4 key projects connecting Ho Chi Minh City and Dong Nai are behind schedule

MINH QUÂN |

Ho Chi Minh City - Expanding the Ho Chi Minh City - Long Thanh expressway, Ben Luc - Long Thanh expressway, Ring Road 3, Hanoi Highway is behind schedule, affecting the connection between Ho Chi Minh City and Dong Nai.

Expanding the Ho Chi Minh City - Long Thanh expressway

The Ho Chi Minh City - Long Thanh - Dau Giay expressway expansion project (section from Ring Road 2 to Bien Hoa - Vung Tau expressway intersection) is 22 km long, started in August 2025, with a total investment of more than 16,300 billion VND.

The section from Ring Road 2 to Ring Road 3 is expanded from 4 to 8 lanes; the section from Ring Road 3 to Bien Hoa - Vung Tau expressway is upgraded to 10 lanes. The project also builds a new 5-lane Long Thanh bridge in the direction from Ho Chi Minh City to Dong Nai.

The project is expected to be completed by the end of 2026. Long Thanh bridge is expected to close the main bridge in December 2026 and complete the remaining items in the first quarter of 2027.

Thi công mở rộng cao tốc TPHCM - Long Thành lên 10 làn xe. Ảnh: Anh Tú
Construction of expanding Ho Chi Minh City - Long Thanh expressway to 10 lanes. Photo: Mr. Tu

However, after 8 months of construction, the progress of some bidding packages has not met requirements. Package XL01 (km4 - km13+900, including Long Thanh bridge) has only reached more than 37% of the contract value, lower than the plan; package XL02 (km13+900 - km25+920) has reached about 30%, about 17% behind schedule.

According to Vietnam Expressway Corporation (VEC - the investor), the main reasons are contractor capacity, site clearance problems and a shortage of construction materials such as embankment soil and rocks.

The investor has requested contractors to increase manpower and equipment, and at the same time proposed a mechanism to adjust material prices to reduce cost pressure. At the same time, it is proposed that localities accelerate site clearance to ensure construction progress.

Ring Road 3 HCMC

The Ho Chi Minh City Ring Road 3 project has a total investment of more than 75. 300 billion VND, more than 76 km long, passing through Ho Chi Minh City, Binh Duong (formerly), Dong Nai and Long An (now Tay Ninh). The project started in June 2023, initially aiming to be completed in mid-2026.

According to the Ho Chi Minh City Traffic Construction Investment Project Management Board (the investor), the progress of the entire route through the city before the merger, more than 47 km long, currently reaches about 75%.

Thi công đoạn Vành đai 3 trên cao phía Đông TPHCM.  Ảnh: Minh Quân
Construction of Ring Road 3 elevated section in the East of Ho Chi Minh City. Photo: Minh Quan

The nearly 15 km elevated section through Thu Duc City (formerly) reached about 82%, higher than the general level. Meanwhile, the Western packages through Cu Chi, Hoc Mon and Binh Chanh (formerly) only reached about 67%, due to a shortage of sand for foundation filling and construction stone for a long time.

The investor said that contractors are under great pressure from input costs, especially rising gasoline and oil prices, leading to a simultaneous increase in sand, stone, asphalt and transportation costs.

These factors directly affect the overall progress, causing the completion milestone of the entire route to be postponed to the end of 2026. In addition to Ho Chi Minh City, some sections of Ring Road 3 through other localities are also behind schedule and are expected to be moved from completion milestones to the end of 2026.

Ben Luc - Long Thanh Expressway

Started in 2014, the Ben Luc - Long Thanh expressway has a total initial investment of 31,300 billion VND, after adjustment it is more than 29,500 billion VND.

This is a strategic traffic route connecting the East and Southwest regions, and also connecting Ho Chi Minh City with Dong Nai. However, the project has been delayed many times throughout the implementation process.

Thi công cầu Phước Khánh. Ảnh: Anh Tú
Construction of Phuoc Khanh bridge. Photo: Anh Tu

Currently, the project has opened to traffic about 32 km in Ho Chi Minh City and Dong Nai, including Binh Khanh bridge. Phuoc Khanh bridge is under construction, expected to be joined in May 2026 and opened to traffic in the third quarter of 2026.

