Ba Ria - Vung Tau starts 10 projects to boost disbursement

Thành An |

To speed up disbursement progress, Ba Ria - Vung Tau plans to start 10 public investment projects in late 2024.

On November 15, the People's Committee of Ba Ria - Vung Tau province said that in the remaining period of 2024, the locality will start 10 new public investment projects in the area; as well as speed up the construction of ongoing projects, striving to complete the public investment disbursement plan in 2024.

Mr. Nguyen Van Tho - Chairman of the Provincial People's Committee said that in 2024, the total public investment capital in the area is more than 20,866 billion VND, of which the central budget capital is 1,747 billion VND. Although 100% of this capital has been allocated to the units, the disbursement progress up to the end of October 2024 is still quite slow, reaching only 56.35% of the plan (more than 11,758 billion VND).

The reason is that some projects are behind schedule and procedures; up to 24/37 investors have disbursed lower than the construction rate. For example, there are 89 completed projects with a total investment of more than 500.8 billion VND but only 241.48 billion VND has been disbursed; 104 transitional projects have a total investment of more than 5,759.4 billion VND but only 54.83% has been disbursed....

To promote the progress of disbursement of public investment capital this year, the Provincial People's Committee has directed functional units and working groups to proactively follow up and strengthen the implementation of their functions and tasks to support investors and promptly remove difficulties and obstacles.

Investors of projects in the site clearance and compensation stage need to quickly complete procedures and documents to submit to competent authorities for appraisal and approval in November 2024.

Cong nhan tham nhua tren du an thanh phan 3 cao toc Bien Hoa - Vung Tau vao chieu 14.11. Anh: Thanh An
Workers lay asphalt on component 3 of Bien Hoa - Vung Tau expressway project on the afternoon of November 14. Photo: Thanh An

At the same time, localities, units and investors are required to coordinate to start construction of the remaining 10/25 projects (on the list of new projects to start in 2024) in November-December 2024. In particular, in addition to civil projects such as the wastewater collection and treatment system of Phuoc Hai town; the main drainage line along National Highway 51; resettlement apartments in Thang Nhat ward..., there are also a number of key traffic projects such as two connecting road projects to Bien Hoa - Vung Tau expressway (from National Highway 56 to Vung Van intersection; from Vung Van to coastal road DT 994); expansion of Phu My - Toc Tien road.

Based on the results of public investment disbursement in 2024, investors with good results will be proposed to be commended and rewarded; as well as handling investors, Project Management Boards, organizations and individuals with low public investment disbursement. At the same time, timely replacement of officials, civil servants and public employees who are weak in capacity, slow, causing harassment and negativity in the implementation and disbursement of public investment capital will be proposed.

According to the Cai Mep - Thi Vai Regional Traffic Project Management Board, the first kilometers of the Bien Hoa - Vung Tau Expressway component 3 project (phase 1) have been paved. In 2024, the project was allocated 1,187 billion VND in capital, and has now disbursed VND 796 billion, reaching 67% (of which, the capital allocated at the beginning of the year of 500 billion VND has been fully disbursed; 487 billion VND is being disbursed, supplemented in May 2024, and 200 billion VND is being transferred in August 2024). The construction progress on site meets the schedule registered with the Ministry of Transport.

The Phuoc An Bridge project is scheduled to be completed by December 2027, and all construction packages in Ba Ria - Vung Tau are on schedule. The total construction output in 2024 is 407.42 billion VND, but only 351.37 billion VND has been disbursed.

 

Thành An
TIN LIÊN QUAN

Binh Duong competes for 50 days and nights to disburse public investment capital

|

Binh Duong province launched a 50-day emulation campaign to disburse public investment capital, striving to achieve 100% of the plan assigned by the Prime Minister.

Binh Dinh Economic Zone is about to reach the target of disbursing 100% of investment capital

|

Binh Dinh - By the end of October 2024, the Provincial Economic Zone Management Board had disbursed more than 97.64% of the total capital allocated by the province to implement projects.

Binh Duong adjusts capital for 16 projects, speeds up disbursement

|

Binh Duong province decided to internally adjust the 2024 public investment capital plan for 16 projects. At the same time, it urged investors and units to speed up capital disbursement.

Search scene for 5 missing 8th grade students in the Red River

|

Phu Tho - Authorities are mobilizing maximum manpower and equipment to the scene to search for 5 8th grade students missing in the Red River.

Police block road, control fire in Nha Trang

|

Khanh Hoa - The fire started on the third floor of a house located in the center of Nha Trang city, making rescue work difficult.

Mr. Nguyen Dinh Viet ceased to be Deputy Chairman of the Economic Committee

|

The National Assembly Standing Committee resolved to approve the dismissal of Mr. Nguyen Dinh Viet from the position of Deputy Chairman of the Economic Committee due to job transfer.

Recovery process of real estate businesses

|

HCMC - The real estate market is showing positive changes, but previous "injuries" are slowing down the recovery process of businesses.

Identities of 5 Phu Tho students missing on the Red River

|

Missing - Hien Quan Commune, Tam Nong District has quickly reported the incident of 5 8th grade students suspected of missing on the Red River.

Binh Duong competes for 50 days and nights to disburse public investment capital

ĐÌNH TRỌNG |

Binh Duong province launched a 50-day emulation campaign to disburse public investment capital, striving to achieve 100% of the plan assigned by the Prime Minister.

Binh Dinh Economic Zone is about to reach the target of disbursing 100% of investment capital

Hoài Phương |

Binh Dinh - By the end of October 2024, the Provincial Economic Zone Management Board had disbursed more than 97.64% of the total capital allocated by the province to implement projects.

Binh Duong adjusts capital for 16 projects, speeds up disbursement

ĐÌNH TRỌNG |

Binh Duong province decided to internally adjust the 2024 public investment capital plan for 16 projects. At the same time, it urged investors and units to speed up capital disbursement.