Ha Tinh - The Ha Tinh Department of Construction has just issued a document appointing the unit to organize an inspection to clarify the cause of the damage to a series of Hong Lam Xuan Thanh villas after storm No. 10.

Accordingly, on November 5, the Ha Tinh Department of Construction issued a document assigning the Ha Tinh Construction Quality Inspection Center to conduct a quality assessment to serve the assessment of the cause of the incident for collapsed and damaged works under the Xuan Thanh Service and Housing Project.

The subjects of appraisal are 23 beach villas with partially collapsed works and works that were severely damaged (the foundation, floor was exposed to frog's jaw); swimming pool, damaged fence; sea embankment. If necessary, inspections and assessments of other works can be conducted to clarify related issues.

Scope of appraisal: Check and evaluate the application of standards and regulations in the design documents compared to current regulations; check the quality management process during the construction process and assess the quality of damaged and collapsed components; other contents that cause construction incidents.

The Ha Tinh Department of Construction also assigned the Center for Construction Quality Inspection to prepare an inspection outline for the subjects and scope of inspection to submit to the Incident Investigation Team for consideration and approval before November 7.

Implement according to the approved Inspection Outline to determine the cause of the incident; assess the safety level of the works after the incident, propose solutions and conditions that investors must meet to be allowed to thoroughly handle the damage to ensure the legitimate rights of the parties involved.

Synthesize and report to the Investigation Team on the results of determining the cause of the incident; coordinate with the Investigation Team to determine the responsibility of the organization and individual causing the construction incident.

Time to complete the appraisal work: according to the appraisal plan for the cause of the incident approved by the Investigation Team and not exceeding 30 days (from the date of signing the contract).

Sau khi nhieu biet thu bi song danh hong, chu dau tu da dung nhieu bao tai cat lam ke tam che chan. Anh: Tran Tuan.
After many villas were damaged by waves, the investor used many sandbags as temporary embankments to cover them. Photo: Tran Tuan

Request Hong Lam Xuan Thanh Joint Stock Company (investor) to organize the signing of a contract with the Ha Tinh Construction Quality Inspection Center on the basis of the approved inspection plan.

Providing complete records, documents, and relevant technical data to serve the assessment of the cause of the incident and creating conditions for the incident investigation team and the inspection organization to access the scene.

After having the results of the appraisal of the cause of the construction incident and determining the responsibility, the organization or individual causing the construction incident must be responsible for paying the cost of organizing the appraisal of the cause of the incident.

Previously, Lao Dong Newspaper had many articles reflecting many villas in Xuan Thanh Service and Housing Area (also known as Hoa Tien Xuan Thanh Resort) in Tien Dien Commune that were collapsed and severely damaged in storm No. 10.

It is worth mentioning that there are signs that the project has not yet implemented a sea dyke to block waves in front of these coastal villas, in addition, the structure of the villas is quite simple, making it difficult to withstand big storms.

TRẦN TUẤN
RELATED NEWS

Suspicion of a villa area severely damaged after a storm in Ha Tinh has not yet built a sea embankment according to the design

|

Ha Tinh - In the construction permit issued by the Ha Tinh Department of Construction, at Hoa Tien Xuan Thanh Resort, there is a 850m long sea embankment.

Urgently reinforce the row of villas that were destroyed by waves in Ha Tinh

|

Ha Tinh - After storm No. 10, investor Hoa Tien Xuan Thanh resort is mobilizing human resources and machinery to temporarily build sand gates to block waves and reinforce the foundations of damaged villas.

Press agencies need to innovate methods and methods of operating newspapers and magazines according to the new model

|

On the afternoon of November 6, the Party Committee of the Vietnam Fatherland Front and Central organizations held a press conference in November 2025, collecting opinions on draft documents submitted to the 14th National Party Congress.

Storm No. 13 Kalmaegi with gusts of level 16 is about to make landfall, is on the coast of Dak Lak-Gia Lai

|

Typhoon No. 13 Kalmaegi is about to make landfall. Forecast for the area near the storm center to pass in the east of Quang Ngai - Gia Lai provinces, the north of Dak Lak has strong winds of level 10-12, gusts of level 15.

Officials working abroad and integrating regularly internationally will be supported with 100% of their salary

|

The Government proposes that people working in foreign affairs and international integration who are regularly supported with 100% of their salary according to the current coefficient (excluding allowances).

Announcement of the 14th Conference of the 13th Party Central Committee

|

Implementing the full-term Working Program, from November 5, 2025 to November 6, 2025, in Hanoi, the 13th Party Central Committee held its 14th Conference to discuss and give opinions on the work of the 14th National Party Congress; Party building work and the political system; personnel work and a number of other important contents. General Secretary To Lam delivered the opening and closing speeches at the Conference.

Dak Lak bans people from going out in storm-affected areas from the afternoon of November 6

|

Dak Lak requires the ban on all people in areas affected by the storm until the storm passes, except for functional forces on duty.

Hundreds of officers and soldiers urgently reinforce Hoi An coast before storm No. 13

|

Da Nang - Hundreds of officers and soldiers of the Da Nang City Military Command urgently reinforced the Hoi An coast before Typhoon 13 made landfall.

Bộ Xây dựng chỉ đạo giám định nguyên nhân biệt thự đổ sập ở Hà Tĩnh

TRẦN TUẤN |

Bộ Xây dựng vừa yêu cầu giám định nguyên nhân và xử lý trách nhiệm liên quan đến loạt biệt thự Hoa Tiên Xuân Thành ở Hà Tĩnh đổ, hư hỏng sau bão số 10.

Suspicion of a villa area severely damaged after a storm in Ha Tinh has not yet built a sea embankment according to the design

TRẦN TUẤN |

Ha Tinh - In the construction permit issued by the Ha Tinh Department of Construction, at Hoa Tien Xuan Thanh Resort, there is a 850m long sea embankment.

Urgently reinforce the row of villas that were destroyed by waves in Ha Tinh

TRẦN TUẤN - NGUYỄN LUÂN |

Ha Tinh - After storm No. 10, investor Hoa Tien Xuan Thanh resort is mobilizing human resources and machinery to temporarily build sand gates to block waves and reinforce the foundations of damaged villas.