: Anh Tu

Phuoc Long Bridge crosses Phu Xuan canal, is 359m long, 10.5m wide, including the approach roads at both ends.

Initially, the project was implemented in the 2016 - 2019 period with a budget of nearly 400 billion VND, but then the progress was delayed, causing the total investment to increase to 748 billion VND.

Tang Long Bridge

At the Tang Long Bridge construction site (Thu Duc City), workers are working day and night to complete the left bridge branch before Lunar New Year 2025.

Currently, the left branch of the bridge has completed the installation of bridge girders, and workers are pouring concrete for the bridge deck. Many other items are also being deployed such as the drainage system, technical trenches, bridge approach roads, etc.

Cau Tang Long da noi nhip, se thong xe truoc Tet Nguyen dan 2025. Anh: Anh Tu
Tang Long Bridge has been completed and will be open to traffic before Lunar New Year 2025. Photo: Anh Tu

After the left branch is completed, the contractor will continue to build the right branch of the bridge, with the goal of completing the entire project by December 2025.

Tang Long Bridge is located on La Xuan Oai Street, started construction in 2017 with a total investment of 450 billion VND. The project's slow progress has caused the total investment capital to increase to more than 688 billion VND.

When completed, Tang Long Bridge will enhance traffic connections on La Xuan Oai Street and meet transportation needs from Ho Chi Minh City High-Tech Park to Rach Chiec River.

Tan Ky - Tan Quy Bridge

The Tan Ky - Tan Quy bridge project across Tham Luong canal in Binh Tan district is also being accelerated to open to traffic before Lunar New Year 2025. To date, the main bridge has completed more than 80% of the volume, and the approach roads at both ends of the bridge are under construction.

Du an cau Tan Ki Tan Quy. Ảnh: Anh Tu
Tan Ky - Tan Quy bridge project in November 2024. Photo: Anh Tu

This project was restarted in June 2024 after 6 years of stagnation due to problems in site clearance and investment method conversion. The project has a total length of 385m, including an 83m long bridge with 4 lanes, sidewalks and access roads at both ends.

When completed, Tan Ky - Tan Quy bridge will help reduce traffic congestion on the road connecting the three districts of Binh Tan, Tan Binh and Tan Phu with the center of Ho Chi Minh City; at the same time, the bridge will also be synchronized with the expansion of Tan Ky - Tan Quy road, contributing to eliminating the "bottleneck" in this area.

Ba Hom Bridge

The Ba Hom Bridge project on Provincial Road 10 (Binh Tan District) has now reached 80% of its volume. The contractor is focusing on completing the main bridge items, expanding the approach road and sidewalk, ensuring traffic opening before Lunar New Year 2025.

Cau Ba Hom tren Tinh lo 10 (TPHCM).  Anh: Anh Tu
Ba Hom Bridge on Provincial Road 10 (HCMC). Photo: Anh Tu

Ba Hom Bridge spans Tham Luong - Ben Cat - Nuoc Len canals with a total investment of 374 billion VND. The project was stalled due to delays in compensation and site clearance, but resumed construction after the entire site was handed over in October 2023.

When completed, Ba Hom Bridge will reduce traffic pressure for the western area of ​​the city, creating more favorable conditions for people to travel between Ho Chi Minh City and neighboring provinces.

TÚ QUÂN
TIN LIÊN QUAN

The 830 billion VND underpass in the South of Ho Chi Minh City will open to traffic on December 31

|

Ho Chi Minh City will open the remaining tunnel branch at the Nguyen Van Linh - Nguyen Huu Tho intersection (District 7) to traffic on December 31, helping to relieve traffic congestion at the southern gateway.

The largest intersection in Ho Chi Minh City is about to complete 2 important bridges

|

HCMC - Ba Dat Bridge and Giong Ong To 2 Bridge, part of the An Phu Intersection Project (Thu Duc City), with a total investment of more than VND3,400 billion, will be completed before Lunar New Year 2025.

Ho Chi Minh City opens 9-year-old unfinished road in Thu Duc

|

HCMC - After 9 years of implementation, Luong Dinh Cua Street (from Nguyen Hoang Street to Tran Nao intersection, Thu Duc City) will open to traffic before Lunar New Year 2025.

Running a red light is fined up to 20 million VND, fines for other acts increased

|

Many violations, such as running red lights, going the wrong way... will have their fines increased many times compared to before. This regulation applies from January 1, 2025.

Peaceful life in a 1,000-year-old ancient village in Nam Dinh

|

Nam Dinh - Dich Diep Trang village still preserves the ancient beauty typical of the old North.

Ministry of Transport informs about merger issue

|

The Ministry of Transport (MOT) has just informed about the merger issue in 2025.

Vital bridge clears traffic congestion in southern HCMC before opening day

|

HCMC - The Phuoc Long bridge project connecting District 7 and Nha Be district, after 4 years of construction, has now completed nearly 100% of the work volume, preparing to open to traffic on December 30.

Germany admits powerlessness against Russian hypersonic missile Oreshnik

|

Germany is virtually defenseless against Russia's Oreshnik hypersonic missile system, according to the German Foreign Ministry.

The 830 billion VND underpass in the South of Ho Chi Minh City will open to traffic on December 31

MINH QUÂN |

Ho Chi Minh City will open the remaining tunnel branch at the Nguyen Van Linh - Nguyen Huu Tho intersection (District 7) to traffic on December 31, helping to relieve traffic congestion at the southern gateway.

The largest intersection in Ho Chi Minh City is about to complete 2 important bridges

MINH QUÂN |

HCMC - Ba Dat Bridge and Giong Ong To 2 Bridge, part of the An Phu Intersection Project (Thu Duc City), with a total investment of more than VND3,400 billion, will be completed before Lunar New Year 2025.

Ho Chi Minh City opens 9-year-old unfinished road in Thu Duc

TÚ QUÂN |

HCMC - After 9 years of implementation, Luong Dinh Cua Street (from Nguyen Hoang Street to Tran Nao intersection, Thu Duc City) will open to traffic before Lunar New Year 2025.