Dong Dang - Tra Linh expressway is becoming more and more complete

Tân Văn |

Cao Bang - After more than 2 years of construction, the Dong Dang - Tra Linh expressway is becoming more and more complete.

After more than 2 years of implementation, the Dong Dang (Lang Son) - Tra Linh (Cao Bang) expressway project is entering an acceleration phase as many important items gradually take shape.

To date, phase 1 of the project has reached about 75% of the construction contract value, and more than 60 km of the route has been asphalted.

In the early days of July, reporters' records showed that the construction atmosphere at the Dong Dang - Tra Linh expressway construction site was urgent.

Tuyến cao tốc có 4 hầm xuyên núi. Ảnh: Tân Văn
The expressway has many tunnels through the mountains. Photo: Tan Van

Along the route, hundreds of machines are operating continuously, workers' groups and teams work shifts day and night to speed up progress.

According to the project enterprise, there are currently 132 construction teams being deployed simultaneously with more than 2,000 engineers, workers and about 1,400 machines and equipment.

Units maintain construction according to the motto "3 shifts, 4 crews", taking advantage of favorable weather conditions to compensate for progress and complete items according to plan.

Up to this point, the construction output value of phase 1 has reached about 75% of the construction contract. Notably, about 60 km from Dong Dang to Dong Khe has completed asphalt concrete paving on one side of the route.

This is considered an important milestone, creating a premise to complete phase 1 of 93 km according to the 22 m wide roadbed scale by the end of 2026.

Diện mạo hoàn chỉnh của tuyến đường ngày một rõ hơn. Ảnh: Tân Văn
The complete appearance of the road becomes clearer and clearer. Photo: Tan Van

In parallel with accelerating the construction of phase 1, items belonging to phase 2 are also being implemented.

Accordingly, the technical design dossier has been completed by the consulting unit and submitted for appraisal for 85.3/121 km of the entire route. Roadbed expansion work is also being carried out simultaneously with a construction value of nearly 500 billion VND.

According to engineer Nguyen Duc Tuan, after more than two years of sticking to the construction site, the appearance of Cao Bang province's first expressway has changed significantly.

Looking from above, the shape of the first modern expressway of Cao Bang province has become clear," Mr. Tuan shared.

The project enterprise said it is focusing all resources to complete about 62 km from Dong Dang to Dong Khe at a roadbed width of 22 m by December 2026, creating favorable conditions for the completion of the entire phase 1.

Đi qua rất nhiều hình thái địa hình nên khi hoàn thành, Đồng Đăng - Trà Lĩnh có thể lọt top những tuyến cao tốc có phong cảnh 2 bên đẹp nhất. Ảnh: Tân Văn
Going through many types of terrain, when completed, Dong Dang - Tra Linh can be in the top of the expressways with the most beautiful scenery on both sides. Photo: Tan Van

Not only those who directly construct, local people also expect the expressway to be put into operation soon.

Mr. Nong Van Trong, Dong Khe commune, said that every day witnessing the project being completed is another time for people to be excited.

According to him, when the road is completed, travel between Cao Bang and Lang Son, Hanoi and other localities will be more convenient, opening up many opportunities for economic development, trade and tourism.

The Dong Dang (Lang Son) - Tra Linh (Cao Bang) expressway project has a total length of more than 121 km, invested in two phases.

In which, phase 1 is 93.35 km long, from the intersection connecting the Huu Nghi - Chi Lang route to Cao Bang province, started in early 2024 with a total investment of more than 14,331 billion VND, implementation time of 36 months.

On the construction site of the trillion-dong expressway in the border region. Video: Tan Van

Phase 2 will expand the roadbed section from Km0 to Km93+300 to 22 m and invest in a new section from Km93+300 to Km121, expected to be completed in 2028.

The project is implemented by a consortium of Deo Ca Group, ICV Vietnam Investment and Construction Joint Stock Company, Deo Ca Transport Infrastructure Investment Joint Stock Company (HHV) and Construction Joint Stock Company 568 in the form of public-private partnership (PPP), BOT contract.

When completed, the Dong Dang - Tra Linh expressway will connect with the Huu Nghi - Chi Lang and Bac Giang - Lang Son expressways, forming an important external expressway axis of the Northeast region.

The route is expected to shorten travel time, reduce logistics costs, promote trade through the border gate area, and create motivation for socio-economic development for Cao Bang and the Northeast provinces.

Tân Văn
RELATED NEWS

Cao Bang allocated nearly 98 hectares of land to build Dong Dang - Tra Linh expressway

|

Cao Bang - The province has just issued a decision to allocate land for phase 1 to implement the Dong Dang - Tra Linh expressway construction investment project.

Technical opening of the 62km section of Dong Dang - Tra Linh expressway on May 19

|

Cao Bang - The Minister of Construction has just inspected the construction site of the Dong Dang - Tra Linh expressway before the technical opening deadline of phase 1.

Dong Dang - Tra Linh expressway will be invested in completing emergency stop lanes

|

Cao Bang - Phase 2 of the expressway project will have a complete 22m roadbed invested, with emergency stop lanes on both sides.

Garbage is partially cleaned up, residents of Imperia Garden apartment building still suffer from the stench

|

Hanoi - The situation of garbage congestion at Imperia Garden apartment building (Thanh Xuan ward) has changed. However, the amount of accumulated garbage and stench still make residents worried.

Hundreds of workers collectively stop working to petition about welfare regimes

|

Thanh Hoa - Hundreds of workers at Long Yi Vietnam Footwear Co., Ltd. have collectively stopped working to petition about welfare regimes.

Ho Chi Minh City buses are free of tickets, passenger volume increases by 14% in just one day

|

Ho Chi Minh City - The bus ticket exemption policy in Ho Chi Minh City has initially been effective when the number of passengers increased by 14% after only one day of implementation.

HCMC must glorify Uncle Ho's name with new achievements

|

Ho Chi Minh City must glorify Uncle Ho's name with new achievements, new values, and new contributions to development.

Red Trade Union - the core uniting the worker force in the early years of the revolution

|

On February 3, 1930, the Communist Party of Vietnam was established. Under the leadership of the Party, the Red General Confederation of Labor gathered the force of workers and boatmen, the main force of the Vietnamese revolution, creating the Xo Viet Nghe Tinh rise 1930-1931.

Cao Bang allocated nearly 98 hectares of land to build Dong Dang - Tra Linh expressway

Tân Văn |

Cao Bang - The province has just issued a decision to allocate land for phase 1 to implement the Dong Dang - Tra Linh expressway construction investment project.

Technical opening of the 62km section of Dong Dang - Tra Linh expressway on May 19

Tân Văn |

Cao Bang - The Minister of Construction has just inspected the construction site of the Dong Dang - Tra Linh expressway before the technical opening deadline of phase 1.

Dong Dang - Tra Linh expressway will be invested in completing emergency stop lanes

Tân Văn |

Cao Bang - Phase 2 of the expressway project will have a complete 22m roadbed invested, with emergency stop lanes on both sides.