Binh Duong speeds up disbursement of public investment capital

Đình Trọng |

Despite being proactive from the beginning of the year, the disbursement of public investment capital in Binh Duong has not yet reached the set target. Binh Duong provincial leaders are requesting to speed up the disbursement of public investment capital.

Slow capital disbursement progress, many projects unfinished

Binh Duong's 2024 public investment plan with state budget capital is 22,000 billion VND. According to the socio-economic situation report of Binh Duong Provincial People's Committee, as of early September 2024, the total disbursed value of public investment capital in Binh Duong was only 5,894 billion VND, reaching 28.1% of the plan assigned by Binh Duong Provincial People's Council (in the same period last year, it reached 38.3% of the plan), reaching 39.6% of the plan assigned by the Prime Minister.

According to records, currently, a number of key transport infrastructure projects in Binh Duong are stalled and behind schedule. Notably, the project to upgrade and expand National Highway 13, about 13km long, started in April 2022 and is still in disarray. The site clearance work has not been completely completed, and compensation is still being paid to relocate households and relocate the power grid. When the site is cleared, the construction will be synchronized and accelerated. The Ho Chi Minh City Ring Road 3 project passing through Binh Duong has a relatively high progress in site clearance compensation. However, construction and installation have not met expectations.

Mr. Nguyen Huu Tuan - Deputy Director of Binh Duong Department of Transport - said that the construction package of Binh Chuan intersection has just been completed, reaching 123/490 billion VND (25%) compared to the contract volume. The Binh Goi bridge package has been completed, reaching 269/569 billion VND, reaching 47% compared to the contract volume. The construction package from Binh Chuan intersection to Saigon River has only reached 11.2% compared to the contract volume. The disbursement of construction and installation for the entire project has so far only spent 1,412/3,237 billion VND (43.6%). Two other major traffic projects are Ho Chi Minh City Ring Road 4 through Binh Duong province, 47.5km long, and Ho Chi Minh City - Thu Dau Mot - Chon Thanh Expressway through the province, about 52km long, expected to start construction at the end of April 2024, but now has to be postponed, expected to start construction in November 2024. Therefore, this also generally affects the progress of disbursement of public investment capital of the province.

Strengthening leadership responsibility

To accelerate the disbursement of public investment capital, the leaders of the Provincial People's Committee have directed departments and branches to regularly inspect, supervise, and take strict measures to handle cases of prolonging project implementation time due to weak capacity of contractors or consulting units. Require investors to fully implement and ensure the time of periodic and ad hoc reporting regimes as required by competent authorities to serve the advice work of managing public investment plans; Further strengthen the role and responsibility of heads of branches and localities in directing and removing difficulties and obstacles in disbursing public investment capital, especially obstacles related to site clearance work...

According to Mr. Vo Anh Tuan - Chief of Office of Binh Duong Provincial People's Committee, the province has assigned the Department of Planning and Investment to preside over and coordinate with the Department of Finance and related agencies, units and localities to urgently advise the Provincial People's Committee to issue a plan to implement the peak campaign "promoting disbursement of public investment capital", striving for the highest disbursement.

Đình Trọng
RELATED NEWS

The burden of work is increasing, teachers have high expectations for the new salary policy

|

The salary adjustment from 2026 is meaningful in recognizing silent contributions, while encouraging teachers to continue to stick with the profession.

International beauties, used cars add sparkling beauty to Da Lat streets

|

Da Lat - Da Lat City of Thousands of Flowers is more sparkling with the participation of nearly 80 international beauties and dozens of ancient cars participating in the parade through the streets.

Electricity says Ecohome Nhon Binh lacks cooperation in power generation

|

Gia Lai - Regarding the prolonged power outage at Ecohome Nhon Binh Social Housing Apartment, the Electricity sector said it has provided full support but the repair process is still very slow.

Thien Khoi FC crowned champion of the 2025 National 7-a-side Football Cup

|

Defeating Dai Tu in a dramatic final match, Thien Khoi FC became the champion of the 2025 Hyundai Thanh Cong Cup National 7-a-side Football Cup (VSC-S5).

Updated gold price at the end of session 7.12: gloomy end of the week

|

Updated gold price at the end of the session on December 7: Gold prices last week decreased simultaneously in both domestic and international markets.

Viet Duc and Bach Mai Hospitals, Facility 2, officially operate from December 19, 2025

|

Bach Mai Hospital, Facility 2 in Ninh Binh, will officially come into phase 1 operation from December 19, 2025 according to the Resolution just issued by the Hospital Party Committee.

Durian died en masse after floods, many households along the Dong Nai river in Lam Dong lost billions

|

Lam Dong - Durian growers along the Dong Nai River in Cat Tien and Cat Tien 2 communes are in trouble as billion-dollar durian gardens have died en masse after floods.

The secret for mountainous districts to disburse nearly 80% of public investment capital

Đặng Tình |

Hoa Binh - Construction projects in Kim Boi district are being accelerated to ensure the disbursement plan for public investment capital.

Can Tho will replace weak officials in public investment management

Phong Linh |

Can Tho - In the solution to promote disbursement of public investment capital in the last months of the year, Can Tho will strengthen discipline and replace officials with weak capacity.

Thanh tra Bình Dương chỉ ra vi phạm ở 3 dự án đầu tư công

ĐÌNH TRỌNG |

Thanh tra tỉnh Bình Dương đã thanh tra 3 dự án đầu tư công ở thành phố Thủ Dầu Một, giai đoạn 2021-2023, và chỉ ra các vi phạm liên quan.