The Ministry of Construction guides the determination of project management cost coefficients according to current regulations

Xuyên Đông |

On the Government Portal, the Ministry of Construction has just instructed citizens to determine the project management cost coefficient according to current regulations.

Mr. L.D.P reflected that the Project Management Board of the area where he works was assigned by the Provincial People's Committee as the investor to implement Project A using capital from the state budget. The project management board of the area directly manages the project (not hiring a consulting organization to participate in project management). The project approval date is October 2025.

According to the provisions of Point 1.4, Section 1, Chapter I, Part II, Appendix VIII of Circular No. 12/2021/TT-BXD dated August 31, 2021 of the Minister of Construction promulgating the construction norms (amended and supplemented by Point 2, Appendix V of Circular No. 09/2024/TT-BXD dated August 30, 2024):

"Instructions for applying project management cost norms:

In case the investor uses their legal status and the affiliated professional apparatus that meets the conditions and capacity to directly manage the project (not hiring a consulting organization to participate in project management) in the form of the investor organizing project management in the Decree detailing a number of contents on the management of construction investment projects of the Government, the cost of project management shall be determined according to the norms issued in Table 1.1 attached to this Circular and adjusted with coefficient k = 0.8".

Mr. P asked, according to the above regulations, the project management cost coefficient for project A is determined to be k = 0.8 or k = 1.0?

The Ministry of Construction responds to this issue as follows:

For construction investment projects with cost management according to Decree No. 10/2021/ND-CP dated February 9, 2021 on management of construction investment costs, project management costs are determined according to the provisions of Point 1.4, Section 1, Chapter I, Part II of Appendix No. VIII issued with Circular No. 12/2021/TT-BXD (amended and supplemented by Point 2, Appendix V of Circular No. 09/2024/TT-BXD).

In case the specialized construction investment project management board is established according to the provisions of Point a, Clause 1, Article 24 of Decree No. 175/2024/ND-CP dated December 30, 2024 of the Government to perform the functions, tasks and powers of the investor in organizing the management of assigned projects as prescribed, the project management cost is determined according to the norms in Circular No. 12/2021/TT-BXD and the coefficient is applied 1.0.

Xuyên Đông
RELATED NEWS

The Ministry of Construction responds to voters about the proposal for a 16-year-old student to take a driver's license exam

|

The Ministry of Construction has just responded to An Giang voters' petition to allow 16-year-old students to take a driver's license exam.

In 2025, the Ministry of Construction has set many records for the project

|

Speaking at the summary conference of the Ministry of Construction on December 21, Deputy Prime Minister Tran Hong Ha emphasized that in 2025, the Ministry has set many records for the project.

The Ministry of Construction informs about the number of kilometers of highways to be built by 2025

|

The Ministry of Construction has just issued a summary report for 2025, which provides information on the implementation of expressway construction.

VinSpeed prioritizes quality before thinking about price

|

Currently, many countries have cheap high-speed railway technology, but VinSpeed still chooses German technology for cooperation.

Hanoi cuts sidewalks at a series of black spots of traffic jams, people hope to complete soon

|

Hanoi - Having to take a detour to avoid congestion, people expect the sidewalk section of Le Van Luong - Hoang Minh Giam - Nguyen Tuan streets to be completed soon.

Many national relics are devastated

|

Ca Mau - Many national relics and provincial relics have deteriorated after being recognized due to slow restoration and exploitation, facing the risk of becoming ruins.

Honoring outstanding individuals and groups in the patriotic emulation movement

|

The National Patriotic Emulation Congress will honor and commend outstanding individuals and groups in patriotic emulation movements.

Being honked in the country, consulting customers to go abroad for stem cells

|

N2 Dermatology Clinic advertises stem cells, organizes customers to go to Japan to perform services, earning hundreds of millions of VND per treatment.

The Ministry of Construction responds to voters about the proposal for a 16-year-old student to take a driver's license exam

Xuyên Đông |

The Ministry of Construction has just responded to An Giang voters' petition to allow 16-year-old students to take a driver's license exam.

In 2025, the Ministry of Construction has set many records for the project

Xuyên Đông |

Speaking at the summary conference of the Ministry of Construction on December 21, Deputy Prime Minister Tran Hong Ha emphasized that in 2025, the Ministry has set many records for the project.

The Ministry of Construction informs about the number of kilometers of highways to be built by 2025

Xuyên Đông |

The Ministry of Construction has just issued a summary report for 2025, which provides information on the implementation of expressway construction.