Accelerating the progress of bringing the Khanh Hoa - Buon Ma Thuot expressway closer to the finish line

PHAN TUẤN |

Dak Lak - In early July, the construction atmosphere on the Khanh Hoa - Buon Ma Thuot expressway is taking place urgently.

In Package No. 3 (under Component Project 3), along with the construction of the roadbed, An Nguyen contractor is simultaneously installing a fence, guardrail and a traffic safety system.

According to Mr. Le Quoc Thang - Deputy Director of An Nguyen Company Limited, the construction unit of the section Km10.+500 to Km108+000 - to date, the output has reached more than 63% of the plan.

Of which, 4.4/6.5km of semi-hollow asphalt concrete has been paved; 6cm thick C19 tight asphalt concrete has also reached 4.4/6.5km, basically meeting the progress.

At the construction site, workers work in "3 shifts, 4 teams". Mr. Y Tien - a fence construction worker shared: "For more than a month now, we have been working through the sun with a high determination, striving to complete the package soon".

Currently, workers are completing the following items: Closing soft guardrails in the section Km104+000 - Km108+000; Zinc barrier pillars in the section Km105+000 - Km107+600; reinforcing slopes, installing more than 100m of fence and guardrail.

The intelligent transportation system (ITS) is also being installed with cable tanks and COD pipes at two sections Km10.10+500 - Km104+800 and Km107+600 - Km108+000.

Mr. Thang said that in July, the contractor will complete all layers of cement reinforced gravel, asphalt concrete pavement, installation of soft guardrails, barbed wire fences, as well as complete the cable tank and COD system of the entire route.

The entire Component Project 3 is over 48km long, with a total investment of over VND6,000 billion, invested by the Dak Lak Province Traffic Construction Investment and Agriculture and Rural Development Project Management Board.

The project is divided into 3 construction packages with the participation of 7 contractors, currently deployed 41 construction teams, mobilizing 462 equipment and 765 human resources. The total volume of the entire route has reached 54.13% of the contract value.

However, compared to the completion date of August 30, 2025, the project is still behind schedule. Among the contractors, Son Hai (package 01) and An Nguyen (package 03) are the two units that are basically closely following the progress.

The leader of the Project Management Board said that they are urging contractors to speed up and take advantage of favorable weather to compensate for the construction volume.

For contractors who are slow for a long time, we will consider cutting the volume to ensure the overall progress of the project, emphasized the leader of the Project Management Board.

PHAN TUẤN
RELATED NEWS

Ben Luc - Long Thanh Expressway Service Fee To be collected

|

Dong Nai - According to Vietnam Expressway Corporation (VEC), the Ben Luc - Long Thanh Expressway is expected to collect service fees in August 2025.

Four cars collided on the Mai Son - QL45 highway

|

On the morning of July 5, at Km291+100 of the North-South Expressway, Cao Bo - Mai Son section ( bordering Ninh Binh and Thanh Hoa), a series of accidents occurred involving at least 4-5 cars.

Opening a road to take a stroke driver on the highway to the hospital for emergency care

|

Discovering Hoang Viet Nam driver unconscious in the cabin on the Phap Van - Cau Gie Expressway, traffic police cleared the way to take the victim to the emergency room.

The Ministry of Construction responds to the proposal to upgrade National Highway 279 to a highway

|

The Ministry of Construction has just responded to voters in Lang Son province's proposal to upgrade a section of National Highway 279 to a highway.

Proposal to reduce the minimum land plot separation area for some areas

|

Ho Chi Minh City - HoREA proposes considering reducing the minimum area for residential land plot separation in some areas to support housing access.

The domain name "ad.vn" was chosen to serve digital content promotion and creation

|

The domain name "ad. vn" is added to the national domain name system, aimed at digital content promotion, marketing, design and creation activities.

Stock market recovers, oil and gas stocks still heavily profit-taken

|

Oil and gas stocks simultaneously turned to adjust due to increased profit-taking pressure, although the stock market still maintained good recovery momentum.

Personalized gifts take the throne, the traditional gift market is quiet on March 8th

|

Near March 8th, a new trend appeared in the gift market in Hanoi. Custom-designed gifts are popular, while traditional gifts have stagnated.

Ben Luc - Long Thanh Expressway Service Fee To be collected

HÀ ANH CHIẾN |

Dong Nai - According to Vietnam Expressway Corporation (VEC), the Ben Luc - Long Thanh Expressway is expected to collect service fees in August 2025.

Four cars collided on the Mai Son - QL45 highway

Trần lâm |

On the morning of July 5, at Km291+100 of the North-South Expressway, Cao Bo - Mai Son section ( bordering Ninh Binh and Thanh Hoa), a series of accidents occurred involving at least 4-5 cars.

Opening a road to take a stroke driver on the highway to the hospital for emergency care

Việt Dũng |

Discovering Hoang Viet Nam driver unconscious in the cabin on the Phap Van - Cau Gie Expressway, traffic police cleared the way to take the victim to the emergency room.

The Ministry of Construction responds to the proposal to upgrade National Highway 279 to a highway

Xuyên Đông |

The Ministry of Construction has just responded to voters in Lang Son province's proposal to upgrade a section of National Highway 279 to a highway.