When Phuoc Khanh bridge is completed, the entire expressway will be connected, contributing to completing the inter-regional traffic network.

Expanding Hanoi Highway and National Highway 1

Hanoi Highway and National Highway 1 are key traffic axes connecting Ho Chi Minh City with Dong Nai. The project to expand the section from Saigon Bridge to Tan Van, 15.7 km long, with a scale of 12 - 16 lanes, was implemented from 2010 with a total investment of 2,516 billion VND, and by 2016 it was adjusted to increase to more than 4,900 billion VND.

Currently, most of the route has been completed, but the section about 2.2 km long from Tan Van intersection to the new Mien Dong Bus Station has not yet been deployed due to site clearance problems.

Quốc lộ 1 (từ bến xe Miền Đông mới đến nút giao Tân Vạn) chưa mở rộng. Ảnh: Anh Tú
National Highway 1 (from the new Mien Dong bus station to Tan Van intersection) has not been expanded. Photo: Anh Tu

This area has 201 affected households, but compensation has only been paid to 55 households. The difference in land unit prices between Ho Chi Minh City and Binh Duong was previously the main reason for the project to be stalled, creating a "bottleneck" that has lasted for many years and often causes congestion.

After the merger, relevant units are completing the adjusted compensation plan, submitting it to the Ho Chi Minh City People's Committee for consideration and approval. The compensation payment is expected to be implemented from the third quarter of 2026, handing over the site and continuing project construction from the fourth quarter of 2026, completing in 2027.

MINH QUÂN
RELATED NEWS

The first elevated road in Ho Chi Minh City continues to postpone the opening date

|

Ho Chi Minh City - The elevated road belonging to the Ring Road 3 project, the eastern section, 14.7km long, 4 lanes, continues to postpone the opening date to June 30, instead of April 30.

Ho Chi Minh City rectifies vehicles carrying materials for Long Thanh expressway expansion construction

|

Ho Chi Minh City rectifies the transportation of construction materials for the Ho Chi Minh City - Long Thanh expressway after recording many inadequacies in traffic safety and environmental sanitation.

Vietnam's highest vertical cable-stayed bridge accelerates to wait for assembly after nearly 11 years

|

Ho Chi Minh City - Phuoc Khanh bridge (belonging to Ben Luc - Long Thanh expressway) has reached about 96% of the volume, and is focusing all efforts on construction waiting for completion in May 2026.

Series of limitations and shortcomings in lending and guarantee appraisal at SeABank Da Nang

|

The State Bank of Vietnam (SBV) requested SeABank Da Nang to rectify the inspection and supervision of loans after the inspection conclusion pointed out shortcomings in credit granting activities here.

Prioritize allocating resources from the budget for drought and saltwater intrusion prevention and control tasks

|

Prioritize allocating resources from the state budget for tasks of preventing and combating subsidence, landslides, flooding, drought, and saltwater intrusion.

1 against 7 to enter specialized school in Ho Chi Minh City

|

Ho Chi Minh City announced the number of registrations for the first wish for 10th grade in the 2026-2027 school year, in which the specialized school group has a high competition rate, up to 1/7.

Online public services will be evaluated by people's satisfaction

|

The draft National Standard on online public services aims to build specific indicators, taking people's satisfaction level as a measure of quality.

The first elevated road in Ho Chi Minh City continues to postpone the opening date

MINH QUÂN |

Ho Chi Minh City - The elevated road belonging to the Ring Road 3 project, the eastern section, 14.7km long, 4 lanes, continues to postpone the opening date to June 30, instead of April 30.

Ho Chi Minh City rectifies vehicles carrying materials for Long Thanh expressway expansion construction

MINH QUÂN |

Ho Chi Minh City rectifies the transportation of construction materials for the Ho Chi Minh City - Long Thanh expressway after recording many inadequacies in traffic safety and environmental sanitation.

Vietnam's highest vertical cable-stayed bridge accelerates to wait for assembly after nearly 11 years

Anh Tú |

Ho Chi Minh City - Phuoc Khanh bridge (belonging to Ben Luc - Long Thanh expressway) has reached about 96% of the volume, and is focusing all efforts on construction waiting for completion in May 2026.