The project to build the new Phong Chau bridge - National Highway 32C, Phu Tho province is implemented according to the Emergency Construction Order, Thang Long Project Management Board is the project investor, the construction unit is Army Corps 12 - Truong Son Construction Corporation.

According to the design, Phong Chau Bridge has a length of about 652.88 m. In particular, the length of the bridge is about 383.3 m (to the tail of the abutment), the two -end road section of the bridge connecting to the current situation of Lam Thao on 113.8 m, Tam Nong side is about 155.78 m ...
Since its implementation, Truong Son Construction Corporation has organized overtime, increased shifts, during holidays, and during Tet... The image of cadres, engineers, workers, and laborers working through Tet has left a deep impression on local people.

Coming to the Phong Chau bridge area in Bong Lang area, Phung Nguyen commune, Lam Thao district in the first days of April, Lao Dong Newspaper reporters recorded that from the shore to the river, the construction site was bustling with the sound of machinery and vehicles.
In particular, after completing the bored pile drilling (previously constructed ahead of schedule), the pillars of the new Phong Chau bridge project have begun to take shape. Engineers and workers are pouring concrete for the pedestal, pillar body...

Mr. Bui Van Tuyen - owner of a business shop at the Phong Chau bridgehead in Van Xuan commune, Tam Nong district - shared: "I hope the new bridge will be completed every day. With such rapid progress, we are very happy and feel grateful to the soldiers and workers at the construction site. They have worked regardless of the sun or rain, day or night, during holidays and holidays...".

Among the new bridge piers, the construction of 2 piers under the Red River (T4 and T5) faces many difficulties when the river is narrow, the flow rate is large, and the geology is complicated...
However, with experience and tireless efforts, the construction unit has achieved the set goal of completing bored piles, pouring concrete for the embankment and pillars before the minor flood occurred.