Ben Tre urgently accelerates the conversion of waste treatment technology

Quyên Phạm |

Ben Tre is urgently speeding up the construction progress of the waste-to-energy plant, expected to start construction in the third quarter of 2025.

On June 19, a source from the reporter said that Mr. Nguyen Truc Son - Permanent Vice Chairman of the People's Committee of Ben Tre province - signed and issued Report No. 373 to the People's Council of Ben Tre province.

According to this report, currently, the Department of Agriculture and Environment of Ben Tre province is implementing the "Project to relocate households and residential areas to ensure safe environmental distance for solid waste incineration plants for power generation and waste treatment areas of Chau Thanh district", to support investors to promptly complete environmental protection procedures under the licensing authority of the Ministry of Agriculture and Environment.

In addition, the Department of Agriculture and Environment is coordinating with the People's Committee of Chau Thanh district to carry out site clearance for an expanded land area of 3.24 hectares to implement the project of a solid waste incineration plant for power generation.

In addition, the Department of Construction of Ben Tre province is currently appraising the Master Plan of the solid waste incineration plant project (the public consultation has been completed and the planning documents are being appraised).

According to the project schedule approved by the Provincial People's Committee, the project is expected to start construction in the third quarter of 2025 and start receiving and treating waste from the fourth quarter of 2026. Currently, the investor is coordinating with provincial departments and branches to urgently complete related investment procedures, ensuring the progress of the solid waste incineration plant project to generate electricity.

Ben Tre da di doi rac tu nha xuong tai Nha may xu ly rac thai Ben Tre ve bai rac Phu Hung (TP Ben Tre, tinh Ben Tre). Anh: Quyen Pham
Ben Tre has moved waste from the factory at Ben Tre waste treatment plant to Phu Hung landfill (Ben Tre city, Ben Tre province). Photo: Quyen Pham

According to the reporter's investigation, there are currently 5 landfills in operation in Ben Tre province, including Chau Binh landfill, An Thanh landfill, Cho Lach town landfill, Binh Dai town landfill and Ba Tri landfill.

Specifically, Chau Binh landfill (Giong Trom district) receives and processes about 30 tons of waste/day. An Thanh landfill (Mo Cay Nam district) receives and processes about 40 tons/day.

Cho Lach town landfill receives and processes about 25-30 tons/day. Binh Dai town landfill receives and processes about 40 tons/day.

Ba Tri landfill (Ba Tri district) receives and processes waste from localities: Ba Tri, Chau Thanh and Ben Tre city, with a volume of about 200-220 tons/day.

In addition, there are 2 centralized waste treatment plants in the province, including the Thanh Phu District Waste Treatment Plant and the Ben Tre Waste Treatment Plant.

In particular, the Thanh Phu District Waste Treatment Plant (invested by Rong Xanh Environmental Services and Trading Company Limited) has a treatment capacity of 100 tons/day. Processing technology includes classification, organic fertilizer cultivation and incineration. The plant has basically completed the investment according to the designed capacity and is currently operating a trial according to regulations.

Ben Tre Waste Treatment Plant (invested by Ben Tre Waste Treatment Joint Stock Company) is implementing a restructuring and reinvestment plan, converting it into a solid waste incineration plant for power generation.

Quyên Phạm
RELATED NEWS

Ben Tre recommends that provinces consider supporting and providing construction stone materials

|

Ben Tre - Ben Tre Provincial People's Committee proposed to the People's Committees of An Giang, Dong Nai, and Binh Duong provinces to support and provide stone materials for the construction of projects in the area.

Relocating more than 12,700 tons of waste at Ben Tre waste treatment plant

|

Ben Tre - To date, the construction unit has moved more than 12,700 tons of waste to Phu Hung landfill. It is expected that by April 27, the garbage relocation work will be completed.

Ben Tre develops a plan to handle headquarters and public assets after the arrangement

|

Ben Tre - The Provincial People's Committee directs relevant agencies to develop a plan to handle headquarters and public assets after the arrangement of commune-level administrative units in 2025.

All vehicles trapped on Gia Bac Pass in Lam Dong have been rescued

|

Lam Dong - After many efforts, the rescue forces have cleared the landslides on Gia Bac Pass, and many vehicles are being rescued.

Vietnam table tennis team practices with Russia

|

The players of the Vietnam Table Tennis Team were rubbed off before the 33rd SEA Games with the Russian Federation team.

Mr. Putin affirmed that Russia has no intention of returning to G8

|

President Putin affirmed that Russia has no intention of returning to the G8, and highly appreciated the strong rise of the Indian economy.

Preparing for the peak of the dry season, the Lo River begins to dry up

|

Tuyen Quang - Although not yet the peak of the dry season, many upstream areas of the Lo River have begun to dry up, exposing underground rock covers.

Another deep flooding point on National Highway 1 through Lam Dong

|

Lam Dong - Floodwaters caused deep flooding at km1700 of National Highway 1, causing traffic congestion.

Ben Tre recommends that provinces consider supporting and providing construction stone materials

Quyên Phạm |

Ben Tre - Ben Tre Provincial People's Committee proposed to the People's Committees of An Giang, Dong Nai, and Binh Duong provinces to support and provide stone materials for the construction of projects in the area.

Relocating more than 12,700 tons of waste at Ben Tre waste treatment plant

Thành Nhân |

Ben Tre - To date, the construction unit has moved more than 12,700 tons of waste to Phu Hung landfill. It is expected that by April 27, the garbage relocation work will be completed.

Ben Tre develops a plan to handle headquarters and public assets after the arrangement

Thành Nhân |

Ben Tre - The Provincial People's Committee directs relevant agencies to develop a plan to handle headquarters and public assets after the arrangement of commune-level administrative units in 2025.