Appointing a unit to inspect a series of damaged villas in Ha Tinh

TRẦN TUẤN |

Ha Tinh - The Ha Tinh Department of Construction has just issued a document appointing the unit to organize an inspection to clarify the cause of the damage to a series of Hong Lam Xuan Thanh villas after storm No. 10.

Accordingly, on November 5, the Ha Tinh Department of Construction issued a document assigning the Ha Tinh Construction Quality Inspection Center to conduct a quality assessment to serve the assessment of the cause of the incident for collapsed and damaged works under the Xuan Thanh Service and Housing Project.

The subjects of appraisal are 23 beach villas with partially collapsed works and works that were severely damaged (the foundation, floor was exposed to frog's jaw); swimming pool, damaged fence; sea embankment. If necessary, inspections and assessments of other works can be conducted to clarify related issues.

Scope of appraisal: Check and evaluate the application of standards and regulations in the design documents compared to current regulations; check the quality management process during the construction process and assess the quality of damaged and collapsed components; other contents that cause construction incidents.

The Ha Tinh Department of Construction also assigned the Center for Construction Quality Inspection to prepare an inspection outline for the subjects and scope of inspection to submit to the Incident Investigation Team for consideration and approval before November 7.

Implement according to the approved Inspection Outline to determine the cause of the incident; assess the safety level of the works after the incident, propose solutions and conditions that investors must meet to be allowed to thoroughly handle the damage to ensure the legitimate rights of the parties involved.

Synthesize and report to the Investigation Team on the results of determining the cause of the incident; coordinate with the Investigation Team to determine the responsibility of the organization and individual causing the construction incident.

Time to complete the appraisal work: according to the appraisal plan for the cause of the incident approved by the Investigation Team and not exceeding 30 days (from the date of signing the contract).

Sau khi nhieu biet thu bi song danh hong, chu dau tu da dung nhieu bao tai cat lam ke tam che chan. Anh: Tran Tuan.
After many villas were damaged by waves, the investor used many sandbags as temporary embankments to cover them. Photo: Tran Tuan

Request Hong Lam Xuan Thanh Joint Stock Company (investor) to organize the signing of a contract with the Ha Tinh Construction Quality Inspection Center on the basis of the approved inspection plan.

Providing complete records, documents, and relevant technical data to serve the assessment of the cause of the incident and creating conditions for the incident investigation team and the inspection organization to access the scene.

After having the results of the appraisal of the cause of the construction incident and determining the responsibility, the organization or individual causing the construction incident must be responsible for paying the cost of organizing the appraisal of the cause of the incident.

Previously, Lao Dong Newspaper had many articles reflecting many villas in Xuan Thanh Service and Housing Area (also known as Hoa Tien Xuan Thanh Resort) in Tien Dien Commune that were collapsed and severely damaged in storm No. 10.

It is worth mentioning that there are signs that the project has not yet implemented a sea dyke to block waves in front of these coastal villas, in addition, the structure of the villas is quite simple, making it difficult to withstand big storms.

TRẦN TUẤN
RELATED NEWS

Suspicion of a villa area severely damaged after a storm in Ha Tinh has not yet built a sea embankment according to the design

|

Ha Tinh - In the construction permit issued by the Ha Tinh Department of Construction, at Hoa Tien Xuan Thanh Resort, there is a 850m long sea embankment.

Urgently reinforce the row of villas that were destroyed by waves in Ha Tinh

|

Ha Tinh - After storm No. 10, investor Hoa Tien Xuan Thanh resort is mobilizing human resources and machinery to temporarily build sand gates to block waves and reinforce the foundations of damaged villas.

Land acquisition of nearly 1,500 households in Ho Chi Minh City to build the largest road in the Southeast region

|

Ho Chi Minh City recovers land from about 1,500 households in Tan An Hoi and Nhuan Duc communes to build the Ho Chi Minh City Ring Road 4 project (section from Saigon River to Thay Cai canal).

Before welcoming thunderstorms to cool down, hot weather developments are forecast

|

According to the meteorological agency, forecasts before thunderstorms, today April 16, the Northwest and Central regions will continue to be hot.

Ha Anh Tuan participates in Sao Nhap Ngu concert with Hoa Minzy, Chi Pu

|

Sao Nhap Ngu concert 2026 - Tuoi Doi Muoi" quickly became the focus of attention when announcing the cast of participating artists, including the appearance of Ha Anh Tuan.

Early ripe Son La plums priced at up to 120 thousand VND still attract customers

|

Son La - Early ripe plums are a bumper crop, beautiful fruit, high prices, farmers are excited, traders come to the garden to buy, and the consumption market is vibrant.

Collecting people's opinions on the draft Political Report at the XI National Congress of the Vietnam Fatherland Front

|

The 11th National Congress of the Vietnam Fatherland Front, term 2026 - 2031 will take place from May 11-13 in Hanoi Capital. This is an important socio-political event taking place immediately after the success of the 14th National Congress of the Party and the election of National Assembly deputies of the 16th term, People's Councils at all levels for the term 2026 - 2031.

Trade union news: Adjusting the payment schedule for pensions and social insurance allowances in May 2026 in Hanoi

|

Trade union news bulletin includes: Adjusting the payment schedule for pensions and social insurance allowances in May 2026; Prices increase, Quang Tri workers struggle to manage spending...

Bộ Xây dựng chỉ đạo giám định nguyên nhân biệt thự đổ sập ở Hà Tĩnh

TRẦN TUẤN |

Bộ Xây dựng vừa yêu cầu giám định nguyên nhân và xử lý trách nhiệm liên quan đến loạt biệt thự Hoa Tiên Xuân Thành ở Hà Tĩnh đổ, hư hỏng sau bão số 10.

Suspicion of a villa area severely damaged after a storm in Ha Tinh has not yet built a sea embankment according to the design

TRẦN TUẤN |

Ha Tinh - In the construction permit issued by the Ha Tinh Department of Construction, at Hoa Tien Xuan Thanh Resort, there is a 850m long sea embankment.

Urgently reinforce the row of villas that were destroyed by waves in Ha Tinh

TRẦN TUẤN - NGUYỄN LUÂN |

Ha Tinh - After storm No. 10, investor Hoa Tien Xuan Thanh resort is mobilizing human resources and machinery to temporarily build sand gates to block waves and reinforce the foundations of damaged villas.