The VND18,000 billion expressway in Lam Dong faces problems in site clearance

LAM HỒNG |

Lam Dong Provincial People's Committee has just worked with Deo Ca Group on the Tan Phu - Bao Loc expressway project. The project is facing difficulties in marking site clearance.

On July 31, Lam Dong Provincial People's Committee held a working session with representatives of Deo Ca Group and related units on the implementation of the Tan Phu - Bao Loc expressway project.

Accordingly, the Tan Phu - Bao Loc expressway project was approved by Lam Dong Provincial People's Committee in early June with a total investment of nearly VND18,000 billion. This expressway starts in Tan Phu district (old), Dong Nai province, ends in Bao Loc city (old), Lam Dong province.

The Tan Phu - Bao Loc Expressway has a total length of 65.88km. Of which, the section in Dong Nai province is 11.91km long, the section in Lam Dong province is 53.97km long.

The Tan Phu - Bao Loc Expressway is designed with a 22m wide roadbed, with 4 lanes, expected to be completed and put into operation by the end of 2027.

At the meeting, Mr. Nguyen Thanh Chuong, representative of Lam Dong Traffic Works Management Board, said that the project is currently facing difficulties in marking site clearance.

Some communes and wards where the project passes through have not yet carried out procedures to determine specific land prices for compensation for site clearance. The project management boards in the area that are investors in resettlement area projects have not yet issued appointment decisions or seals to resolve the work according to their authority.

According to the representative of the Lam Dong Traffic Construction Management Board, currently, due to some problems, the authorities have not transferred nearly 420 billion VND to Dong Nai province to carry out compensation, site clearance, and resettlement for the project.

Mr. Le Quynh Mai, Vice Chairman of the Board of Directors of Deo Ca Group, representative of the project proposal investor consortium, said that due to some changes, the Tan Phu - Bao Loc expressway project only has this group participating.

The Tan Phu - Bao Loc Expressway passes through mountainous terrain, with a high total investment. Therefore, the project's payback period is nearly 24 years, longer than other expressways. A representative of Deo Ca Group proposed that the competent authority adjust the capital ratio from the State budget so that this unit can reduce the payback period to less than 20 years.

At the meeting, Vice Chairman of Lam Dong Provincial People's Committee Nguyen Hong Hai requested the Lam Dong Traffic Construction Management Board to coordinate with relevant units to carefully review legal procedures, ensuring regulations to implement resettlement areas.

At the same time, he requested this unit to urgently deploy the approval of bidding documents and select investors according to regulations.

The leaders of Lam Dong province also requested departments, branches and sectors of Lam Dong province to coordinate with Deo Ca Group to resolve the proposals of this unit; determine the project land area overlapping with other planning to report to Lam Dong Provincial People's Committee for resolution.

LAM HỒNG
RELATED NEWS

Agree to expand the entire North-South expressway in the East under the PPP method

|

The Deputy Prime Minister agreed to the plan to expand the entire North-South expressway in the East; requested that before August 4, the Prime Minister be informed of the expansion plan.

20 inspections by the Prime Minister and Deputy Prime Minister to accelerate the progress of 3,000 km of expressway

|

The Prime Minister requested to continue accelerating, making a breakthrough to strive to have 2,476 km of expressway by August 19 and exceed the target of 3,000 km of expressway by the end of 2025.

Taking advantage of the dry hours, speeding up the construction of the billion-dong expressway in the West

|

Can Tho - Workers in the packages take advantage of every dry hour, continuously constructing to ensure the progress of the Chau Doc - Can Tho - Soc Trang expressway project.

Racing against time, resolutely completing the target of 3,000km of highway

|

The Prime Minister emphasized the spirit of racing against time, only discussing work, not retreating, and resolutely completing the goal of having at least 3,000km of expressway by the end of 2025.

Vietnam's manufacturing industry flourishes as orders increase again in July

|

The PMI of Vietnam's manufacturing sector reached 52.4 points in July, the highest level in nearly a year, thanks to increased new orders despite exports still being affected by tariffs.

More than 1,000m3 of rock and soil buries National Highway 279 from Lao Cai to Lai Chau

|

Lao Cai - A landslide appeared on National Highway 279 after heavy rain, causing the traffic route from Nam Xe commune to Muong Than commune (Lai Chau province) to be cut off.

Deputy Prime Minister talks about implementing restructuring of SCB Bank

|

The Deputy Prime Minister said that in the past, credit institutions have been restructured very strongly, and SCB Bank is being restructured.

List of enterprises expected to honor "Outstanding Enterprises for Workers" in 2025

|

The 2025 "Outstanding Enterprise for Workers" Award is a prestigious socio-political event chaired by the Vietnam General Confederation of Labor, in coordination with the Ministry of Home Affairs and the Vietnam Federation of Commerce and Industry (VCCI), assigned to Lao Dong Newspaper to directly implement.

Agree to expand the entire North-South expressway in the East under the PPP method

PHẠM ĐÔNG |

The Deputy Prime Minister agreed to the plan to expand the entire North-South expressway in the East; requested that before August 4, the Prime Minister be informed of the expansion plan.

20 inspections by the Prime Minister and Deputy Prime Minister to accelerate the progress of 3,000 km of expressway

PHẠM ĐÔNG |

The Prime Minister requested to continue accelerating, making a breakthrough to strive to have 2,476 km of expressway by August 19 and exceed the target of 3,000 km of expressway by the end of 2025.

Taking advantage of the dry hours, speeding up the construction of the billion-dong expressway in the West

PHƯƠNG ANH |

Can Tho - Workers in the packages take advantage of every dry hour, continuously constructing to ensure the progress of the Chau Doc - Can Tho - Soc Trang expressway project.

Racing against time, resolutely completing the target of 3,000km of highway

PHẠM ĐÔNG |

The Prime Minister emphasized the spirit of racing against time, only discussing work, not retreating, and resolutely completing the goal of having at least 3,000km of expressway by the end of 2025.