Report sent to Prime Minister; Deputy Prime Minister Tran Hong Ha; Ministry of Construction.
According to the report, to maximize the efficiency of Gia Binh airport after completion and increase airport connectivity with neighboring provinces and cities, the People's Committee of Bac Ninh province proposed a route connecting Gia Binh airport with Hanoi capital and connecting the Golden Canal Bridge to Hai Duong province with a total length of about 31.6 km located in Bac Ninh province, cross-section of the route: 120m, including:
The section from Gia Binh airport to Hanoi capital is about 22.9 km long. The section from Gia Binh airport to Kenh Vang bridge, to Hai Duong is about 8.7 km long.
The estimated investment cost in Bac Ninh province is about 40,300 billion VND.
Regarding the form and investment plan: Competent authority: Bac Ninh Provincial People's Committee; Project Contract type: Construction - Transfer contract (BT contract).
Payment method to Investors: Expected to use land funds located in Bac Ninh province.
To " complete the synchronization of international airports and connecting routes by 2026 at the latest" according to the Prime Minister's direction, the People's Committee of Bac Ninh province also proposed that the Prime Minister consider approving a number of specific policies and mechanisms to deploy the route connecting Gia Binh airport with Hanoi capital.
Some specific policies proposed by the People's Committee of Bac Ninh province are as follows:
Implement in parallel the work of investment preparation, site clearance, and implementation of the Construction Project with the adjustment and updated supplementation of the Provincial Planning.
Allow the simultaneous implementation of procedures to shorten the implementation time of other projects and PPP projects, BT contracts.
Based on the scale, route direction and the preliminary total investment approved by the Prime Minister as above, allowing the People's Committee of Bac Ninh province to decide to apply the form of direct bidding for investors before the effective date of the PPP Law (BT contract) on July 1, 2025.
Allowing the appointment of short-term bidding packages for consulting packages, packages for technical infrastructure relocation, packages for compensation, support, and resettlement of land acquisition for BT projects and counterpart projects of BT projects in Bac Ninh province.