Quang Ngai - Hoai Nhon Expressway worth VND20400 billion, sprinting to the finish line by the end of 2025

VIÊN NGUYỄN |

With 79 days left, the Quang Ngai - Hoai Nhon expressway project must be completed according to the direction of the Prime Minister.

The sprint stage

The North-South Expressway Construction Investment Project, Quang Ngai - Hoai Nhon section, has a total investment of more than VND 20,400 billion (of which the construction value is nearly VND 14,500 billion), with a length of 88 km, passing through the provinces of Quang Ngai (60.3km) and Gia Lai (27.7km).

This is the largest project of the 12 component projects. The route has 3 tunnels across the mountain including tunnel No. 1 610m long, tunnel No. 2 698m long and tunnel No. 3 3,200m long, along with 77 bridges, 586 culverts, 81 underpasses for people.

According to the Government's direction, the project must be completed by the end of 2025. At this time, construction units are mobilizing maximum machinery and human resources to speed up the project's progress.

Cao toc Quang Ngai - Hoai Nhon du kien hoan thanh vao cuoi nam 2025. Anh: Vien Nguyen
The Quang Ngai - Hoai Nhon Expressway is expected to be completed by the end of 2025. Photo: Vien Nguyen

On October 14, speaking with a reporter from Lao Dong Newspaper, a representative of Deo Ca Group (the lead contractor of the consortium) said that 50 50% of construction teams with 3,000 personnel and 1,100 equipment are being deployed at the construction site. Total output to date has reached about 11,500 billion VND, equivalent to 86% of the total volume.

Regarding the road, the crushed stone aggregate has been completed 100%, and about 78 km of asphalt has been paved. According to the plan, the asphalt concrete construction is expected to be completed by the end of October 2025. Regarding the bridge, there are 77 bridges on the route, all bridges have completed the lower structure; girder casting; girder installation and are constructing the bridge deck.

Regarding the tunnel, tunnels 1 and 2 have basically completed the construction and installation of electromechanical equipment and a smart traffic system. tunnel No. 3 has dug through 2 tunnels, and is constructing concrete for tunnel lining and roadbed.

Regarding production, the assembly of traffic safety components has reached about 100% of output. Currently, the construction of safety nets on both sides of the route has been completed, and the installation of guardrails, median strips, signs, etc. is underway.

Not enough work during the day, take advantage of working at night

Mr. Tran Van Chi - Executive Director of the XL1 package said that up to now, the contractor has implemented over 90% of the package. Currently, the contractor is focusing on implementing the construction of signs, painting road markings, etc. All are trying to speed up the progress to complete the XL1 package as planned.

According to the reporter's records, in the XL2 package of more than 27km and the XL3 package of more than 30km, the working atmosphere is very bustling. Each convoy of trucks, concrete mixer trucks, excavators, bulldozers, etc. operated non-stop. A bit hot from the ground, the engine and machinery blown out of the tunnel, but could not stop the urgent labor of thousands of workers and engineers who were working day and night.

Thi cong hang muc ham tren tuyen cao toc Quang Ngai - Hoai Nhon. Anh: Vien Nguyen
Construction of the tunnel on the Quang Ngai - Hoai Nhon expressway. Photo: Vien Nguyen

On October 10, 2025, the Government Office issued a document conveying the direction of Deputy Prime Minister Nguyen Hoa Binh on accelerating the implementation progress of the Quang Ngai - Hoai Nhon Component Project.

Permanent Deputy Prime Minister Nguyen Hoa Binh requested the Provincial Party Secretary and Chairman of the People's Committee of Quang Ngai province to focus on resolving and handling the contents under their authority in accordance with the direction of the Prime Minister.

Resolutely directing functional agencies and local authorities at all levels to focus on resolving difficulties and problems to hand over the entire project site in October 2025, in which priority is given to the main asphalt concrete pavement locations before October 15, 2025; be responsible to the Government and the Prime Minister if there are further delays...

According to the contract, the project completion deadline is August 2026, however, contractors are striving to complete before December 31, 2025, 8 months ahead of schedule. When completed, the expressway will not only contribute to reducing pressure on National Highway 1, shortening travel time, but also open up opportunities for economic and social development for the South Central region, especially Quang Ngai and Gia Lai provinces. This will be an important "push" in transport infrastructure, regional connectivity and effective investment attraction in the coming years.

VIÊN NGUYỄN
RELATED NEWS

Quang Ngai focuses on removing obstacles on the Quang Ngai - Hoai Nhon expressway site

|

Quang Ngai - No later than October 15, 2025, the province must hand over the cleared land so that the contractor can speed up the construction of the Quang Ngai - Hoai Nhon expressway.

3,000 workers work through the September 2 Ceremony for the progress of the Quang Ngai - Hoai Nhon Expressway project

|

Whether it is a normal day or a holiday or Tet holiday, for more than 2 years, thousands of workers, engineers... have been working tirelessly at the Quang Ngai - Hoai Nhon expressway construction site, determined to complete the project on schedule by the end of 2025.

The third largest mountain tunnel in the country on the Quang Ngai - Hoai Nhon expressway has been dug

|

tunnel No. 3, part of the Quang Ngai - Hoai Nhon expressway component project, has been dug. When completed, this will be the third largest mountain tunnel in the country.

20h News: Revealing the assets seized in the Shark Binh-related case

|

20h News: Revealing the assets seized in the Shark Binh case; Complete the construction of 30km of the Long Thanh airport boundary fence before December 19...

A lifetime of passion for you and the fierce competition between AI and humans

|

Nguyen Vu and AI sang "Say a lifetime for you", trying to put it on the " balance" to see which song made the audience more excited.

Two-tire car explodes but still drives in the wrong direction in Hanoi, people shout to stop

|

Hanoi - A car had 2 tires exploded on the right and was traveling in the wrong direction, the driver showed unusual signs.

Gold price increases, buyers earn nearly 10 million VND/tael after two weeks

|

Gold prices are recording a strong increase in both domestic and international markets. Investors made a profit of up to 9.9 million VND/tael after a week of paying.

Scams warnings from Cambodia - no easing of thousands of USD salary

|

A Korean monk working as a rescue worker in Sihanoukville has warned about scams going to Cambodia to find light, high-paying jobs.

Quang Ngai focuses on removing obstacles on the Quang Ngai - Hoai Nhon expressway site

VIÊN NGUYỄN |

Quang Ngai - No later than October 15, 2025, the province must hand over the cleared land so that the contractor can speed up the construction of the Quang Ngai - Hoai Nhon expressway.

3,000 workers work through the September 2 Ceremony for the progress of the Quang Ngai - Hoai Nhon Expressway project

Viên Nguyễn |

Whether it is a normal day or a holiday or Tet holiday, for more than 2 years, thousands of workers, engineers... have been working tirelessly at the Quang Ngai - Hoai Nhon expressway construction site, determined to complete the project on schedule by the end of 2025.

The third largest mountain tunnel in the country on the Quang Ngai - Hoai Nhon expressway has been dug

VIÊN NGUYỄN |

tunnel No. 3, part of the Quang Ngai - Hoai Nhon expressway component project, has been dug. When completed, this will be the third largest mountain tunnel in the country.