Quang Ngai - Hoai Nhon expressway and more than 1,000 days of lightning speed construction

Viên Nguyễn |

After more than 1,000 days of lightning-fast construction with the spirit of "making days is not enough, taking advantage of nights", the Quang Ngai - Hoai Nhon expressway has reached the finish line 8 months earlier than planned.

Opening roads on cliffs

In the midst of the last days of 2025, when the Central region is bustlingly preparing for the early Tet, the Quang Ngai - Hoai Nhon expressway is also entering its final stages of completion. From the mountain peaks bordering Quang Ngai - Gia Lai, calls urging work echo like the drumbeat of more than 1,000 days and nights of uninterrupted work.

Few people thought that after only three seasons of rain and storms, an 88 km long highway with three tunnels with a total length of over 4.5km could be completed sooner by more than 8 months. But that seemingly impossible thing came true on December 19, 2025 - the moment the project officially inaugurated and opened to traffic throughout the route.

Right from the start of construction in early January 2023, the Prime Minister clearly directed: Open to where, do to where, absolutely do not let congestion or overlap of procedures. That order became a "guide" for contractors to manage progress day by day, hour by hour.

The first construction teams weave into the rugged rocky mountains, where many sections have never had footprints of heavy machinery. In temporary camps set up on the mountainside, workers of Deo Ca Group recounted that in peak months they almost "live in tunnels", facing many dangers. Mr. Tran Hai Au - worker of XL2 package recounted: "On days of torrential rain, water rushes down white. No one tells anyone, just gather them together and do it. One hour late is a chain of delays.

At tunnel number 3 - the "heart" of the project - construction conditions are even harsher. The tunnel is more than 3,200m long, the largest of the entire North-South expressway in the 2021-2025 period, at times more than 500 engineers and workers are divided into 3 shifts for 24 hours. "We dig mountains with all our strength and pride. Each meter of tunnel is a milestone of perseverance" - Mr. Nguyen Tien Thanh - Commander of tunnel number 3 shared.

In mid-December 2025, when reporters were present at the construction site, the bustling atmosphere was evident on every face. More than 80/88km of road surface had been paved with asphalt; 60 bridges were completed simultaneously. Construction teams focused on intersections, service roads and traffic safety systems. Inside the tunnel, electrical engineer Nguyen Huu Thang and the technical team were busy checking the fan system, lighting, cameras, loudspeakers and fire prevention and fighting. “Looking at the tunnel brightly lit, the systems operating smoothly, we felt like we were relieving a mountain of pressure” - Mr. Thang said.

Outside, the construction teams are paving asphalt, painting roads, installing railings, signs... The sound of machinery resonates endlessly, harmonizing with the calls of workers to create a passionate construction music.

Hinh hai cao toc Quang Ngai - Hoai Nhon sau gan 3 nam thi cong. Anh: VIEN NGUYEN
Form of Quang Ngai - Hoai Nhon expressway after nearly 3 years of construction. Photo: VIEN NGUYEN

1,000 fast days

According to the contract, the project is expected to be completed in August 2026. But with the determination of Project Management Board 2 and the efforts of the contractor consortium led by Deo Ca Group, the progress has been dramatically shortened. Each item is divided into smaller items, deployed in parallel – "tunnel for tunnel, bridge for bridge, road for road" – drastically reducing waiting time.

Mr. Tran Dai Xuan - Deputy Director of the Project Management Board - affirmed: "Not luck. This is the result of scientific construction organization and the extremely high sense of responsibility of the entire force.

On December 19, 2025, the Quang Ngai - Hoai Nhon expressway officially reached the finish line, exceeding the plan by more than 8 months - one of the rare progress records of the transportation industry. With a total investment of more than 20,400 billion VND, the expressway passes through Quang Ngai and Gia Lai, opening a new connecting axis between the Central - Central Highlands regions, designed with 4 lanes, operating speed of 80km/h.

The appearance of this route significantly reduces the load on National Highway 1 - which has been overloaded for many years - and at the same time creates a new "bloodline" for transportation for the regional economy. The expressway helps shorten transportation time between Dung Quat seaport, central industrial parks to the Central Highlands, creating a strong boost for logistics and trade.

On the opening day, many workers stood silently watching the first stream of vehicles passing through the tunnel. No one said anything, but in their eyes pride shone. More than 1,000 days - not long compared to the decades of life of the expressway - but it was a time of hardship, of the spirit of "working daytime is not enough - taking advantage of nighttime", of hasty meals by the drilling machine, and sleepless nights in the mountain shelter.

Now, on the cliffs that were once dug deep, a modern road has opened, connecting lands, connecting even dreams. The Quang Ngai - Hoai Nhon expressway has been completed and its story will be repeated as evidence of the aspiration to rise of thousands of people who have created a straight road in the sunny and windy Central region.

Viên Nguyễn
RELATED NEWS

In the middle of the night, the Quang Ngai - Hoai Nhon expressway construction site is still bustling with the sound of machinery

|

Under the lights, thousands of workers are working on the Quang Ngai - Hoai Nhon expressway, racing against time to complete the project by the end of 2025.

Quang Ngai - Hoai Nhon Expressway accelerates, ready to open to traffic by the end of 2025

|

The Quang Ngai - Hoai Nhon expressway project has 6 months left to open to traffic. The contractor is speeding up the progress, ensuring the project is completed on time.

Stocks aim for the 2,000-point mark in 2026

|

2025 marks the most vibrant growth year in history, making Vietnam one of the most efficient stock markets in the world.

President Putin, Zelensky and world leaders congratulate New Year

|

In the moment of transition to the new year, many world leaders, including President Putin and Zelensky, sent congratulatory messages to the people.

Night literacy class for people in Vietnam - Laos border areas

|

Quang Tri - In the border area of Lia commune, literacy classes at night open up opportunities to change the lives of ethnic minorities.

Bustling buying and selling at Cua Sot Fishing Port on New Year's Day

|

Ha Tinh - On the first day of the new year 2026, at Cua Sot fishing port, before dawn, it was already bustling with buyers and sellers.

Ngoc Viet cancels shows, question marks about the responsibility of artists

|

At the investigating agency, Ngoc Viet Education Director Nguyen Thi Thu Ha testified that the biggest mistake was not being able to implement the payment schedule with the artist.

The State Treasury no longer collects budget revenue in cash from 2026

|

From 2026, the State Treasury will stop cash budget revenue collection to increase transparency and modernize financial management.

In the middle of the night, the Quang Ngai - Hoai Nhon expressway construction site is still bustling with the sound of machinery

VIÊN NGUYỄN |

Under the lights, thousands of workers are working on the Quang Ngai - Hoai Nhon expressway, racing against time to complete the project by the end of 2025.

Quang Ngai - Hoai Nhon Expressway accelerates, ready to open to traffic by the end of 2025

VIÊN NGUYỄN |

The Quang Ngai - Hoai Nhon expressway project has 6 months left to open to traffic. The contractor is speeding up the progress, ensuring the project is completed on time.

Làm chủ công nghệ xây hầm cao tốc Quảng Ngãi – Hoài Nhơn

VIÊN NGUYỄN |

Đơn vị thi công cao tốc Quảng Ngãi – Hoài Nhơn đã cải tiến công nghệ thi công hầm nhằm rút ngắn tiến độ hoàn thành.