Upgrading the roof of a series of wooden stilt houses in flood-affected resettlement areas

THANH TUẤN |

Gia Lai - In the flood-affected resettlement area, a series of stilt houses have been raised, and workers are constructing the roof.

On August 10, Ia Tul Commune People's Committee, Gia Lai came to the scene to supervise and inspect the construction progress of the resettlement area project for people in disaster-stricken and flooded areas.

At the scene, dozens of skilled workers are constructing the roof. The solid wooden frame has been basically completed.

All stilt houses are made of wood by contractors, many wooden trees with diameters from 20-40cm are used to erect pillars, beams, and roofs, suitable for the traditional stilt house characteristics of the people.

Mr. Pham Van Duc - Chairman of Ia Tul Commune People's Committee - said: The commune is determined to start construction of all houses before August 31st, complete house handover before November 2nd to bring 207 households to new residences before floods occur in the area, avoiding the risk of affecting people's lives.

In which, 55 poor and near-poor households were supported to build new stilt houses with a cost of 220 million VND/unit, ensuring both adaptation to floods and suitability with customs and culture.

Các nhân công lành nghề thi công phần mái nhà. Ảnh: Thanh Tuấn
Skilled workers construct the roof. Photo: Thanh Tuan

Vice Chairman of Gia Lai Provincial People's Committee Duong Mah Tiep requested the Provincial Construction Investment Project Management Board and contractors to focus manpower and machinery, and accelerate the progress of essential items in the project area such as halls, transport infrastructure, drainage, electricity systems...

In addition, land allocation and support must be public and transparent, prioritizing poor households and households unable to build themselves so that people can soon stabilize their lives.

In 2025, Gia Lai province suffered two serious natural disasters including storm No. 13 (Kalmaegi) and heavy rain and floods in November. The whole province has many residential areas deeply flooded; more than 57,000 houses flooded; 28,196 houses collapsed, fallen, swept away or heavily damaged, requiring urgent construction and repair.

Total estimated damage is over 11,500 billion VND, of which storm No. 13 caused damage of over 10,000 billion VND, and the flood caused damage of about 1,500 billion VND.

THANH TUẤN
RELATED NEWS

Lighting up hope in the flood-stricken area of Muong Than

|

Lai Chau - Muong Than people are gradually overcoming losses, igniting hope to rebuild their lives from the joint efforts of the government and the community.

New roofs open a way to settle down for people in flood-affected Muong Than areas

|

Lai Chau - New roofs are being built every day in the resettlement area in Muong Than commune, helping people in flood-affected areas soon stabilize their lives.

Two Hanoi Medical University students disciplined after making statements about patients on TikTok

|

Two students of Hanoi Medical University were disciplined and dismissed from the position of deputy class monitor for inappropriate statements about patients on social networks.

Verifying clip of a girl sitting close to the railway track, her phone thrown off by a train in Hanoi

|

Hanoi - Functional forces are verifying a clip of a girl sitting close to the track turning a train, causing her phone to be hit by a train and thrown away while passing by.

State Bank of Vietnam proposes banks to reduce lending interest rates

|

The SBV proposes that banks implement preferential credit packages, at least 1%/year lower than the average lending interest rate for the same term.

Rescue of 6 people trapped between two landslide points after heavy rain in Lao Cai

|

Lao Cai - While traveling through the IC15 expressway connection, 6 people were suddenly trapped due to landslides occurring at both ends of the route, unable to continue moving.

Be stricter with workers who violate the law when working abroad

|

National Assembly deputies believe that the situation of workers absconding when working abroad negatively affects the national image.

Đẩy nhanh tái định cư để ổn định cho người dân vùng lũ Gia Lai

THANH TUẤN |

Gia Lai - Các khu tái định cư trên nền đất chắc chắn đang được đẩy nhanh tiến độ thi công để sớm đưa hàng nghìn hộ dân đến nơi ở mới an toàn.

Lighting up hope in the flood-stricken area of Muong Than

Đinh Đại |

Lai Chau - Muong Than people are gradually overcoming losses, igniting hope to rebuild their lives from the joint efforts of the government and the community.

New roofs open a way to settle down for people in flood-affected Muong Than areas

Đinh Đại |

Lai Chau - New roofs are being built every day in the resettlement area in Muong Than commune, helping people in flood-affected areas soon stabilize their lives.