On June 10, Mr. Tran Ngoc Tam - Chairman of Ben Tre Provincial People's Committee - conducted a field survey and inspected the construction progress of construction package No. 03 of the Road project from Giao Long Port to Phu Thuan Industrial Park (DT.DK.07), Chau Thanh - Binh Dai inter-district.

According to the report of the investor of construction package No. 03 of the Road project from Giao Long port to Phu Thuan industrial park, up to now, 150/150 households have handed over the site. The volume of work performed at the site has been completed at about 62%, estimated at 67 billion VND.
However, according to the investor of construction package No. 03 of the Road project from Giao Long Port to Phu Thuan Industrial Park (DT.DK.07), Chau Thanh - Binh Dai inter-district is facing difficulties due to prolonged storms affecting the implementation and gathering of organic excavation soil to continue construction of the next items. In addition, the increasingly scarce stone materials also greatly affect the project's completion progress.

Mr. Tran Ngoc Tam - Chairman of Ben Tre Provincial People's Committee - requested the investor and construction unit to urgently construct, increasing the number of shifts to 4 teams to basically complete the project on the occasion of the National Day holiday on September 2, 2025.
Chairman of Ben Tre Provincial People's Committee Tran Ngoc Tam said that Ben Tre Provincial People's Committee has sent a document to the People's Committees of An Giang, Dong Nai, and Binh Duong provinces to consider supporting and providing construction stone materials for the locality to construct projects in Ben Tre province.